SUPPLY CONTRACT BETWEEN WÄRTSILÄ FINLAND OY AND LIHIR GOLD LIMITED REGARDING SUPPLY AND DELIVERY OF A FLOATING POWER PLANT BARGE AND RELATED SERVICES
Page 2
CLAUSE 1
|
DEFINITIONS AND INTERPRETATION | 5 | ||||
CLAUSE 2
|
SCOPE OF THE CONTRACT | 8 | ||||
CLAUSE 3
|
PRICE | 9 | ||||
CLAUSE 4
|
PAYMENT TERMS | 10 | ||||
CLAUSE 5
|
DELIVERY DATE | 12 | ||||
CLAUSE 6
|
PRE-COMMISSIONING, INSTALLATION AND COMMISSIONING ASSISTANCE | 13 | ||||
CLAUSE 7
|
PERFORMANCE TESTS | 15 | ||||
CLAUSE 8
|
GUARANTEED PERFORMANCE AND LIQUIDATED DAMAGES | 16 | ||||
CLAUSE 9
|
TOTAL AMOUNT OF LIQUIDATED DAMAGES | 17 | ||||
CLAUSE 10
|
BUYER’S OBLIGATIONS, REPRESENTATIONS AND WARRANTIES | 17 | ||||
CLAUSE 11
|
SUSPENSION OR TERMINATION | 18 | ||||
CLAUSE 12
|
CONFIDENTIALITY AND INTELLECTUAL PROPERTY | 20 | ||||
CLAUSE 13
|
INSPECTION AND TESTS AND SUPPLIER REPORTING | 21 | ||||
CLAUSE 14
|
DELIVERY OF PRELIMINARY DESIGN DRAWINGS | 22 | ||||
CLAUSE 15
|
WARRANTY | 22 | ||||
CLAUSE 16 CLAUSE 17 CLAUSE 18 CLAUSE 19 CLAUSE 20 CLAUSE 21 CLAUSE 22 CLAUSE 23 CLAUSE 24 CLAUSE 25 |
LIMITATIONS OF LIABILITY, GENERAL INDEMNITY ENVIRONMENTAL ISSUES AND SAFETY IMPORT AND EXPORT RESTRICTIONS FORCE MAJEURE APPLICABLE LAW ARBITRATION FINAL PROVISIONS CHANGE ORDERS CORPORATE WARRANTIES NOTICES |
24 25 25 26 26 26 27 28 30 31 |
|
Page 3
Exhibit A
|
Technical Specifications and Scope of Supply | |
1 Scope of Supply | ||
2 Technical Specifications | ||
3 Data Sheets | ||
4 Main Flow Diagrams | ||
5 List of Suppliers | ||
6 Lay out drawings | ||
Exhibit B
|
Performance Xxxxxxx/Xxxxxxxxxx | |
0 Xxxxxxxx X — performance guarantees | ||
2 Emission statement (DBAA992527) | ||
Exhibit C
|
Performance Test Guidelines | |
1 Power and heat rate tests (WDAAA245063) | ||
2 Lubricating oil consumption test (DAAB184367) | ||
3 Stack emissions test (DAAB195899) | ||
Exhibit D
|
Model Advance Payment Guarantee | |
Exhibit E
|
Model Performance Guarantee | |
Exhibit F
|
Model Payment Guarantee | |
Exhibit G
|
Draft Quality Assurance Plan | |
Exhibit H
|
Draft Delivery Schedule and Milestone Certificate | |
Exhibit I
|
Performance Test Completion Certificate | |
Exhibit J
|
Substantial Completion Certificate |
Page 4
1.1 | For the purposes of this Contract, the following words and terms shall have the meanings specified below: | |
Affiliate means a person or entity who, with respect to a specified person or entity, directly or indirectly through one or more intermediaries controls, or is controlled by, or is under common control with, the person or entity specified. | ||
Change of Law means (a) the enactment, adoption, promulgation, modification or repeal, after the signing of this Contract, of any Governmental Rule; or (b) any interpretation of any Governmental Rule imposed by tribunal decision or by any other Governmental Unit, which differs from the interpretation of such Governmental Rule at the date this Contract was signed; or (c) the imposition of any material condition on the issuance or renewal of any Governmental Approval after the signing of this contract; or (d) the failure to issue or renew any Governmental Approval, which, in any such case, establishes or modifies requirements materially affecting the design, engineering, procurement or supply of the Plant making completion of the work with respect to the Plant and Services materially more burdensome than the requirements expressly specified in this Contract. |
Page 5
Change Order means a written order to the Supplier pursuant to clause 23 hereof authorizing an addition, deletion or revision in the Equipment, the Plant and/or Services, any change to the Contract Price, and/or any adjustment to the Delivery date, or any scheduled dates of Delivery as well as to estimated project schedule. | ||
Commissioning shall be carried out in accordance with the Supplier’s standard guidelines and procedures at the Site and shall mean any functional tests that have not been carried out during Pre-Commissioning in the Shipyard and the Performance Test. | ||
Contract means this supply contract, including all exhibits attached hereto, as amended from time to time as provided herein. | ||
Contract Price shall have the meaning set out in clause 3. | ||
Delivery means the delivery of the Plant, as set forth in clause 5. | ||
Electrical Energy means the electrical energy measured in kJ or kWh at the Electrical Power Guarantee Point during an Electrical Power Test. | ||
Electrical Power means the electrical power calculated as the Electrical Energy divided by the time determined in Exhibit B (Performance Figures/Guarantees) of the Contract during an Electrical Power Test, and measured in kW. | ||
Electrical Power Test means a test conducted in accordance with Exhibit C (Performance Test Guidelines) of the Contract to determine Electrical Power. | ||
Electrical Power Guarantee means the guarantee that the Electrical Power measured during the Electrical Power Test shall be no lower than the value stated in Exhibit B (Performance Figures/Guarantees) of the Contract as recalculated for Site Conditions in accordance with Exhibit C (Performance Test Guidelines). | ||
Electrical Power Guarantee Point means the point specified in Exhibit B (Performance Figures/Guarantees) where the electrical energy is measured during the Electrical Power Test. | ||
Equipment means the engines and auxiliary equipment specified in Exhibit A (Technical Specifications and Scope of Supply) to be delivered by the Supplier. | ||
Facility means the facility at Site in which the Plant will be installed by the Buyer including the necessary works, systems, foundations, mooring facility, power evacuation, fuel supply and other systems, equipment and works required for the proper installation and function of the Plant. | ||
Factory Testing shall have the meaning set out in clause 13.1. | ||
Governmental Approval means any authorisation, consent, approval, license, lease, ruling, permit, certification, exemption, or registration, by or with any Governmental Unit. | ||
Governmental Rule means any statute, law, regulation, ordinance, rule, judgement, order, decree, directive, or requirement, or any similar form of decision of or determination by, or any interpretation or administration of, any of the foregoing, by any Governmental Unit. | ||
Governmental Unit means any national, provincial, state or local government, any political subdivision thereof, or any governmental, quasi-governmental, judicial, public or statutory instrumentality, administrative agency, authority, body or other entity having jurisdiction, in whole or in part, over the performance of the work with respect to the Equipment, the Plant and/or Services, the Facility or its operations, transmission of electricity to the Buyer, or the health, safety or environmental conditions of the Plant, Facility or the Site or otherwise over the parties hereto. |
Page 6
Heat Rate means the average ratio of the Total Fuel Energy consumed over the Electrical Energy, given as kJ / kWh. | ||
Heat Rate Guarantee means the guarantee that the Heat Rate during a Heat Rate Test shall not exceed the value stated in Exhibit B (Performance Figures/Guarantees) as recalculated for Site Conditions in accordance with Exhibit C (Performance Test Guidelines). | ||
Heat Rate Test means a test conducted in accordance with Exhibit C (Performance Test Guidelines) to determine the Heat Rate. | ||
Lubricating Oil Consumption Guarantee means the guarantee that the specific lube oil consumption measured during a lube oil consumption test shall not exceed the value stated in Exhibit B (Performance Figures/Guarantees). | ||
Xxxxx Xxxxxxx means the landward side of the straight line between the following two coordinates [3º 05’ 44.7” S, 152º 38’ 15.9” E] and [3º 07’ 15.4” S, 152º 39’ 23.8” E] in Lihir (Niolam) Island, New Ireland Province, Papua New Guinea. | ||
Maximum Heat Rate Guarantee means the maximum heat rate as stated in Exhibit B (Performance Figures/Guarantees) which the Plant may not exceed in order to be accepted hereunder. | ||
Milestone Certificate means the certificate in the form set forth in Exhibit H issued by the Supplier to the Buyer, certifying that a portion of the works in the Shipyard has been completed entitling Supplier to a milestone payment in accordance with the provisions of clause 4.3 c). | ||
Minimum Electrical Power Guarantee means the minimum electrical power stated in Exhibit B (Performance Figures/Guarantees) which the Plant has to achieve to be accepted hereunder. | ||
Minimum Performance Requirements means the Minimum Electrical Power Guarantee and the Maximum Heat Rate Guarantee. | ||
Performance Tests shall have the meaning set out in clause 7.1. | ||
Performance Tests Advisor means a Supplier authorised and approved (at the Suppliers discretion) contractor engaged to carry out and/or have an advisory role during the Commissioning and Performance Tests (which shall be the subject of a separate contract). | ||
Performance Test Completion Certificate shall have the meaning set out in clause 8.1.4. | ||
Plant means the floating power plant barge to be constructed by the Supplier, consisting, inter alia, of the Equipment. | ||
Pre-Commissioning means those steps and processes, functional and safety tests which can as far as practically possible be carried out in the Shipyard and in accordance with the Supplier’s standard guidelines and the Technical Specification or Inspection and Test Program in Exhibit G. Pre-Commissioning shall, to the extent possible in the Shipyard, include start-up of the 20V32 generating sets (without synchronisation and loading). | ||
Services means any services the Supplier has agreed to perform pursuant to the Contract by way of Pre-Commissioning, repairing or replacing the Plant, or by way of performing or re-performing the Services under the warranty or otherwise. | ||
Shipyard means the shipyard where the Supplier will have the Plant constructed. |
Page 7
Site means the location on Lihir Island, New Ireland Province, Papua New Guinea where the Plant is to be installed by the Buyer and where the Commissioning and Performance Tests shall be conducted. | ||
Site Conditions means the conditions at the Site, stipulated in Exhibit B (Performance Figures/Guarantees), for purposes of the Plant design and calculation of the Performance Test results. | ||
Subcontractor means any person or entity having a contract with the Supplier or any other subcontractor to perform any part of the Supplier’s obligations under the Contract. | ||
Substantial Completion means the point in time when the Plant is ready for the conduct of the Commissioning and the Supplier has so notified the Buyer. | ||
Substantial Completion Certificate means the certificate in the form set forth as Exhibit J (Substantial Completion Certificate) issued by the Supplier as provided in clause 6.3 evidencing that Substantial Completion with respect to the Plant has occurred and the Plant is ready for Commissioning. | ||
Supplier’s Workshop means any workshop of the Supplier, any workshop of a company belonging to the Wärtsilä Group, any workshop of a Subcontractor, any workshop of a manufacturer of the Equipment and/or the Plant, or any other suitable place decided by the Supplier in its sole discretion. | ||
Technical Specifications and Scope of Supply means Exhibit A. |
1.2 | The headings contained herein are included solely for the convenience of the Parties and are not to be used as a basis for interpreting the various sections of this Contract. | |
1.3 | The term “day” as used in this Contract means a calendar day. | |
1.4 | Documents, drawings, schedules, manuals and other technical documents under this Contract will be written in the English language. |
2.1 | The Supplier sells and undertakes to deliver and the Buyer buys and undertakes to accept delivery of the Plant in accordance with the terms and conditions of this Contract, including all Exhibits which form an integral part of this Contract and which are attached hereto as set out in the TABLE OF EXHIBITS above. In case of any discrepancy or inconsistency between the terms herein and those specified in any Exhibits hereto, the Contract text shall take precedence over the Exhibit. The Exhibits shall be interpreted in the order shown in the Table of Exhibits above. | |
2.2 | Not used | |
