Work Schedule Underway Sample Clauses

Work Schedule Underway. The parties recognize that, as a research institution, it may be necessary to conduct scientific operations around the clock. As such, RFO vessels are subject to sail at most any hour of the night or day to meet the needs of science. The work schedule for crew members when their vessel is underway will be established by the needs of the scientific project using the vessel. The Captain of each vessel will determine departure times and estimated times of arrival back in port, based on a Cruise Plan submitted in advance by the scientist in charge of the cruise. In nonemergency situations, Crewmembers’ work schedules will be assigned by the Captain based on the Cruise Plan and the scientific requirements of the cruise. Crewmembers will be given as much advance notice of the work schedule for each cruise as is reasonably possible. Due to the many variables associated with operating oceanographic research vessels, the work schedule of crew members when the vessel is underway may be subject to change at any time. Inclement weather, equipment failure or other problems may force the cruise to be delayed, or sailing times changed, with little if any, notice.
AutoNDA by SimpleDocs
Work Schedule Underway. 22 The parties recognize that, as a research institution, it may be necessary to conduct 23 scientific operations around the clock. As such, RFO vessels are subject to sail at most 24 any hour of the night or day to meet the needs of science. The work schedule for crew 25 members when their vessel is underway will be established by the needs of the scientific 26 project using the vessel. The Captain of each vessel will determine departure times and 27 estimated times of arrival back in port, based on a Cruise Plan submitted in advance by 28 the scientist in charge of the cruise. In nonemergency situations, Crewmembers’ work 29 schedules will be assigned by the Captain based on the Cruise Plan and the scientific 30 requirements of the cruise. Crewmembers will be given as much advance notice of the 31 work schedule for each cruise as is reasonably possible.

Related to Work Schedule Underway

  • Construction Progress Schedule; Overall Project Schedule The Contractor shall submit for review by the Design Professional and approval by the Owner a Construction Progress Schedule based upon the Design Professional’s Preliminary Design and Construction Schedule and prepared using a CPM (Critical Path Method) process within sixty days after the Effective Date of the Contract, utilizing a full-featured software package in a form satisfactory to the Design Professional and Owner, showing the dates for commencement and completion of the Work required by the Contract Documents, including coordination of mechanical, plumbing, and electrical disciplines, as well as coordination of the various subdivisions of the Work within the Contract. Milestones must be clearly indicated and sequentially organized to identify the critical path of the Project. The Construction Schedule will be developed to represent the CSI specification divisions. It shall have the minimum number of activities required to adequately represent to the Owner the complete scope of Work and define the Project’s (and each Phase’s if phased) critical path and associated activities. The format of the Construction Progress Schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, inspections for Material Completion and Occupancy Date, and Final Completion Date. The Contractor shall submit, along with the Construction Progress Schedule, the Submittal Schedule for approval by the Design Professional, correlating the associated approval dates for the documents with the Construction Progress Schedule. Upon recommendation by the Design Professional and approval by the Owner, the Construction Progress Schedule shall become the Overall Project Schedule, which shall be utilized by the Design Professional, Owner and Contractor. The Contractor must provide the Design Professional and the Owner with monthly updates of the Overall Project Schedule indicating completed activities and any changes in sequencing or activity durations, including approved change orders. See also Article 3.3.5.

  • Work Schedule A 4/10 work schedule is four (4) ten hour days in a seven (7) day period, for a total of forty (40) hours per week.

  • Construction Progress Schedule A schedule indicating proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, preparation, submittal, and processing of Shop Drawings and Samples, delivery of materials or equipment requiring long-lead time procurement, and proposed date(s) of Material Completion and Occupancy and Final Completion. The schedule will be developed to represent the sixteen or seventeen CSI Specification Divisions. It shall have a minimum number of activities as required to adequately represent to Owner the complete scope of work and define the Project’s critical path and associated activities. If the Project is to be phased, then each individual Phase should be identified from start through completion of the overall Project and should be individually scheduled and described, including any Owner’s occupancy requirements and showing portions of the Project having occupancy priority. The format of the schedule will have dependencies indicated on a monthly grid identifying milestone dates such as construction start, phase construction, structural top out, dry-in, rough-in completion, metal stud and drywall completion, equipment installation, systems operational, Material Completion and Occupancy Date, final inspection dates, Punchlist, and Final Completion date.

  • Work Schedule Changes 215. It is agreed that pursuant to the exercise of management rights, normal work schedules may be changed without mutual agreement, subject to compliance with other provisions of this Agreement. However, it is agreed that the effects of consequences of such changes are subject to the meet and confer obligation to the extent required by state law.

  • Fourth Schedule All petroleum as defined in the Xxxxxxxxx Xxx 0000 on or below the surface of the land the subject of this lease is reserved to the Crown in right of the State of Western Australia with the right of the Crown in right of the State of Western Australia and any person lawfully claiming thereunder or otherwise authorised to do so to have access to the land the subject of this lease for the purpose of searching for and for the operations of obtaining petroleum (as so defined) in any part of the land. FIFTH SCHEDULE (Date of commencement of the lease). SIXTH SCHEDULE (Any further conditions or stipulations).

  • Modification of Work Schedule When a change of work schedule is requested by an employee and approved by the Agency, all forms of penalty pay and daily overtime compensation shall be waived by the employee for the requested change in schedule, but not for work over forty (40) hours per week.

  • Work Schedules Workweeks and work shifts of different numbers of hours may be established by the Employer in order to meet business and customer service needs, as long as the work schedules meet federal and state laws.

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Time Schedule 4.1. A project schedule is included in Appendix A.

Time is Money Join Law Insider Premium to draft better contracts faster.