Unexcused Scheduled Maintenance Outages. In the event Seller desires to take a Unit out of service in a manner that would be recognized by the CAISO as a planned outage but does not otherwise comply with the timelines set forth in Sections 3.10(b) through 3.10(f) to be deemed an Excused Scheduled Maintenance Outage, Seller shall notify Buyer of its proposed Maintenance Outage schedule for the Unit(s) by submitting Notice to Buyer in accordance with PG&E’s Outage Reporting Protocols as promptly as possible upon determining the need for such maintenance. Buyer, as the SC, shall submit the proposed Maintenance Outages for the Unit(s) to the CAISO in the form proposed by Seller which will be subject to CAISO approval. If such requested Outage is approved by CAISO, it will then be deemed by Buyer to be an Unexcused Scheduled Maintenance Outage, and Seller shall adhere to the Outage schedule approved by the CAISO for that Outage. At any time, Buyer may request that Seller re-schedule its Unexcused Scheduled Maintenance Outage, in which case Seller shall notify Buyer of any incremental costs associated with the schedule change and an alternative schedule change, if any, that would entail lower incremental costs. If Buyer’s proposed change to Seller’s Unexcused Scheduled Maintenance Outage Schedule is feasible and imposes no incremental costs (as compared to Seller’s proposed schedule) or if Buyer agrees to pay the incremental costs, Seller shall use commercially reasonable efforts to accommodate Buyer’s request and Buyer, as the SC, shall communicate the change to the CAISO and seek CAISO approval for the revised Unexcused Scheduled Maintenance Outage. However, unless it is transmitting to Seller a CAISO order, Buyer may not change Seller’s Unexcused Scheduled Maintenance Outage schedule unilaterally.
AutoNDA by SimpleDocs

Related to Unexcused Scheduled Maintenance Outages

  • Maintenance Outages If Seller reasonably determines that it is necessary to schedule a Maintenance Outage, Seller shall notify Buyer of the proposed Maintenance Outage at least five (5) days before the outage begins (or such shorter period to which Buyer may reasonably consent in light of then existing conditions). Upon such notice, the Parties shall plan the Maintenance Outage to mutually accommodate the reasonable requirements of Seller and the service obligations of Buyer; provided, however, that, unless Buyer otherwise consents, such consent not to be unreasonably withheld, no Maintenance Outage may be scheduled between the hour ending 0700 through the hour ending 2200, Monday through Saturday, during the time period commencing on May 15 and concluding on September 15. Notice of a proposed Maintenance Outage shall include the expected start date and time of the outage, the amount of Capacity of the Facility that will not be available, and the expected completion date and time of the outage. Seller shall give Buyer notice of the Maintenance Outage as soon as Seller determines that the Maintenance Outage is necessary. Buyer shall promptly respond to such notice and may request reasonable modifications in the schedule for the outage. Seller shall use all reasonable efforts to comply with any request to modify the schedule for a Maintenance Outage. Seller shall notify Buyer of any subsequent changes in Capacity available to Buyer or any changes in the Maintenance Outage completion date and time. As soon as practicable, any notifications given orally shall be confirmed in writing. Seller shall take all reasonable measures and exercise its best efforts in accordance with Prudent Electrical Practices to minimize the frequency and duration of Maintenance Outages.

  • Unscheduled Maintenance Unscheduled maintenance may be required to resolve issues that are critical for Customer and/or performance of the Cloud Services. Druva will use its commercially reasonable efforts to notify Customer at least six (6) hours prior to the unscheduled maintenance.

  • Scheduled Maintenance Maintenance window for disruptive work to Service will be limited 12:00 A.M. to 4:00 A.M., Central Daylight Time (CDT), any day with requirement of one (1) calendar week notification to Customer prior to maintenance. LightEdge will send an e-mail notification of such disruptive maintenance to Service to Authorized Contacts of Customer. Once notification is sent to Customer this will be considered a “Scheduled Maintenance”. Any Service SLAs will NOT apply during a Scheduled Maintenance.