2.3 | The Plant and manufacture thereof, shall be in accordance with the requirements set forth in Exhibit A (Technical Specifications and Scope of Supply) only. The Parties agree that for the purpose of complying with any governmental or other rules, regulations, standards or codes, the Plant shall be deemed in compliance therewith if the Plant meets the stack emissions levels stated in Exhibit B (Performance Figures/Guarantees). If any other standards or codes are found to be mandatory applicable, they shall be treated as a Change of Law under this Contract. All modifications, documentation, approvals, and any procedures, which are required due to any applicable laws or regulations outside the country of manufacture of the Equipment and/or the Plant, shall be the responsibility of and arranged and paid entirely by the Buyer. As a result of continuous technical development the Supplier may seek approval in writing from the Buyer to make improvements to the Plant and Services not yet delivered and such approval shall not be unreasonably withheld by the Buyer. |
Page 8
2.4 | Subject to the previous clause, no variation of the Plant, Services and/or the Contract shall be effective unless it and its consequences are confirmed in writing by the Parties and a Change Order is signed by duly authorised representatives of both Parties in accordance with the procedure set out in clause 23. | |
2.5 | Any illustrations, catalogues, drawings and dimensions which are either provided by the Supplier or are otherwise acquired by the Buyer otherwise than in accordance with this Contract and which relate to the Equipment, Services and/or the Plant are for information purposes only and are not to be relied upon by the Buyer as containing any representations, warranties or indemnities, save and to the extent that the contents of any such document are expressly incorporated in writing into the Contract (including clear references to such illustrations, catalogues, drawings and dimensions) or the obligation to give such a document is stipulated in the Contract. | |
2.6 | The Buyer declares and guarantees that the Buyer has, in due time prior to entering into the Contract, fully informed the Supplier of the standards, codes and regulations applicable to the Plant and its operation. The standards, codes and regulations applicable to the design and/or manufacture of the Plant are as set forth in the Technical Specification and Scope of Supply. If any other standards, codes or regulations are found to be mandatory applicable, they shall be treated in the same manner as stipulated in clause 2.4 above. |
3.1 | The total price for the Plant and the Services hereunder is (such amount, as it may from time to time be adjusted pursuant to the terms of this Contract is the “Contract Price”). | |
The above price is further broken down into following main sections: |
a) | Equipment and material (including engineering, project management etc) that will be delivered, by the Supplier, to the Shipyard is priced | ||
b) | Barge hull construction, installation and other works and services carried out in the Shipyard by Subcontractors is priced at | ||
c) | Services carried out by Supplier in the Shipyard is priced at | ||
d) | Shipment of Plant from the Shipyard to DES Xxxxx Xxxxxxx, Lihir Island, PNG priced at |
The Contract Price is based on delivery DES Xxxxx Xxxxxxx, Lihir Island (Incoterms 2000). The total Contract Price includes the costs of normal standard export packing, which shall under normal transport conditions prevent damage or deterioration of the Equipment before it reaches the point of destination. | ||
3.2 | The Contract Price does not include any present or future taxes, VAT, stamp duty, duties, imposts, deductions, withholdings, other charges and liabilities (all together, “Taxes”) imposed by any authorities, whether national or local outside the country of manufacture of the Equipment and/or Plant and associated with the Plant, the Equipment, the Services, the Supplier’s performance hereunder and/or this Contract. The Buyer shall bear, and where applicable reimburse the Supplier for such Taxes. | |
3.3 | If, at any time, an adjustment event arises in respect of any supply made by a Party under this Contract, a corresponding adjustment must be made between the parties. Payments to give effect to the adjustment must be made between the parties and the Supplier must issue a valid adjustment note in relation to the adjustment event. |
Page 9
4.1 | Payment of the Contract Price shall be made by the Buyer to the Supplier’s bank account designated by the Supplier in accordance with the timeframes set out below in clause 4.3. Banking charges incurred inside Finland or the country in which the Shipyard is situated shall be for the account of the Supplier while those incurred outside those countries shall be borne by the Buyer. | |
4.2 | All sums invoiced by the Supplier shall be paid by the Buyer into the Supplier’s bank account in Finland without any set off, counterclaim or deduction and are not subject to any settlement discount or other special terms of payment. | |
Notwithstanding the above, the Buyer may deduct from any amount due or becoming due to the Supplier under this Contract all undisputed debts and amounts due from the Supplier to the Buyer under or in connection with this Contract, provided it gives the Supplier no less than 10 days notice in writing of its intention to do so. | ||
4.3 | The Buyer agrees to pay the Contract Price to the Supplier in the following manner: |
a) | of the Contract Price as an advance payment not later than seven
(7) days after the date of signing of this Contract provided the
Supplier gives the Buyer: (i) an invoice; and (ii) an advance payment guarantee of equal value issued by a first class international bank nominated by the Supplier and acceptable to the Buyer (S&P rating of at least A-) in form and substance set forth in Exhibit D (Model Advance Payment Guarantee) to be maintained until a minimum of 60 days following the scheduled date of Delivery as set forth in clause 5.2(a) or as specified in Exhibit H (Draft Delivery Schedule and Milestones). |
||
b) | of the Contract Price upon shipment of the last Wärtsilä 20V32 generating set out of the eight (8) 20V32 generating sets to be delivered by the Supplier under this Contract, not later than seven (7) days after receipt of the following documents from the Supplier: |
1) | commercial invoice; | ||
2) | copy of clean on board xxxx(s) of lading giving evidence that all 8 generating sets of 20V32 type have been shipped from Finland to the country of the Shipyard; | ||
3) | packing list; and | ||
4) | performance guarantee in an amount of of the Contract Price issued by a first class international bank nominated by the Supplier and acceptable to the Buyer (S&P rating of at least A-) in form and substance set forth in Exhibit E (Model Performance Guarantee). The Model Performance Guarantee shall be maintained until 12 months following issue of Performance Test Completion Certificate. |
c) | of the Contract Price divided into the five (5) milestone events as defined in below milestone payment schedule, not later than seven (7) days after receipt of the following documents from the Supplier; |
1) | commercial invoice; and | ||
2) | a Milestone Certificate corresponding to the achieved milestone event ; |
Page 10
Milestone payments schedule: |
Milestone | Milestone | |||||
No. | event | Milestone Certificate | payment amount | |||
1
|
Keel laying | Milestone Certificate signed by the Supplier and the Shipyard evidencing that the barge hull keel has been laid | ||||
2
|
Launching of the barge hull | Milestone Certificate signed by the Supplier and the Shipyard evidencing that the barge hull has been launched into the water | ||||
3
|
Placing of generating sets | Milestone Certificate signed by the Supplier and the Shipyard (or applicable installation party) evidencing that all 8 generating sets of 20V32 type have been placed on the barge hull | ||||
4
|
Installation of radiators | Milestone Certificate signed by the Supplier and the Shipyard (or applicable installation party) evidencing that the cooling radiators of all 8 generating sets of 20V32 type have been installed on the power house roof | ||||
5
|
First smoke | Milestone Certificate signed by the Supplier and the Shipyard (or applicable installation party) evidencing that the first generating set out of the 8 generating sets of 20V32 type has been started |
d) | of the Contract Price upon completion of the construction and installation works and Pre-Commissioning in the Shipyard not later than seven (7) days after receipt of the following documents from the Supplier: |
1) | commercial invoice; | ||
2) | copy of Substantial Completion Certificate; and | ||
3) | xxxx of lading for the Plant confirming that the Plant has been placed upon the semi-submersible transport vessel from the Shipyard. |
4.4 | In order to secure the Buyer’s payment obligations under this Contract, the Buyer shall within thirty (30) days after the date of signing of this Contract, deliver to the Supplier a payment guarantee (the “Payment Guarantee”) in an amount of of the Contract Price and issued by a first class international bank nominated by the Buyer and acceptable to the Supplier (S&P rating of at least A-) in form and substance set forth in Exhibit F (Model Payment Guarantee) to be maintained until a minimum of 30 days following receipt of the Substantial Completion Certificate. |
Page 11
Upon payment of the milestone in 4.3(b) above: |
(a) | the Buyer shall within seven (7) days, deliver to the Supplier a replacement payment guarantee (the “Replacement Payment Guarantee”) in an amount equal to the difference between the aggregate of all sums paid by the Buyer to the Supplier under the Contract and the Contract Price and issued by a first class international bank nominated by the Buyer and acceptable to the Supplier (S&P rating of at least A-) in form and substance set forth in Exhibit F (Model Payment Guarantee) to be maintained until a minimum of 30 days following receipt of the Substantial Completion Certificate; and | ||
(b) | upon receipt of the Replacement Payment Guarantee, the Supplier must promptly return the Payment Guarantee to the Buyer. |
The Buyer is entitled to progressively decrease the value of the Replacement Payment Guarantee in an amount equal to any further payments of any percentage of the Contract Price until such times as the Replacement Payment Guarantee is reduced to zero at which point, the Supplier must return it to the Buyer. | ||
4.5 | Amounts not paid by either Party to the other when due under this Contract shall bear interest from the date payment was due to the date of payment in full at a rate per annum equal to over the one (1) month’s Euro Inter Bank Offered Rate (EURIBOR) of the due date. | |
The overdue interest shall be paid forthwith against an invoice on the date specified therein (not to be less than 14 days). | ||
4.6 | At the conclusion of validity of any payment or performance guarantee issued under this Contract by one party to the other, the recipient of the guarantee must return that guarantee to the party who provided the guarantee within 14 days. The party who provides a guarantee to the other party can request the early return of that guarantee but only when all obligations secured by that guarantee have been discharged in full (to be determined in the sole discretion of the recipient of the guarantee, acting reasonably). |
5.1 | The Plant must be delivered DES Xxxxx Xxxxxxx, Lihir Island (Incoterms 2000). The delivery is to occur at a suitable discharging location to be nominated by the Supplier or the Suppliers transport provider (provided it is within Xxxxx Xxxxxxx). | |
5.2 | References to “Delivery” in this Contract shall be to the following dates: |
(a) | Unless the schedule is varied in accordance with this Contract, the Plant must be placed on the semi-submersible delivery vessel at a suitable loading location near the Shipyard by no later than 1 March 2011, such date to be evidenced by a xxxx of lading for the Plant. The Buyer agrees that no liquidated damages for delay will accrue for a period of seven (7) days from 1 March 2011. | ||
(b) | The Plant shall be delivered at a suitable discharging location DES Xxxxx Xxxxxxx, Lihir Island by no later than 21 March 2011. For the removal of doubt, because the parties acknowledge that delays during the shipment of the Plant are beyond their control, liquidated damages of per day of delay shall be payable by the Supplier to the Buyer. The Buyer shall be responsible for any delays (including but not limited to demurrage costs) caused by its failure to discharge the Plant from the delivery vessel at the discharging location. |
5.3 | If the Supplier fails to deliver the Plant from the Shipyard in accordance with clause 5.2(a) due to reasons attributable to the Supplier, the Buyer shall be entitled to receive liquidated damages calculated at the rate of of the Contract Price per week of delay (pro rata based) . |
Page 12
The total amount of liquidated damages to be paid by the Supplier for the Supplier’s delay in Delivery shall in no case exceed of the Contract Price. | ||
5.4 | In case the Plant cannot be loaded onto the transport vessel from the Shipyard on or after 1 March 2011 for reasons attributable to the Buyer: |
a) | the Buyer shall arrange for storage and insurance of the Plant. The storage and insurance shall be at the Buyer’s risk and expense. | ||
b) | Delivery shall be deemed to be completed and the Buyer shall proceed to pay in accordance with clause 4.3(d). |
5.5 | If the Delivery is delayed because of force majeure or because of an act or omission of the Buyer or due to reasons within the control of the Buyer, or due to reasons not being at the Supplier’s risk (such as Change of Law outside the country of the manufacture of the Equipment and/or the Plant), or if the Buyer is late in providing technical documentation or equipment/material for inclusion in the Plant, the Supplier shall be granted an extension of time for the Delivery which will be equal to the additional period of time caused by such delay. The Buyer shall pay all reasonable expenses related to these delays, including, but not limited to, the storage of the Equipment and/or the Plant, subject to limitation of liability set forth in this Contract. | |
5.6 | The Supplier shall maintain possession of title and ownership of the Plant which shall automatically pass to the Buyer only when payment in full of the total Contract Price has been received by the Supplier. If the applicable law of the Contract does not allow the Supplier such a retention of title or ownership of the Plant, the Supplier shall be entitled to such other similar or corresponding rights as the applicable law allows it to retain. The Buyer shall take all measures to ensure that the title of the Supplier is in no way prejudiced. | |
Notwithstanding the above, upon payment in full of the amounts in clauses 4.3(a) and 4.3(b) by the Buyer to the Supplier, title to eight (8) generating sets of 20V32 type shall pass to the Buyer. | ||
Risk of loss or damage to the Equipment and the Plant shall pass in accordance with the relevant Incoterm (2000). | ||
5.7 | The Buyer shall have no right to reject or refuse the Delivery or acceptance of the Plant by reason of minor defects which do not prevent the normal operation of the Plant, provided that the Supplier agrees to remedy such defects after the Delivery of the Plant in compliance with the Contract. |
6.1 | The Buyer will prepare the Facility in which the Plant will be installed by the Buyer, including as necessary the construction of all roads and other required civil works and the required mooring facilities, so that the Site and the Facility are timely ready before the Commissioning of the Plant. Furthermore, the Buyer shall be responsible for the supply and setting up of all utilities’ services, fuel storage facilities and the interconnection of the Plant to the electricity grid. | |
6.2 | Following the delivery of the Equipment to the Shipyard the installation of the Equipment and the Pre-Commissioning of the Plant shall be carried out by the Supplier in accordance with the Technical Specification and Scope of Supply and the Supplier’s standard guidelines and procedures. | |
6.3 | Substantial Completion | |
6.3.1 | On the date that the Supplier believes that it has achieved Substantial Completion and the Plant is ready for Commissioning, the Supplier shall deliver to the Buyer a Substantial Completion Certificate. Within five (5) days of receipt of the Substantial |
Page 13
Completion Certificate, the Buyer shall deliver its acceptance of the Substantial Completion Certificate or a notice to the Supplier rejecting the Substantial Completion Certificate. The Buyer shall not unreasonably withhold acceptance of the Substantial Completion Certificate and shall specifically identify its reasons for rejection of the Substantial Completion Certificate. If the Supplier accepts the reasons for such rejection, it shall take corrective action and submit a new Substantial Completion Certificate to the Buyer for action in accordance with the procedures set forth in this clause. If the Supplier disagrees with the reasons for the rejection or if the Owner fails to act upon the Substantial Completion Certificate within the time period provided for herein (or such longer period as the Parties may mutually agree upon), the Supplier may refer the dispute to Fast Track Arbitration in accordance with clause 21.3. | ||
The Plant shall be considered ready for Commissioning as soon as the Owner has accepted and counter signed the Substantial Completion Certificate. The Substantial Completion certificate indicates that: 1) the Plant is in conformity with the Technical Specifications and Scope of Supply (subject to minor defects which will be the subject of a punch list); 2) the Plant is constructed according to the Supplier’s instructions and guidelines; and 3) the Plant can be started safely. |
6.3.2 | By declaring Substantial Completion, the Supplier declares that the Plant is ready for Commissioning. Commissioning shall be carried out at the Site by the Buyer with the technical assistance of the Performance Tests Advisor, such services to be the subject of a separate contract. | |
6.4 | Not Used. | |
6.5 | The Supplier shall provide a monthly report containing the following headings: |
• | Progress reported against the project schedule | ||
• | Safety and Security at Shipyard; | ||
• | Progress during the month and total progress; | ||
• | Purchasing / Subcontracts; | ||
• | Financial; | ||
• | Customer Relations; | ||
• | Resource management; | ||
• | Main Obstacles/Project Risks; | ||
• | Site Meetings; | ||
• | Letters to/from Client; | ||
• | Quality Assurance/Technical Feedback from Supervisors and LGL representative; | ||
• | Others; and | ||
• | Photos. |
6.6 | N/A | |
6.7 | The Commissioning of the Plant cannot be started before the issuance of the Substantial Completion Certificate. The Supplier reserves the right to stop the Commissioning procedure in order to make necessary adjustments. Under no circumstances shall the Buyer be authorised to carry out the Commissioning without the assistance of the Performance Tests Advisor. |
Page 14
6.8 | The Supplier shall provide free of charge any power, water, lubricants, chemicals, fuel and lubricating oil required for Pre-Commissioning of the Plant at the Shipyard. |
6.9 | If Commissioning cannot be carried out due to reasons attributable to the Buyer within three (3) months from the Delivery of the Plant as specified in clause 5.2(a), the Plant and the Services shall be deemed to be accepted by the Buyer and the Performance Test Completion Certificate shall be issued and the performance of the Plant shall in all respects be deemed to have been in accordance with this Contract. |
7.1 | Performance tests shall be performed and the performance of the Plant shall be measured and calculated in accordance with the Exhibit C (Performance Test Guidelines) and the Supplier’s standard procedures to determine whether the Plant meets the performance guarantees specified in Exhibit B (Performance Figures/Guarantees) (the “Performance Tests”). The methods for measurements, tolerances and calibration requirements used are described in Exhibit C (Performance Test Guidelines). The timing for the Performance Tests is to be agreed between the Buyer and the Supplier but shall be no earlier than 4 weeks after the issuance of the Substantial Completion Certificate and no later than as is required under clause 7.2.2 below. | |
7.2.1 | The Performance Tests shall be carried out at the Site in accordance with Exhibit C (Performance Test Guidelines), the Supplier’s standard procedures and Exhibit A (Technical Specifications and Scope of Supply). The Performance Tests shall be carried out by the Buyer with assistance and technical advisory services provided by the Performance Tests Advisor, promptly following: (a) the receipt and acknowledgement by the Buyer of the Substantial Completion Certificate from the Supplier confirming the proper installation and readiness of the Plant for the Commissioning. The fuel for the Performance Tests as specified in Exhibit B (Performance Figures/Guarantees) or better shall be provided by the Buyer. Prior to the testing, both Parties shall designate one official witness to the Performance Tests who shall have definitive authority in reaching agreement, before and during the Performance Tests, on the test procedure and the results. Such witness shall also have the right to represent the Buyer for all purposes in the event the Buyer is absent from the Performance Tests. Upon completion of the Performance Tests, the Performance Test Completion Certificate shall be issued in accordance with clause 8. | |
7.2.2 | If the Buyer fails to commence carrying out the Performance Tests after having been notified by the Supplier or the Performance Tests Advisor and thereby preventing the Performance Tests from being completed or if the Performance Tests at the Site have not been carried out within three (3) months after from the Delivery of the Plant as specified in clause 5.2(a) and such failure is due to reasons not attributable to the Supplier or the Performance Tests Advisor then: |
(a) | the Performance Tests shall be deemed to have been properly carried out; | ||
(b) | the Performance Test Completion Certificate shall be issued upon expiry of the aforementioned three (3) months’ period and no claims whatsoever arising under that certificate may be presented; and | ||
(c) | the Services shall be considered rendered and accepted. |
7.3 | If a Performance Test fails due to reasons attributable to the Supplier or the Performance Tests Advisor, the Supplier shall be given a reasonable period of time to make necessary adjustments and repairs to the Plant. After this adjustment period, a new Performance Test shall be conducted. If during this second Performance Test any performance guarantee/figure set forth in Exhibit B (Performance Figures/Guarantees) cannot be reached, the Parties shall jointly make an investigation so as to find out the reason (to be concluded in no more than 21 days). If it is due to |
Page 15
reasons for which the Supplier or the Performance Tests Advisor is responsible for, the Supplier or the Performance Tests Advisor shall make necessary repairs, replacement and/or modifications to the Plant as soon as possible. After making the modifications new Performance Tests shall be carried out as soon as practically possible. | ||
7.4 | The Buyer shall not be entitled to use the Plant (or any part thereof) for commercial purposes before the conclusion of the Performance Tests. If the Buyer does so without the consent of the Supplier (which shall not be unreasonably withheld), then (i) the Buyer shall be regarded as having thereby accepted the Plant; (ii) the Substantial Completion Certificate (unless already issued) and the Performance Test Completion Certificate shall be issued; (iii) the Services shall be considered rendered and accepted as a whole in accordance with this Contract. |
8.1 | The performance guarantees given by the Supplier for the Plant are set forth in this clause 8 and Exhibit B (Performance Figures/Guarantees). The performance of the Plant and its compliance with the Performance Figures/Guarantees shall be determined in the Performance Tests. | |
8.1.1 | If the Plant fails to achieve the Minimum Electrical Power Guarantee or the Maximum Heat Rate Guarantee during the Performance Tests, the Supplier shall take appropriate corrective measures and the relevant Performance Test shall be re-performed until the achievement of the Minimum Performance Requirements. | |
8.1.2 | If the Plant achieves the Minimum Electrical Power Guarantee and the Maximum Heat Rate Guarantee but not the Electrical Power Guarantee and/or the Heat Rate Guarantee, the Supplier may declare the Performance Tests to be completed and pay liquidated damages according to clause 8.2, or may take appropriate corrective actions and have the relevant Performance Test re-performed until the achievement of the Electrical Power Guarantee and the Heat Rate Guarantee. | |
8.1.3 | The determination whether the Plant has achieved both the Minimum Electrical Power Guarantee and the Maximum Heat Rate Guarantee must be based on the results of the same Performance Test. The determination whether the Plant has achieved both the Electrical Power Guarantee and the Heat Rate Guarantee must be based on the results of the same Performance Test. | |