  • Scheduled Outages (1) No later than five (5) Business Days prior to the dates required by the ISO for delivery of schedules for planned outages (which such ISO required delivery dates are currently January 15th, April 15th, July 15th and October 15th of each calendar year during the Facility Term), and at least sixty (60) days prior to the later of: (A) Initial Synchronization, or (B) SCE becoming Seller’s Scheduling Coordinator, Seller shall submit to SCE its schedule of proposed planned outages (“Outage Schedule”) for the subsequent twenty four-month period using the Web Client. If Seller fails to submit an Outage Schedule for any period as required under this Section 3.19, then Seller shall not be permitted to schedule or have any planned outages with respect to such period. The foregoing shall not prevent Seller from modifying its Outage Schedule in cooperation with SCE and the ISO. SCE shall provide Notice to Seller in the event that the ISO changes the ISO required delivery dates for schedules for planned outages. In addition, no later than thirty (30) days prior to October 15 of each year, Seller shall submit to SCE its estimate of its planned outages for the following year. (2) Seller shall provide the following information for each proposed planned outage: (A) Start date and time; (B) End date and time; and (C) Capacity expected to be online, in MW, during the planned outage. (3) Within twenty (20) Business Days after SCE’s receipt of an Outage Schedule, SCE shall notify Seller in writing of any reasonable request for changes to the Outage Schedule, and Seller shall, consistent with Prudent Electrical Practices and as permitted by the ISO, accommodate SCE’s requests regarding the timing of any planned outage. (4) Seller shall cooperate with SCE to arrange and coordinate all Outage Schedules with the ISO. (5) In the event a condition occurs at the Generating Facility which causes Seller to revise its planned outages, Seller shall provide Notice to SCE, using the Web Client, of such change (including an estimate of the length of such planned outage) as soon as practicable after the condition causing the change becomes known to Seller. (6) Seller shall promptly prepare and provide to SCE upon request, using the Web Client, all reports of actual or forecasted outages that SCE may reasonably require for the purpose of enabling SCE to comply with Section 761.3 of the California Public Utilities Code or any Applicable Law mandating the reporting by investor owned utilities of expected or experienced outages by electric energy generating facilities under contract to supply electric energy.

  • Line Outage Costs Notwithstanding anything in the NYISO OATT to the contrary, the Connecting Transmission Owner may propose to recover line outage costs associated with the installation of Connecting Transmission Owner’s Attachment Facilities or System Upgrade Facilities or System Deliverability Upgrades on a case-by-case basis.

  • Scheduled Downtime For the purposes of this Agreement, Scheduled Downtime will mean those hours, as determined by us but which will not occur between the hours of 9:00 AM and 5:00 PM Eastern Time, Monday through Friday without your authorization or unless exigent circumstances exist, during which time we will perform scheduled maintenance or adjustments to the Environment. We will use our best efforts to provide you with at least twenty-four (24) hours of notice prior to scheduling Scheduled Downtime.

  • Service Outages (a) Service Outages Due to Power Failure or Disruption. 911 Dialing does not function in the event of a power failure or disruption. If there is an interruption in the power supply, the Service, including 911 Dialing, will not function until power is restored. Following a power failure or disruption, you may need to reset or reconfigure the Device prior to utilizing the Service, including 911 Dialing. (b) Service Outages Due to Internet Outage or Suspension or Termination of Broadband Service or ISP Service. Service outages or suspensions or terminations of service by your broadband provider or ISP will prevent all Service, including 911 Dialing, from functioning. (c) Service Outage Due to Suspension or Termination of Your Citi-Tel Account. Service outages due to suspension or termination of your account will prevent all Service, including 911 Dialing, from functioning. (d) Service Outages Due to ISP or Broadband Provider Blocking of Ports or Other Acts. Your ISP or broadband provider or other third party may intentionally or inadvertently block the ports over which the Service is provided or otherwise impede the usage of the Service. In that event, provided that you alert us to this situation, we will attempt to work with you to resolve the issue. During the period that the ports are being blocked or your Service is impeded, and unless and until the blocking or impediment is removed or the blocking or impediment is otherwise resolved, your Service, including the 911 Dialing feature, may not function. You acknowledge that Citi-Tel is not responsible for the blocking of ports by your ISP or broadband provider or any other impediment to your usage of the Service, and any loss of service, including 911 Dialing, that may result. In the event you lose service as a result of blocking of ports or any other impediment to your usage of the Service, you will continue to be responsible for payment of the Service charges unless and until you terminate the Service in accordance with this Agreement.

  • Outages and Maintenance In the event that a Registry Operator plans maintenance, it will provide notice to the ICANN emergency operations department, at least, twenty-four (24) hours ahead of that maintenance. ICANN’s emergency operations department will note planned maintenance times, and suspend Emergency Escalation services for the monitored services during the expected maintenance outage period. If Registry Operator declares an outage, as per its contractual obligations with ICANN, on services under a service level agreement and performance requirements, it will notify the ICANN emergency operations department. During that declared outage, ICANN’s emergency operations department will note and suspend emergency escalation services for the monitored services involved.