8.1.4 | Upon the completion of the last Performance Test, whether upon the achievement of the Electrical Power Guarantee and the Heat Rate Guarantee or otherwise in accordance with the provisions of clause 8.2, the Supplier shall issue to the Buyer a performance test completion certificate in the form of Exhibit I (the “Performance Test Completion Certificate”) setting forth the Electrical Power and Heat Rate achieved. Within five (5) days from the receipt thereof, the Buyer shall deliver its acceptance of the Performance Test Completion Certificate or a notice of rejection to the Supplier setting forth the specific reasons for such rejection. If the Supplier accepts such rejections (acting in a reasonable manner), it shall take corrective action and submit a new Performance Test Completion Certificate. The Buyer shall not be obligated to accept the Performance Test Completion Certificate unless the Minimum Performance Requirements as stated in Exhibit B (Performance Figures/Guarantees) have been achieved. Under no circumstances shall the issuance of this Performance Test Completion Certificate be delayed due to minor deficiencies that do not affect the use of the Plant. | |
8.2 | Liquidated Damages |
Page 16
8.2.1 | Electrical Power Guarantee | |
If after the repairs and adjustments as deemed necessary by the Supplier have been completed, the Electrical Power Guarantee specified in Exhibit B (Performance Figures/Guarantees) as measured in accordance with Exhibit C (Performance Test Guidelines) is not achieved during the final performance test run due to reasons attributable to the Supplier or the Performance Tests Advisor, the Supplier shall be liable for liquidated damages calculated at the rate of of the Contract Price for every in average short of the Electrical Power Guarantee. | ||
8.2.2 | Heat Rate Guarantee | |
If after the repairs and adjustments as deemed necessary by the Supplier have been completed, the Heat Rate Guarantee for the generator sets, excluding emission control systems, specified in Exhibit B (Performance Figures/Guarantees) as measured in accordance with Exhibit C (Performance Test Guidelines) is not achieved during the final performance test run due to reasons attributable to the Supplier or the Performance Tests Advisor, taking into consideration the average of all the generator sets supplied hereunder, the Supplier shall be liable for liquidated damages calculated at the rate of of the Contract Price for every of excess average heat rate. | ||
8.2.3 | Lubricating Oil Consumption Guarantee | |
If after the repairs and adjustments as deemed necessary by the Supplier have been completed, the Lubricating Oil Consumption Guarantee specified in Exhibit B (Performance Figures/Guarantees) as measured in accordance with Exhibit C (Performance Test Guidelines) cannot be met due to reasons attributable to the Supplier or the Performance Tests Advisor, taking into consideration the average of all engines supplied hereunder, the Supplier shall be liable for liquidated damages at the rate of of the Contract Price per of excess average consumption. | ||
8.3 | Maximum Performance Liquidated Damages | |
Notwithstanding anything to the contrary in this clause 8, the liquidated damages payable by the Supplier for the Plant’s failure to meet any Performance Figure/Guarantee set forth in Exhibit B shall in no case exceed of the Contract Price and the aggregate of any and all liquidated damages payable by the Supplier for the Plant’s failure to meet the Performance Figures/Guarantees shall in no case exceed of the Contract Price. |
9.1 | The total aggregate amount of liquidated damages payable by the Supplier under this Contract whether for performance or for delay shall in no case exceed of the Contract Price. The liquidated damages shall be the Buyer’s only remedy for delay in delivery and for any deviations in the Plant and the Performance Figures/Guarantees and shall constitute the Supplier’s only liability in these respects. |
10.1 | The Buyer shall be responsible for obtaining all permits, approvals, authorizations, consents and licenses from all relevant authorities for the Plant, the engineering, delivery, Commissioning and operation of the Plant, and any Services to be provided under this Contract, except in the country of manufacturing of the Equipment and the Plant. |
Page 17
10.2 | The Buyer shall be responsible: (i) for providing the Supplier promptly within the time required by the Supplier all necessary information and data on the Site the correctness, accuracy and sufficiency of which are hereby warranted by the Buyer; and (ii) for providing timely access to the Facility and Site to the Supplier’s personnel for the performance of the Services. | |
10.3 | Nothing in this Contract shall operate so as to lessen the Buyer’s responsibility toward the Supplier even in the event the Buyer has contracted a part of the work in respect of the Plant, Site and/or Facility to a third party. Any delays, inactions or actions of such third party contractor of the Buyer which have an impact on the performance of the Supplier shall be considered delays, inactions or actions on the part of the Buyer for purposes of this Contract. | |
10.4 | Nothing in this Contract shall operate so as to lessen the Supplier’s responsibility toward the Buyer even in the event the Supplier has contracted a part of the work in respect of the Plant to a third party. Any delays, inactions or actions of such third party contractor of the Supplier which have an impact on the performance of the Buyer shall be considered delays, inactions or actions on the part of the Supplier for purposes of this Contract. |
11.1 | It is expressly agreed that, upon giving 5 days written notice to the Buyer, the Supplier shall have the right to change the delivery schedule and/or suspend its performance if: (i) it has not received the advance payment; or (ii) the Buyer has not opened the Payment Guarantee as set forth in this Contract. The Buyer shall compensate the Supplier for all reasonable direct costs as a result of or in connection with any of the foregoing events. | |
In case the advance payment or the receipt of the Payment Guarantee is delayed the Supplier shall be granted an extension of time for the Delivery which will be no more than the additional period of time caused by such delay (taking into consideration the effects the delay for not being able to commit to the supplies from the Subcontractors), however for any other delayed payments the Delivery date may only be extended with the number of days equal to the days of delay of any contractual payment. | ||
Without prejudice to any other right or remedy available, either Party shall reserve the right to suspend its performance of this Contract on the occasion of, and for a period equal to, any default by the other Party in payment of any sum due and payable to the other hereunder, provided it has given no less than 10 days notice of its intention to do so to the other party. | ||
If the Buyer is in breach of any of its payment obligations or of its obligation to open the Payment Guarantee and this breach continues longer than three months, the Supplier shall be entitled by notice in writing to the Buyer and without requiring the consent of any court to terminate this Contract with immediate effect. |
11.2 | Remedying breaches |
Page 18
11.3 | If a Party is in material breach of a clause of the Contract, the other Party may, by giving ten (10) days notice in writing to the defaulting Party, suspend performance of any of its obligations under this Contract or any part thereof. The suspension right does not prevent a Party from using its right to exercise all remedies available to it under the Contract or at law. | |
11.4 | Upon termination of this Contract due to the Buyer’s breach of its contractual obligations the Supplier is entitled to: (i) be remunerated by the Buyer for all the work already performed under this contract; and (ii) to all other remedies available under the Contract and applicable law, all subject to limitations of liability set forth in this Contract. | |
11.5 | Upon termination of this Contract due to the Supplier’s breach of its contractual obligations the Buyer is entitled to such remedies available under the Contract and applicable law, all subject to limitations of liability set forth in this Contract. | |
11.6 | If the Buyer, taking into full consideration the extension of time for Delivery by reason of permissible delays, has become entitled to the maximum amount of liquidated damages provided in clause 5.3, and the Supplier has been in delay for at least three (3) months, then in such event, the Buyer may at its discretion as an alternative and to the exclusion of any other remedy either: (i) accept the Delivery and shall receive or retain, whichever is applicable, the above mentioned liquidated damages; or (ii) cancel this Contract and be entitled, as a sole and exclusive remedy, to a refund of all payments made by the Buyer to the Supplier under this Contract and interest thereon calculated at the rate stipulated in clause 4.5 above from the date of actual receipt of payment to the date of actual repayment. | |
11.7 | In the event either Party is declared bankrupt, insolvent, requests (temporary) moratorium, or proceeds with the liquidation of its business, the other Party has the right to immediately cancel this Contract in whole or in part reserving any rights with respect to compensation for costs, damages and interest. | |
11.8 | The Buyer has the right to cancel the Contract at its sole discretion, with the consequence that the Supplier’s obligation to perform its obligations shall immediately cease. | |
Following such cancellation, the Buyer shall pay the Supplier in accordance with the cancellation payment schedule set out in clause 11.8.1. | ||
The cancellation charges are the sole and exclusive remedy for Buyer’s cancellation for convenience. | ||
All the payments already paid by the buyer to the Supplier under this Contract prior to cancellation for convenience shall be deducted from the applicable cancellation charges. | ||
Payment of the cancellation charges shall be made by the Buyer to the Supplier within thirty (30) days after receipt of the Supplier’s invoice therefore. Upon such payment, title to, and risk of loss of or damage to, any Equipment and/or portion of the Plant delivered or capable of being transferred or ready for delivery by the Supplier or Subcontractor shall transfer to the Buyer. |
Page 19
11.8.1 | Cancellation payment schedule: |
Number of days elapsed from the | ||
signing date of Contract | Payment in EUR | |
0 – 30 days
|
||
31 – 90 days
|
||
91 – 150 days
|
||
151 – 200 days
|
||
201 – 300 days
|
||
301 – 400 days
|
||
401 or more days
|
12.1 | Neither Party shall copy or disclose to a third party any document or data provided by the other Party (“Confidential Information”) without the prior written consent of the other Party or use Confidential Information for purposes other than those for which they were provided. The obligations under this clause 12.1 shall not apply to the extent that the receiving Party can prove, that: |
a) | information which, at the time of disclosure, was in public domain, without violation of confidence by the Receiving Party; or | ||
b) | information which, after such disclosure by the disclosing Party, becomes part of public domain by publication or otherwise, without violation of confidence by the receiving Party; or | ||
c) | information which the receiving Party can demonstrate by clear and convincing evidence, was in its possession at the time of such disclosure by the disclosing Party; or | ||
d) | information which is lawfully obtained by the receiving Party from a third party without an obligation of confidentiality, provided that third party is not, to the receiving Party’s best knowledge, in breach of any obligation of confidentiality to the disclosing Party relating to that information; or | ||
e) | information which is developed by the receiving Party independent without resort to the disclosed confidential Information. | ||
f) | the information is required to be disclosed by law or the rules of a stock exchange on which the Party’s securities are listed |
12.2 | All intellectual property rights (“IP Rights”) associated with the Plant and the Services or any document or data provided by the Supplier in connection therewith shall remain the Supplier’s property. The Supplier hereby grants to the Buyer a royalty-free, non-exclusive, non-transferable and irrevocable right to use the IP Rights and the Plant for the intended purpose. | |
12.3 | The Buyer shall defend, indemnify and hold harmless the Supplier against all third party claims, losses and damages, including reasonable attorneys’ fees, arising out of or resulting from any reuse, modification, reproduction or publication of the Supplier’s intellectual property documents or data caused by the Buyer, provided that: i) the Supplier promptly notifies the Buyer in writing of any such claims; and ii) the Supplier provides full disclosure and necessary assistance in respect of such claims made against the Supplier. |
12.4 | The Supplier shall defend the Buyer against claims made against the Buyer by any third party unrelated to the Buyer for infringement or alleged infringement of a patent or similar registered intellectual property right in respect of the manufacture or sale of the Plant and the Services, provided that: i) the Buyer promptly notifies the Supplier in |
Page 20
writing of any such claims; ii) the Buyer provides full disclosure and necessary assistance in respect of such claims made against the Buyer; and iii) the Buyer does not take any position adverse to the Supplier with respect to such claims and gives the Supplier sole authority, at the expense of the Supplier, to settle and defend such claims. The Supplier’s sole obligation will be at its discretion, to either procure the right for the Buyer to continue use of the Plant and the Services, or to modify or replace the Plant and the Services in whole or in part avoiding any such infringements. | ||
12.5 | Notwithstanding anything to the contrary contained in clause 12.4, the Supplier shall not have any liability to the Buyer to the extent that any infringement or claim thereof is based upon: (i) use of the Plant and the Services in combination with equipment or software not supplied by the Supplier where the Plant and the Services would not itself be infringing; (ii) compliance with the Buyer’s designs or specifications; (iii) use of the Plant and the Services in an application or environment for which it was not designed; or (iv) modifications of the Plant and the Services by anyone other than the Supplier without the Supplier’s prior written approval. |
13.1 | The Buyer, its representative or an internationally recognised inspection service may inspect materials and/or components used and witness the tests following the assembly of the Equipment and/or the Plant. The factory testing shall take place in the respective manufacturer’s factory in accordance with the relevant manufacturer’s standard testing procedures (“Factory Testing”). The date and time of the inspection and tests shall be communicated to the Buyer in advance. Inspection and testing shall be performed at the factory of the Supplier or Subcontractor during normal working hours. The Supplier shall bear the expenses of inspection and tests carried out at its factory, excluding the expenses (including travel and lodging) of the Buyer’s authorized representatives. If the Buyer is not represented at the tests, the test report shall be communicated to and deemed to be accepted as accurate by the Buyer. | |
13.2 | If the results of the Supplier’s or Subcontractor’s standard acceptance test procedures (including Factory Testing) confirm that any materials or components are found to be defective or not in accordance with Exhibit A (Technical Specifications and Scope of Supply), the Supplier shall correct the defect as soon as possible at its cost. | |
13.3 | Not used | |
13.4 | The Buyer shall cooperate without delay in any inspection or test agreed upon. If the Buyer prevents the test from being performed or fails to contribute to it according to the Contract, the results of such inspection or test will be deemed to have been done in accordance with the Contract and deemed approved by the Buyer in all respects, subject only to the Supplier’s warranty as provided here below. Where the results of such inspection or test are not in accordance with the requirements of the Contract, the Supplier shall take all appropriate steps to remedy such failure and make arrangements to re-test accordingly at its cost. | |
13.5 | At the Buyer’s request, the Supplier will investigate whether parts of the Equipment and/or the Plant or systems are defective or non-conforming. The Buyer shall pay such investigative costs unless the parts of the Equipment and/or the Plant or systems are deemed by the Supplier to be defective or non-confirming. | |
13.6 | The Buyer and the Supplier must attend regular meetings (at a minimum, bi-weekly) to discuss progress under this Contract. Such meetings shall initially be by bi-weekly teleconference at a mutually acceptable time. When the Supplier is in the Shipyard phase of manufacture, meetings are to be held at the Shipyard. |
Page 21
14.1 | At the appropriate time during the design and manufacture of the Plant, the Supplier shall deliver the Buyer preliminary design drawings, as specified in Exhibit A (Technical Specifications and Scope of Supply) whereof the following shall be subject to the Buyer’s review and approval: |
a) | Plant layout and general arrangement drawings (section and plan views); | ||
b) | Barge hull layout drawings (section and plan views); | ||
c) | Electrical single-line drawing; and | ||
d) | Process Main flow diagrams (P&ID). |
14.2. | The Buyer shall provide its approval or comments thereon to the Supplier within seven (7) days of receipt of the drawings. | |
14.3 | The Supplier shall promptly revise the drawings with the approved amendments and shall promptly deliver to the Buyer the revised drawings. The Buyer shall provide its approval or comments thereon to the Supplier within seven (7) days of receipt of the revised drawings. | |
14.4 | Any such approval or comments (under the preceding paragraphs) shall not relieve the Supplier from any obligation or responsibility. | |
14.5 | The Supplier shall provide operation and maintenance manuals as specified in Exhibit A (Technical Specifications and Scope of Supply) to the Buyer within thirty (30) days after Substantial Completion. | |
14.6 | The Supplier will update the preliminary quality assurance plan furnished under Exhibit G with preliminary timetables for the inspection and testing plan and preliminary drawing list and schedule within ten (10) weeks of the start of the Contract. |
15.1 | The Supplier shall repair or replace, at its sole discretion, any defect in the Plant which appears during the warranty period (defined in clause 15.3 below) as a result of defective material or manufacturing provided, always when required by the Supplier, that any defective parts of the Plant shall be returned to the Supplier, at the Supplier’s cost, to the place instructed by the Supplier. The Supplier shall repair or re-perform, in whole or in part, at its sole discretion, any defective Services which appear during the warranty period. The Buyer shall immediately take appropriate steps to prevent any defect from becoming more serious and to enable the Supplier to rectify the aforesaid defect. | |
In order to receive this remedy, any warranty claims or requests with respect to this warranty must be made in writing without delay and not later than fourteen (14) days following i) discovery of such defect during the warranty period, or ii) the day when such defect should have been discovered by the Buyer (exercising reasonable operations and maintenance practices) during the warranty period. The Buyer shall have the responsibility to establish that its claim is covered by this warranty. | ||
The Supplier agrees that it will wherever possible seek to minimise disruption to the ongoing operation of the Plant and the Buyer’s operations at the Site whenever the Supplier is carrying out its obligations under this warranty. |
Page 22
15.2 | Replaced parts of the Plant shall become the Supplier’s property. The Supplier shall bear only the costs of repairing or replacing the defective parts of the Plant at the Supplier’s Workshop (in accordance with clause 15.5 below), as well as the costs occasioned by the transport of the defective and of the repaired or replacement parts of the Plant between the Supplier’s Workshop and the place of Delivery (in accordance with clause 5.2(b)) as originally agreed in the delivery terms of the Contract. The Supplier shall not be responsible for removal or replacement of systems, structures of or other products at the facility of the Buyer or its customer in order to access the defective part of the Plant. | |
15.3 | The warranty period with respect to the Plant begins at the Delivery (in accordance with clause 5.2(a)) and ends twelve (12) months from the date of the Performance Test Completion Certificate or fifteen (15) months from the date of the Delivery (in accordance with clause 5.2(a)), whichever first occurs. The warranty period for the Services shall be six (6) months from the performance of the Service. | |
15.4 | The warranty period in respect of the Plant and the Services which have been repaired, replaced or re-performed under the warranty shall be six (6) months from the date of repair, replacement or re-performance, or until the expiration date of the original (contracted) warranty period of the Plant and the Services, whichever occurs later, under the same terms, conditions and limitations of liability, as those applicable to the Plant and the Services. However, in case were a part is replaced due to faulty design the warranty shall be twelve (12) months for the replaced part from the date of replacement. Under no circumstances shall the warranty period of any part of the Plant exceed twenty-four (24) months, and with respect to the Services twelve (12) months, from the date of commencement of the original warranty period as stipulated in sub clause 15.3. | |
15.5 | Services to be performed under the warranty shall be based on a normal working week and shall be for the account of the Supplier. A normal working week at the Supplier’s Workshop comprises of forty (40) hours spread over five (5) working days and not exceeding eight (8) hours per day. A normal working week at the Site comprises of fifty (50) hours spread over five (5) working days and not exceeding ten (10) hours per day. Services agreed to be performed outside the normal working week limits shall be charged to the Buyer as overtime. Any waiting time, for which the Supplier is not responsible, shall be charged to the Buyer as normal working time. | |
15.6 | This warranty does not cover any defects due to or connected with: 1) materials, components, tools, software or design provided by the Buyer or on behalf of the Buyer; 2) negligence or wilful misconduct or other improper acts or omissions of the Buyer, its employees or agents or other third parties; 3) other than original Spare Parts, accessories or attachments supplied by the Supplier; 4) improper installation, service work or alterations carried out by the Buyer ; 5) normal wear and tear; 6) use of unsuitable material consumables; 7) extreme ambient conditions not communicated by the Buyer to the Supplier before the signature of the Contract, 8) fluctuations in the grid; 9) any use, maintenance, service or operation of the Plant or any part thereof which is not in conformity with the Supplier’s or any Subcontractor’s manuals, instructions or specifications or which is otherwise not in accordance with normal industry practice. The Supplier’s warranty obligation (elsewhere than at the Supplier’s Workshop) does not include any cranage, electricity, scaffolding, docking, diving, sub-sea work, towage costs, demounting or mounting costs in order to access the defective parts of the Plant and all such reasonable costs and expenses shall be reimbursed by the Buyer to the Supplier when applicable. If after the Supplier’s warranty investigation it is found that the Buyer does not have a warranty claim within the scope of this Contract, then the Buyer shall be responsible for all applicable costs and expenses for such inspection, repaired or replaced parts of the Plant and Services or any other service work performed or re-performed by the Supplier. |
Page 23
15.7 | The Buyer shall provide the Supplier or Supplier’s representative access during the warranty period to take samples of fuels, lube oils, cooling liquids and other chemicals and materials, as need may be, used for the operation of the Plant. The Supplier reserves the right to perform simulations and tests to the Buyer’s equipment and attached systems in order to identify the cause of the failure in the operation of the Plant. The Supplier’s rights under this clause are subject to complying with the Buyer’s Site specific health, safety and security requirements and must be undertaken without undue disruption to the Buyer’s mining operations. |
15.8 | OTHER THAN THE CORPORATE WARRANTIES IN CLAUSE 24, THIS CLAUSE 15 SETS FORTH THE ONLY WARRANTIES APPLICABLE TO THE PLANT AND THE SERVICES AND IS IN LIEU OF ANY OTHER WARRANTIES, GUARANTEES, OBLIGATIONS AND LIABILITIES EXPRESS OR IMPLIED INCLUDING WARRANTIES, GUARANTEES, OBLIGATIONS OR LIABILITIES AGAINST NONCONFORMITY OR DEFECTS (HIDDEN OR OTHERWISE). THE BUYER HEREBY WAIVES ALL OTHER REMEDIES, WARRANTIES, GUARANTEES AND LIABILITIES, EXPRESS OR IMPLIED, ARISING BY LAW OR OTHERWISE (INCLUDING WITHOUT LIMITATION FITNESS FOR PURPOSE, MERCHANTABILITY OR SATISFACTORY QUALITY). |