  • Planned Maintenance (a) Subject to any modification or amendment of this Agreement made pursuant to Section 4.2(c) or Section 7.3(d), Planned Maintenance occurring during the Delivery Term shall be coordinated and scheduled in accordance with this Section 9.6. Seller shall perform all Planned Maintenance (including Major Planned Maintenance) in a manner that optimizes the generation and benefits to Buyer of the Contract Energy, Storage Energy, and other Products (e.g., during off-peak periods and low-irradiance periods) and, without limiting the foregoing, either (i) outside of Daylight Hours or (ii) during the months of October and November only, during Daylight Hours; provided, however, that the foregoing restrictions shall not apply to any Planned Maintenance that Seller is required to perform pursuant to any applicable manufacturer warranty that cannot reasonably be performed by Seller subject to such restrictions. (b) Seller shall deliver to Buyer a proposed schedule for Planned Maintenance in respect of each Contract Year (“Planned Maintenance Schedule”) no later than ninety (90) Days before the start of such Contract Year. Planned Maintenance Schedules submitted by Seller shall (i) comply with the second sentence of Section 9.6(a) and (ii) include reasonably detailed descriptions of the Planned Maintenance to be performed, the Days and times in which each type of Planned Maintenance is scheduled to be performed, the estimated amount(s) of Contract Capacity and Storage Capacity that will be unavailable due to Planned Maintenance and the total number of hours that Seller expects that the Contract Capacity and Storage Capacity will be unavailable due to Planned Maintenance. The general form for the Planned Maintenance Schedule is set forth in Schedule 9.6. (The Planned Maintenance descriptions reflected in the general form set forth in Schedule 9.6 are provided for indicative purposes only, and are not necessarily representative of the detail, time periods, or certainty required for a Planned Maintenance Schedule hereunder.) (c) Buyer shall have the right to disapprove, in its reasonable discretion (provided that Buyer shall have the right to disapprove, in its sole and absolute discretion, any Planned Maintenance proposed by Seller that is inconsistent with the terms of this Agreement), any Planned Maintenance set out in any Planned Maintenance Schedule proposed by Seller for any Contract Year, except for any Planned Maintenance that (i) is scheduled to occur outside of Daylight Hours or during Daylight Hours during the months of October and November or (ii) Seller is required to perform pursuant to any applicable manufacturer warranty and that is scheduled to occur in compliance with Section 9.6(a). If Seller submits its Planned Maintenance Schedule for a Contract Year in accordance with the requirements of this Agreement and Buyer does not disapprove of any Planned Maintenance set out in such Planned Maintenance Schedule by sixty (60) days after submission, then such Planned Maintenance Schedule shall be deemed approved. If Buyer, in the exercise of its discretion as set forth above, disapproves any Planned Maintenance in such Planned Maintenance Schedule within the applicable time period specified above after its submission, Buyer shall notify Seller and the Parties shall use Commercially Reasonable Efforts to agree upon and finalize a mutually acceptable Planned Maintenance Schedule for the applicable Contract Year. Seller shall conduct Planned Maintenance during such Contract Year only in accordance with an agreed Planned Maintenance Schedule; provided, however, that Seller may (A) move Planned Maintenance included in an agreed Planned Maintenance Schedule that is not Major Planned Maintenance, so long as such move is consistent with the terms of this Agreement (including the second sentence of Section 9.6(a)) or, with respect to Major Planned Maintenance, if such Major Planned Maintenance is scheduled to occur outside of Daylight Hours or during Daylight Hours during the months of October and November and (B) schedule and perform Planned Maintenance not reflected in the Planned Maintenance Schedule so long as such Planned Maintenance is scheduled to be performed outside of Daylight Hours or during Daylight Hours during the months of October and November and Seller provides Buyer at least two (2) weeks’ prior written notice of such Planned Maintenance; provided further that Buyer shall have the right to advise Seller of periods when Buyer prefers, based on solar irradiance, supply, market and other conditions, that any Major Planned Maintenance be deferred, and Seller shall use Commercially Reasonable Efforts to comply with such request. (d) Seller shall use Commercially Reasonable Efforts to complete any Planned Maintenance and place the Facility back into full commercial operation as soon as reasonably possible. If Seller determines that any Planned Maintenance scheduled in an agreed Planned Maintenance Schedule no longer needs to be completed or will not consume the entire time scheduled therefor in the agreed Planned Maintenance Schedule, Seller shall provide (i) a Generation Forecast to Buyer reflecting the forecasted amount of Delivered Energy during each affected interval that takes into account such change and (ii) in the case of any Major Planned Maintenance, a written notice declaring the cessation and termination of the applicable Major Planned Maintenance period (in which event, the Major Planned Maintenance period shall terminate in accordance with the terms of such Generation Forecast and written notice).

  • Forced Outages During any forced outage, the NYISO or Connecting Transmission Owner may suspend interconnection service to the Interconnection Customer to effect immediate repairs on the New York State Transmission System or the Distribution System. The NYISO shall use Reasonable Efforts to provide the Interconnection Customer with prior notice. If prior notice is not given, the NYISO shall, upon request, provide the Interconnection Customer written documentation after the fact explaining the circumstances of the disconnection.