16.1 | OTHER THAN LIQUIDATED DAMAGES IN ACCORDANCE WITH THIS CONTRACT, IN NO EVENT SHALL THE SUPPLIER BE LIABLE FOR ANY INDIRECT, CONTINGENT, SPECIAL, CONSEQUENTIAL OR INCIDENTAL DAMAGES, HOWEVER CAUSED OR ARISING (INCLUDING WITHOUT LIMITATION) FOR ANY LOSS OF ACTUAL OR ANTICIPATED PROFITS OR REVENUE OR ANTICIPATED SAVINGS, PUNITIVE OR EXEMPLARY DAMAGES, OR REPLACEMENT, REMOVAL OR REINSTALLATION SERVICE WORK NOT ARISING FROM THE WARRANTY PROVIDED HEREIN, TOWAGE CHARGES (AFTER DELIVERY IN ACCORDANCE WITH CLAUSE 5.2(b)), COSTS OF DOCKING (AFTER DELIVERY IN ACCORDANCE WITH CLAUSE 5.2(b)), DIVING OR SUB-SEA WORK, DAMAGE TO ANY VESSEL, ENGINE ROOM OR POWER PLANT SITE, COSTS FOR ANY ADDITIONAL TESTS (INCLUDING, WITHOUT LIMITATION, SEA TRIALS), DEBRIS REMOVAL, OR FOR LOSS OF TIME OR USE OF ANY EQUIPMENT, THE PLANT AND SERVICES DELIVERED HEREUNDER. THIS LIMITATION ON THE SUPPLIER’S LIABILITY SHALL APPLY TO ANY LIABILITY FOR BREACH OF THE SUPPLIER’S OBLIGATIONS UNDER OR IN CONNECTION WITH THE CONTRACT, WHETHER BASED ON WARRANTY, FAILURE OF OR DELAY IN DELIVERY OR OTHERWISE. | |
IN NO EVENT SHALL THE BUYER BE LIABLE FOR ANY INDIRECT, CONTINGENT, SPECIAL, CONSEQUENTIAL OR INCIDENTAL DAMAGES, HOWEVER CAUSED OR ARISING (INCLUDING WITHOUT LIMITATION) FOR ANY LOSS OF ACTUAL OR ANTICIPATED PROFITS OR REVENUE OR ANTICIPATED SAVINGS, PUNITIVE OR EXEMPLARY DAMAGES. | ||
The limitations of liability set out in this clause 16, however, do not apply to wilful misconduct, unlawful intent or gross negligence on the part of the Parties. The limitations of liability do not apply to the extent that it is contrary to any applicable mandatory law. | ||
16.2 | Notwithstanding any other provision of the Contract, the Supplier’s total aggregate liability on all claims of any kind whether in contract, warranty, indemnity, tort (including negligence), strict liability, or otherwise, arising out of the performance or breach of the Contract shall not exceed |
Page 24
16.3 | Notwithstanding any other provision of the Contract, the Buyer’s total aggregate liability (excluding the Buyer’s liability to pay the Contract Price) for all claims of any kind whether in contract, warranty, indemnity, tort (including negligence), strict liability, or otherwise, arising out of the performance or breach of the Contract shall not exceed | |
16.4 | Not used. | |
16.5 | Each Party shall indemnify and hold the other Party harmless from any claims by a third party for loss of or damage to property or death or personal injury arising out of or connected with that Party’s negligence while engaged in its activities under the Contract. In the event such damage or injury is caused by the joint or concurrent negligence of the Supplier and the Buyer, the loss shall be borne by each Party in proportion to its negligence. | |
16.6 | The Party who claims a breach of contract shall be required to take all reasonable measures to mitigate the loss which has occurred. | |
16.7 | The Supplier shall not be liable for any work carried out by the Buyer or for any equipment or material supplied by the Buyer for the installation or incorporation into the Plant. |
17.1 | With respect to the environmental requirements and regulations (e.g. noise and emissions) the Plant shall be in accordance with the requirements set forth in the Technical Specifications and Scope of Supply. All additional safety and environmental devices required for the operation of the Plant must be compatible with the Plant and shall be provided by and at the exclusive responsibility of the Buyer. | |
17.2 | The Supplier shall be fully responsible for affixing warning labels or plates on the Equipment in accordance with the applicable EU directives. The Buyer shall be fully responsible for affixing any additionally required warning labels or plates containing warnings or safety and operation procedures and instructions as required by law or safe working practice to the Plant. The Buyer shall also be responsible for ensuring that any persons using the Plant are aware of all the necessary safety instructions and that these are followed at all times. |
18.1 | The Parties agree the Plant and the Services shall be delivered subject to all applicable export controls or restrictions imposed on technology and products by any country or organization which are enforceable in the jurisdiction of the Supplier, its affiliates or parent company, including the Supplier’s country, the United Nations, the European Union and the United States of America. The Buyer acknowledges that the Plant and the Services and all related technical information, documents and materials may not be imported or exported, re-exported, trans-shipped, diverted or transferred, directly or indirectly, contrary to such controls or restrictions. | |
18.2 | The Buyer confirms that the Plant and the Services will be used solely for the intended peaceful purposes. The Buyer further confirms that the Plant and the Services will not be used in connection with any chemical, biological, nuclear weapons or missiles or any other vehicles or vessels capable of delivering such weapons, or in support of any terrorist activity or any other military end use. Nor will the Plant and the Services or any part thereof be re-sold if it is known or suspected by the Buyer that they are intended to be used for such purposes. Upon request by the Supplier, the Buyer shall furnish the Supplier with all relevant certificates relating to export control laws, regulations and restrictions, such as, but not limited to, end-user certificates, in form and substance specified by the Supplier. |
Page 25
19.1 | Neither Party shall be liable for any failure or delay in performing its obligations hereunder (other than an obligation to pay money), or for any loss or damage resulting there from, caused by or arising from an event of force majeure (“Force Majeure”) which includes without limitation: acts of God, wars, riots, embargos, hostilities, public disorder, strikes, lockouts or other industrial disputes, epidemics, fires, accidents, governmental restrictions and actions, acts of civil or military authorities, winding up or loss of workmen, unusually severe weather conditions or any other circumstances beyond the control of a party or its subcontractor but only to the extent that the Force Majeure event causes that failure or delay. | |
19.2 | Once a Party is aware that its performance under this Contract is likely to be affected by an event of Force Majeure, the affected Party shall, without any delay and in any event within 10 days, give written notice to the other Party setting out all relevant details relating to the delay. | |
19.3 | The affected Party shall consider with the other Party action to be taken to overcome the circumstances of force majeure and shall use its reasonable endeavours to overcome such circumstances, provided that, if the performance of the Contract is prevented for more than six (6) months because due to such circumstances, either Party may terminate the Contract by giving fourteen (14) days prior written notice to the other Party. | |
19.4 | Any termination as a result of Force Majeure shall not affect obligations and respective consideration due which have already been performed or provided at the time when the termination notice is given, nor does it affect the Supplier’s right to receive payment of any amounts due under the Contract in respect of obligations and work already performed. The title to any part of the Equipment and/or the Plant (at their current stage upon termination) paid by the Buyer shall be transferred to the Buyer. |
20.1 | The Contract shall be governed by and interpreted in accordance with the laws in force in Singapore, excluding the conflict of law rules applicable in such jurisdiction. |
21.1 | Negotiation of Disputes and Disagreements | |
21.1.1 | In the event of any dispute or disagreement arising out of or relating to the implementation or performance of this Contract (other than a dispute which is referable either to Fast Track Arbitration for resolution pursuant to clause 21.3 or directly to arbitration under the terms of this Contract), which the Parties hereto have been unable to settle or agree upon within a period of thirty (30) days after the dispute or disagreement arises, each Party shall nominate a senior officer of its management to meet at a mutually agreed time and place not later than forty-five (45) days after the dispute or disagreement has arisen to attempt to resolve such dispute or disagreement. | |
21.1.2 | Should a resolution of such dispute or disagreement not be obtained within fifteen (15) days after nomination of senior officers for such purpose, either Party may then by notice to the other submit the dispute to arbitration in accordance with the provisions of clause 21.2. | |
21.2 | Arbitration Resolution | |
21.2.1 | After following the procedure in clause 21.1, any claim, dispute or controversy arising |
Page 26
out of or relating to this Contract (other than a dispute to which the Fast Track Arbitration provisions of clause 21.3 apply) shall be submitted to binding arbitration under the Rules of Conciliation and Arbitration of the International Chamber of Commerce. The Parties shall cooperate in good faith in providing to the Arbitrator any information reasonably needed to resolve the dispute. No discovery proceedings shall be allowed. | ||
21.2.2 | The arbitration shall be held in Singapore and shall be conducted in the English language. If the amount of any asserted claim or counterclaim does not exceed the arbitration shall be conducted before a single arbitrator in accordance with the expedited procedures and rules of the Rules of Conciliation and Arbitration of the International Chamber of Commerce. In all other cases unless otherwise agreed, there shall be three arbitrators, with each Party selecting one; the third arbitrator, who shall be the chairman of the panel, shall be selected by the two Party-appointed arbitrators. The claimant shall name its arbitrator in the demand for arbitration and the responding party shall name its arbitrator within ten (10) days after receipt of the demand for arbitration. The third arbitrator shall be named within ten (10) days after the appointment of the second arbitrator. | |
21.2.3 | The award rendered by the arbitration shall be final and binding upon the Parties without the right of appeal to the courts and judgement thereon may be entered and enforced by any court having jurisdiction thereof. | |
21.3 | Fast Track Arbitration | |
21.3.1 | The Buyer and the Supplier shall decide upon an independent third party mutually acceptable to both Parties (the “Fast Track Arbitrator”) and an alternate third party (the “Alternate”) to decide disputes referable by the Parties for Fast Track Arbitration in accordance with this Contract. | |
21.3.2 | If the Buyer and the Supplier do not agree on a Fast Track Arbitrator, then the Dispute Board Centre of the International Chamber of Commerce shall be requested to select the Fast Track Arbitrator and the Alternate. The Fast Track Arbitrator and the Alternate each must have experience in diesel engine powered generation facilities. | |
21.3.3 | Either Party may refer any dispute arising out of the application of the provisions of clauses 6, 7 and 8 to the Fast Track Arbitrator as provided in said clause by written notice to the Fast Track Arbitrator and the other Party. | |
21.3.4 | If a Party has given written notice of its intent to refer such a dispute, the other Party shall be bound to Fast Track Arbitration as provided in this clause and may not resort to the procedures of clause 21.2. | |
21.3.5 | In the event that the Fast Track Arbitrator is unavailable to resolve the dispute within the time period stated in this clause, the dispute shall be referred to the Alternate. The Fast Track Arbitrator or the Alternate, as the case may be (the “Arbitrator”), shall be directed to resolve the dispute within fifteen (15) days of referral. The Parties shall cooperate in good faith in providing to the Arbitrator any information reasonably needed to resolve the dispute. | |
21.3.6 | The decision of the Arbitrator shall be final, binding and non-appealable on both Parties unless either of the Parties has, within thirty (30) days from the receipt of the said decision, submitted the dispute into the arbitration procedure set forth in clause 21.2. |
22.1 | Subject to any separate commissioning services contracts between the Parties or its Affiliate this Contract represents the entire agreement between the Parties hereto relating to the subject matter hereof and may be amended or varied only in writing by |
Page 27
duly authorised representatives of the Parties. The Parties expressly waive all provisions contained in any past agreement or correspondence which negate, limit, extend or conflict with the provisions herein. | ||
22.2 | The Supplier reserves the right to subcontract its obligations under this Contract (or any part thereof). Any delays, inactions or actions of the Supplier’s sub-contractors which have an impact on the performance of this Contract shall be considered delays, inactions or actions on the part of the Supplier for purposes of this Contract. The Supplier shall not be liable for the performance of subcontractor(s) selected by the Buyer against the recommendation of the Supplier and any delays, inactions or actions of such third party contractor of the Supplier which have an impact on the performance of the Buyer shall be considered delays, inactions or actions on the part of the Supplier for purposes of this Contract. | |
22.3 | Not used | |
22.4 | Not used | |
22.5 | Not used | |
22.6 | The Contract or any rights and obligations under the Contract may be assigned to an Affiliate of a Party, provided that the assigning Party remains liable for the performance of the assigned obligations by the assignee under the Contract. In any other case the Contract or any rights and obligations under the Contract may not be transferred, delegated or assigned by a Party without the prior written consent of the other Party (such approval not to be unreasonably withheld). In the event the Contract or any rights and obligations under the Contract are so transferred, delegated or assigned, the Contract shall be binding upon and shall inure to the benefit of the assignee. | |
22.7 | Each Party shall obtain a comprehensive insurance coverage for its own personnel, its own property and its own scope of activities, including in the case of the Supplier, such insurances as set out in Exhibit A. Such policies are to note the interests of the Buyer in the Equipment (or part thereof) and the Plant. | |
22.8 | The provisions of the Contract are severable and if any provision is held to be invalid or unenforceable by any court of competent jurisdiction then such invalidity or unenforceability shall not affect the remaining provisions of the Contract. | |
22.9 | This Contract shall become binding in its entirety on the date first written above when the duly authorised representatives of the Parties have signed the Contract. | |
22.10 | In carrying out their obligations under this Contract and in providing instructions, procedures and requirements under this Contract and in considering any change order proposal and agreeing any change order, the Parties will act in accordance with the principles of good faith and fair dealing. | |
22.11 | The provisions of this Contract shall be interpreted in good faith. | |
22.12 | This Contract may be executed in counterparts by the parties. |
23.1 | Buyer Requested Change Orders. | |
If the Buyer desires to make any change to the Plant and/or Services including, without limitation, upgrading materials or equipment or reducing the scope of works required to be performed by the Supplier, the Buyer shall advise the Supplier, and the Buyer and the Supplier shall, within 5 days, consult concerning the estimated cost and impact on the Delivery schedule and the Contract Price. Thereafter, the Buyer may request, and the Supplier shall, upon receipt of such request and within 14 days |
Page 28
(unless otherwise agreed), prepare a detailed estimate of the cost of such change taking into account the effect of such change on the Plant and/or Services and other agreed upon and contemplated Change Orders. The Buyer shall review the Supplier’s estimate, and if the Buyer accepts or the Parties otherwise agree upon the Change Order (to be evidenced by a Change Order notice signed by both Parties), the Parties shall promptly adjust the scheduled dates of Delivery, Contract Price and any of the Exhibits to this Contract requiring adjustment to reflect such Change Order. | ||
23.2 | Supplier Requested Change Order | |
If the Supplier determines that a condition or the occurrence of an event requires a change in the Plant and/or Services, the Contract Price and/or in date of Delivery due to reasons not specified elsewhere in this Contract, the Supplier shall prepare and deliver to the Buyer a notice for a Change Order, which shall describe such condition or event in detail. Thereafter, the Supplier shall, prepare within 14 days (unless otherwise agreed), a detailed estimate of the cost of such change, taking into account the effect of such change on the Plant and/or Services and other agreed upon and contemplated Change Orders. Within a further 14 days (unless otherwise agreed), the Buyer shall review the Supplier’s estimate and if the Buyer accepts or the Parties otherwise agree upon the Change Order, it shall be endorsed by the Buyer and the Parties shall promptly adjust the scheduled dates of Delivery, Contract Price and any of the Exhibits to this Contract requiring adjustment to reflect such Change Order. | ||
23.3 | Change Orders for Changes of Law | |
If, after the signing of this Contract, there shall be any Change of Law outside the country of manufacturing of the Equipment and/or the Plant, requiring a change in this Contract (including, but not limited to the Equipment and/or the Plant), the Supplier shall prepare a Change Order form. Upon receipt of the Buyer’s written consent, which shall not unreasonably be withheld, such Change Order shall be implemented. If the Supplier reasonably determines that proceeding with its obligations under the Contract without complying with the Change of Law would expose Supplier, its employees, representatives or Subcontractors to any fine, penalty or other punitive action by any Governmental Unit, then provided it gives no less than 5 days written notice to the Buyer, the Supplier shall be entitled to suspend its performance of its obligations under this Contract until the Buyer has issued an appropriate Change Order or the parties have agreed on a mutually acceptable way forward. The Buyer shall indemnify and hold Supplier harmless from and against all claims, costs, damages, fines and expenses, including without limitation legal fees and disbursements, arising out of or related to Supplier’s failure to comply with any Change of Law for which Buyer had not issued a Change Order. | ||
23.4 | Disputes with respect to Change Orders. | |
If the Parties have not reached agreement with respect to the rejection by the Buyer of a Change Order or proper adjustment to the Equipment, the Plant and/or the Services or Contract Price and/or the scheduled dates of Delivery with respect to any event or other occurrence described in clause 23.2 (other than changes in the Equipment, the Plant and/or Services proposed by the Supplier and approved by the Buyer) within thirty (30) days of the Supplier’s notice thereof, the cost or amount, if any, of such adjustment and extension of the scheduled dates of Delivery, if any, shall be determined pursuant to the provisions of clause 21 and if the dispute is not settled through friendly consultations the Parties will follow the procedure set forth in clause 21.3 until the decision in the dispute is given according to the rules of the procedure. This decision shall be final and binding on both Parties unless either of the Parties have within thirty (30) days from the receipt of the said decision has submitted the dispute into the arbitration procedure set forth in clause 21.2. |
Page 29
23.5 | Change Orders Agreed Rates | |
Without prejudice to what has been stated above, unless otherwise agreed, changes to the Plant and/or Services pursuant to Change Orders under this Clause 23 shall be delivered, performed and/or made based on the rates listed below. In the event that no rate has been specified for an item forming part of the scope of a Change Order the adjustment to the Contract Price shall be mutually agreed by the Parties pursuant to the provisions of this Clause. |
Material, equipment, labour and installation works
|
Offer received from respective supplier and/or the Shipyard contractor to be submitted to the Buyer. Cost of this portion shall be based on: Offer received from respective supplier and/or the Shipyard contractor (to be submitted to the Buyer) plus administration fee of plus an agreed profit margin of | |
Transport, where and if applicable
|
Based on actual cost plus administration fee of plus an agreed profit margin of Estimation will be given for a budgetary purpose prior to confirmed Change Order. | |
Engineering cost
|
per each engineering hour | |
Additional advisory services at the Shipyard, where and if applicable
|
Mechanical advisor; per each day Electrical advisor; per each day PLC programmer; per each day. |
|
Above rates include board, lodging, local transportation, profits and administration fees. |
The Parties represent and warrant individually that: |
(1) | it is a company duly incorporated and validly existing under the laws of its place of incorporation; | ||
(2) | it has taken all necessary action to authorize the execution, delivery and performance of this Contract, in accordance with its terms; | ||
(3) | it has power to enter into and perform its obligations under this Contract and to carry out the transactions contemplated by this Contract; | ||
(4) | its obligations under this Contract are valid and binding and are enforceable against it in accordance with respective terms subject to any necessary stamping and registration, the availability of equitable remedies and laws relating to the enforcement of creditor’s rights; | ||
(5) | it has the corporate power to own its own assets and to carry on its business as it is now being conducted; | ||
(6) | it is not the responsible entity of any trust; |
Page 30
(7) | the execution, delivery and performance of this Contract and the transactions under it do not: |
(A) | breach its constitution or other constituent documents; or | ||
(B) | breach any law or decree of any court or official directive which is binding on it; | ||
(C) | cause a limitation on its powers or the powers of its directors or other officers to be exceeded; |
(8) | no litigation, arbitration, tax claim, dispute or administrative or other proceeding (which has not been disclosed to the other Party in writing) has been commenced, is pending or, to its knowledge, threatened in writing aga¡nst it which is likely to have a material adverse effect upon it or its ability to perform its financial or other obligations under this Contract; and |
25.1 | Any and all notices pursuant to this Contract shall be in the English language and can be validly given by either registered mail or courier service to the addresses provided below. Alterations to any address must be conveyed to the other Party in writing in order to become effective. |
The Buyer |
||
Lihir Gold Limited |
||
Attn: Executive General Manager |
Telephone: x000-000-0000 | |
0xx Xxxxx Xxxxxxx Xxxxx |
Telefax: x000-000-0000 | |
Cnr. Xxxxxxxx Xxxxxx & Xxxxxxxx Xxxxxx |
||
X.X. Xxx 000 |
||
Xxxx Xxxxxxx NCD 121 |
||
Papua New Guinea |
||
The Supplier |
||
Wärtsilä Finland Oy |
||
Attn: Project Manager |
Telephone: x000-00-0000000 | |
Tarhaajantie 2 |
Telefax: x000-0-000 9133 | |
X.X. Xxx 000 |
||
Xx-00000 Xxxxx, Xxxxxxx |
On Behalf of the Buyer
|
On Behalf of the Supplier | |
LIHIR GOLD LIMITED
|
WÄRTSILÄ FINLAND OY | |
/s/ Xxxx Xxxxx
|
/s/ Xxxxxxx Xxxxxx | |
Signature
|
Signature |
Page 31
Xxxxx Xxxxx
|
Xxxxxxx Xxxxxx | |
Name (in full)
|
Name (in full) | |
Project Manager, — MOPU
|
General Manager | |
Title
|
Title | |
/s/
Xxxxxx Xxxxxxx
|
/s/ Xxxxx Xxxxxxxxxxx | |
Witness Signature
|
Witness Signature | |
Xxxxxx Xxxxxxx
|
Xxxxx Xxxxxxxxxxx | |
Witness Name (in full)
|
Witness Name (in full) | |
Senior Geothermal Eng.
|
Area Sales Manager | |
Witness Title
|
Witness Title |
Page 32
1. | Scope of supply | |
2. | Technical specification Q0900869 & fire protection specification DBAB103090 | |
3. | Technical data sheets | |
4. | Main flow diagrams: - DBAB070290 – Single line diagram - DBAB070563 – Fuel oil system - DBAB070884 – Lube oil system - DBAB079390 – Compressed air system - DBAB079391 – Cooling system - DBAB079392 – Charge air & exhaust gas system - DBAB079403 – Steam distribution system (inside engine hall) - DBAB104506 – Steam distribution system (outside engine hall) - DBAB105117 – Oily water system - DBAB105118 – Fire fighting system - DBAB105762 – Water supply system |
|
5. | List of suppliers: WDAAA041238 | |
6. | Lay out drawings - 0-000-00000 Plan engine hall - 0-000-00000 Section A-A - 0-000-00000 Plan roof level - 0-000-00000 Tank location plan - 0-000-00000 View from land - 0-000-00000 View from sea |
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Total | TOTAL |
|||||||||||||
A | POWER GENERATION |
|||||||||||||
A1 | GENERATING SET |
|||||||||||||
A1.1 | ENGINE |
|||||||||||||
Wärtsilä 20V32 engine |
8 | x | ||||||||||||
Turbocharger cleaning device |
8 | x | ||||||||||||
A1.2 | GENERATOR, 11 kV / 50 Hz |
|||||||||||||
Generator |
8 | x | ||||||||||||
A1.3 | BASE FRAME |
|||||||||||||
Common base frame |
8 | x | ||||||||||||
Fastening equipment (set) |
8 | x | ||||||||||||
A1.4 | ELASTIC MOUNTING |
|||||||||||||
Steel springs (set) |
8 | x | ||||||||||||
A1.5 | COUPLING |
|||||||||||||
Flexible coupling |
8 | x | ||||||||||||
A1.7 | CONNECTIONS |
|||||||||||||
Flexible connections between engine and external piping |
8 | x | ||||||||||||
- Flexible hoses and gaskets (set) |
1 | |||||||||||||
- Cooling water bellows (set) |
1 | |||||||||||||
- Exhaust gas bellows |
2 | |||||||||||||
- Charge air bellows compensator |
2 | |||||||||||||
A1.8 | PLATFORMS |
|||||||||||||
Engine maintenance platform prefabricated |
8 | x | ||||||||||||
A2 | MECHANICAL AUXILIARY SYSTEMS |
|||||||||||||
A2.0 | AUXILIARY MODULES |
|||||||||||||
Engine auxiliary module with integrated compact booster |
8 | x | ||||||||||||
- Fuel oil filter |
1 | |||||||||||||
- Fuel booster pump |
1 | |||||||||||||
- Return fuel pump |
1 | |||||||||||||
- Fuel oil cooler |
1 | |||||||||||||
- Return fuel tank |
1 | |||||||||||||
- Pre heating unit |
1 | |||||||||||||
- Thermostatic valve high temperature water system |
1 | |||||||||||||
- Thermostatic valve low temperature water system |
1 | |||||||||||||
- Pressure increasing pump |
1 | |||||||||||||
- Steam heater |
1 | |||||||||||||
- Piping and insulation |
1 | |||||||||||||
- Valves and gauges |
1 | |||||||||||||
- Module control panel |
1 | |||||||||||||
Exhaust gas module |
8 | x | ||||||||||||
- Low temperature expansion tank |
1 | |||||||||||||
- Charge air silencer |
2 |
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
- Exhaust gas branch pipe |
1 | |||||||||||||
- Piping and insulation |
1 | |||||||||||||
- Oil mist separator |
1 | |||||||||||||
A2.1 | FUEL SYSTEM |
|||||||||||||
A2.1.1 | LIGHT FUEL OIL SYSTEM |
|||||||||||||
Light fuel oil transfer pump unit, on land |
1 | x | ||||||||||||
Light fuel oil day tank, integrated in barge hull |
1 | x | ||||||||||||
Light fuel oil day tank equipment |
1 | x | ||||||||||||
Light fuel oil feeder unit |
1 | x | ||||||||||||
Light fuel oil flow meter for total fuel consumption measurement |
1 | x | ||||||||||||
Piping and valves light fuel oil system inside engine hall |
1 | x | ||||||||||||
Piping and valves light fuel oil system outside engine hall |
1 | x | ||||||||||||
Piping and valves light fuel oil system outside, on land |
1 | x | ||||||||||||
A2.1.3 | HEAVY FUEL OIL SYSTEM (designed for a maximum fuel viscosity
of 180 cSt) |
|||||||||||||
Heavy fuel oil storage tank, on land |
1 | x | ||||||||||||
Heavy fuel oil transfer pump unit, on land |
1 | x | ||||||||||||
Heavy fuel oil storage tank, integrated in barge hull |
5 | x | ||||||||||||
Heavy fuel oil storage tank equipment |
5 | x | ||||||||||||
Heavy fuel oil transfer pump unit, on power barge |
1 | x | ||||||||||||
Heavy fuel oil storage tank suction heater |
5 | x | ||||||||||||
Heavy fuel oil buffer tank, integrated in barge hull |
1 | x | ||||||||||||
Heavy fuel oil buffer tank equipment |
1 | x | ||||||||||||
Heavy fuel oil separator unit |
2 | x | ||||||||||||
- Separator |
1 | |||||||||||||
- Delivery pump |
1 | |||||||||||||
- Strainer |
1 | |||||||||||||
- Steam heater |
1 | |||||||||||||
- Sludge tank |
1 | |||||||||||||
- Sludge pump |
1 | |||||||||||||
- Steel frame |
1 | |||||||||||||
- Control panel |
1 | |||||||||||||
- Interconnection pipes, flanges, seals and valves |
1 | |||||||||||||
Heavy fuel oil day tank |
1 | x | ||||||||||||
Heavy fuel oil day tank equipment |
1 | x | ||||||||||||
Heavy fuel oil feeder unit |
2 | x | ||||||||||||
Heavy fuel oil flow meter for total fuel consumption measurement |
2 | x | ||||||||||||
Piping and valves heavy fuel oil system inside engine hall |
1 | x | ||||||||||||
Heavy fuel oil trace heating material inside engine hall |
1 | x | ||||||||||||
Heavy fuel oil pipe insulation inside engine hall |
1 | x | ||||||||||||
Piping and valves heavy fuel oil system outside engine hall |
1 | x | ||||||||||||
Piping and valves heavy fuel oil system, on land |
1 | x | ||||||||||||
A2.2 | LUBRICATING OIL SYSTEM |
|||||||||||||
Lubricating oil separator unit |
8 | x | ||||||||||||
Lubricating oil unloading pump unit: fresh oil. |
1 | x | ||||||||||||
Lubricating oil storage tank: fresh oil. Integrated in barge hull |
1 | x | ||||||||||||
Equipment for lubricating oil storage tank: fresh oil |
1 | x | ||||||||||||
Lubricating oil service tank. Integrated in barge hull |
1 | x | ||||||||||||
Lubricating oil service tank equipment |
1 | x | ||||||||||||
Lubricating oil transfer pump unit (mobile) |
1 | x |
Page: 2 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Lubricating oil transfer pump unit (stationary) |
1 | x | ||||||||||||
Lubricating oil storage tank: used oil. Integrated in barge hull |
1 | x | ||||||||||||
Lubricating oil unloading pump unit: used oil |
1 | x | ||||||||||||
Equipment for lubricating oil storage tank: used oil |
1 | x | ||||||||||||
Piping and valves lubricating oil system inside engine hall |
1 | x | ||||||||||||
Pumps, piping and valves lubricating oil system, on land – if
required |
1 | x | ||||||||||||
Automatic lubricating oil top up system inside Power Barge |
1 | x | ||||||||||||
A2.3 | COMPRESSED AIR SYSTEM |
|||||||||||||
Starting air bottle |
2 | x | ||||||||||||
Starting air compressor unit — double |
1 | x | ||||||||||||
Instrument air compressor unit |
2 | x | ||||||||||||
Instrument air bottle |
2 | x | ||||||||||||
Piping and valves compressed air system (set) |
1 | x | ||||||||||||
A2.4 | COOLING SYSTEM |
|||||||||||||
Cooling radiator (set) |
8 | x | ||||||||||||
Cooling radiator legs (set) |
8 | x | ||||||||||||
Epoxy coated fins & frames (coating for leg structure included
in the building structure). |
1 | x | ||||||||||||
Cooling radiator ladder and railings |
8 | x | ||||||||||||
Maintenance water tank unit (fresh water). Integrated in barge
hull |
1 | x | ||||||||||||
Piping and valves maintenance water system (set) |
1 | x | ||||||||||||
Piping and valves cooling system inside engine hall |
1 | x | ||||||||||||
Piping and valves cooling system outside engine hall |
1 | x | ||||||||||||
A2.5 | CHARGE AIR SYSTEM |
|||||||||||||
Charge air filter, frame epoxy coated |
8 | x | ||||||||||||
Ducting charge air system (set) |
16 | x | ||||||||||||
A2.6 | EXHAUST SYSTEM |
|||||||||||||
Exhaust gas silencer |
8 | x | ||||||||||||
Bellows for exhaust gas silencer |
16 | x | ||||||||||||
Ducting exhaust gas system (set) |
8 | x | ||||||||||||
Bellows for exhaust gas ducting |
8 | x | ||||||||||||
Insulation exhaust gas ducting (set) |
8 | x | ||||||||||||
Exhaust gas stack pipe |
8 | x | ||||||||||||
A2.8 | STATION SUPPORT SYSTEM |
|||||||||||||
A2.8.1 | OILY WATER SYSTEM |
|||||||||||||
Oily water transfer pump unit |
3 | x | ||||||||||||
Oily water buffer tank. Integrated in barge hull |
1 | x | ||||||||||||
Oily water feed pump unit |
1 | x | ||||||||||||
Oily water treatment unit |
1 | x | ||||||||||||
Sludge tank. Integrated in barge hull |
1 | x | ||||||||||||
Sludge loading pump unit |
1 | x | ||||||||||||
Piping and valves oily water treatment system (set) |
1 | x | ||||||||||||
Sludge disposal (at Site) |
1 | x | ||||||||||||
A2.8.2 | WATER TREATMENT SYSTEM |
|||||||||||||
Fresh water storage tank. Integrated in the barge hull |
1 | x | ||||||||||||
Raw water storage tank. Integrated in the barge hull |
1 | x |
Page: 3 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Water treatment unit |
1 | x | ||||||||||||
Treated water storage tank. Integrated in the barge hull |
1 | x | ||||||||||||
Water booster unit |
2 | x | ||||||||||||
Piping and valves treated water system (set) |
1 | x | ||||||||||||
A2.8.3 | FIRE FIGHTING SYSTEM |
|||||||||||||
Fire fighting room pump equipment |
1 | x | ||||||||||||
Foam systems for tanks |
1 | x | ||||||||||||
Engine’s + Fuel treatment water mist systems |
1 | x | ||||||||||||
Hydrants and hose cabinets inside |
1 | x | ||||||||||||
MFU’s |
3 | x | ||||||||||||
Hose reels and foam hose reels |
1 | x | ||||||||||||
Switchgear room, CO2 extinguishing system |
1 | x | ||||||||||||
Office, Canteen, Corridor sprinkler syst. |
1 | x | ||||||||||||
Workshop sprinkler syst. |
1 | x | ||||||||||||
Parts store sprinkler syst. |
1 | x | ||||||||||||
Outside hydrants and hose equipment |
1 | x | ||||||||||||
Detection (incl.tanks) |
1 | x | ||||||||||||
Fire fighting main piping and valves |
1 | x | ||||||||||||
Standpipe inside |
1 | x | ||||||||||||
Foam piping |
1 | x | ||||||||||||
All extinguishers (set) |
1 | x | ||||||||||||
Fireman’s outfits and storage lockers |
2 | x | ||||||||||||
UHF radios |
1 | x | ||||||||||||
Fire water tank. Integrated in the barge hull |
1 | x | ||||||||||||
A3 | ELECTRICAL SYSTEMS |
|||||||||||||
A3.1 | MAIN SWITCHGEAR |
|||||||||||||
Main busbar |
2 | x | ||||||||||||
Generator cubicle |
8 | x | ||||||||||||
Neutral point cubicle |
8 | x | ||||||||||||
Bustie cubicle |
2 | x | ||||||||||||
Outgoing feeder cubicle |
6 | x | ||||||||||||
Station auxiliary transformer feeder cubicle |
2 | x | ||||||||||||
Measuring cubicle |
4 | x | ||||||||||||
Generator cubicle cable (set) |
8 | x | ||||||||||||
Generator neutral point cable (set) |
8 | x | ||||||||||||
Trailing cable support systems |
1 | x | ||||||||||||
Outgoing feeder cubicle cable (set) |
6 | x | ||||||||||||
Cable terminations and cable fittings, each for his own
supply |
1 | x | x | |||||||||||
A3.2 | STATION SERVICE SYSTEM |
|||||||||||||
Station auxiliary transformer |
2 | x | ||||||||||||
Blackstart unit |
1 | x | ||||||||||||
- Diesel generating set |
1 | |||||||||||||
- Light fuel oil tank |
1 | |||||||||||||
- Radiator |
1 | |||||||||||||
- Exhaust gas ducting and silencer |
1 | |||||||||||||
- Interconnecting pipes, valves and flanges (set) |
1 | |||||||||||||
- Electric panel |
1 | |||||||||||||
- Steel frame |
1 | |||||||||||||
- Container |
1 | |||||||||||||
Low voltage switchboard |
1 | x |
Page: 4 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Full current isolator switches for electrical motors, if
required (set) |
1 | x | ||||||||||||
Frequency converter (for cooling radiator) |
8 | x | ||||||||||||
Radiator panels |
8 | x | ||||||||||||
Station auxiliary transformer medium voltage cables (set) |
2 | x | ||||||||||||
Station auxiliary transformer low voltage cables (set) |
2 | x | ||||||||||||
Low voltage cables (set) |
1 | x | ||||||||||||
Cable terminations and cable fittings |
1 | x | ||||||||||||
A3.3 | DC SYSTEM |
|||||||||||||
DC system power plant control |
2 | x | ||||||||||||
A3.5 | OUTDOOR SWITCHYARD |
|||||||||||||
Power transformer |
2 | x | ||||||||||||
Common equipment |
1 | x | ||||||||||||
Transformer bay |
2 | x | ||||||||||||
Transmission line bay |
2 | x | ||||||||||||
Trailing cable (set) |
6 | x | ||||||||||||
Remote terminal unit (RTU) |
1 | x | ||||||||||||
Power line carrier (PLC) |
1 | x | ||||||||||||
A3.6 | CONNECTION WITH UTILITY |
|||||||||||||
Overhead distribution line |
1 | x | ||||||||||||
Physical connection with the grid |
1 | x | ||||||||||||
Tariff metering system |
1 | x | ||||||||||||
A3.7 | CONNECTION WITH LOCAL INDUSTRY |
|||||||||||||
Local electrical study |
1 | x | ||||||||||||
Local interconnect study |
1 | x | ||||||||||||
Distribution cable |
1 | x | ||||||||||||
Physical connection with local industry |
1 | x | ||||||||||||
A4 | AUTOMATION SYSTEM |
|||||||||||||
A4.1 | OPERATOR’S STATION |
|||||||||||||
WOIS workstation |
3 | x | ||||||||||||
WISE workstation |
1 | x | ||||||||||||
Uninterrupted power supply (UPS) |
1 | x | ||||||||||||
A4.2 | CONTROL PANELS |
|||||||||||||
Central common control panel |
1 | x | ||||||||||||
Central generating set control panel |
8 | x | ||||||||||||
Differential protection relay |
8 | x | ||||||||||||
Local generating set control panel |
8 | x | ||||||||||||
Automation requirements, hull equipment |
1 | x | ||||||||||||
A4.5 | CABLES AND ACCESSORIES |
|||||||||||||
Control and instrumentation cables |
1 | x | ||||||||||||
A5 | HEAT RECOVERY SYSTEM |
|||||||||||||
A5.1 | STEAM GENERATION SYSTEM |
|||||||||||||
A5.1.1 | STEAM GENERATION SYSTEM FOR FUEL HEATING |
|||||||||||||
Exhaust gas boiler |
3 | x |
Page: 5 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
- Inlet and outlet hoods with inspection doors |
1 | |||||||||||||
- Modulating exhaust gas by-pass damper with actuator |
1 | |||||||||||||
- Manual steam soot blowing equipment |
1 | |||||||||||||
- Shut-off valves |
1 | |||||||||||||
- Blow-down drain |
1 | |||||||||||||
- Safety valve |
1 | |||||||||||||
- Relief valve |
1 | |||||||||||||
- Pressure switches |
1 | |||||||||||||
- Level switches |
1 | |||||||||||||
- Level control device |
1 | |||||||||||||
- Insulation and cladding |
1 | |||||||||||||
- Counter flanges, bots, nuts and gaskets |
1 | |||||||||||||
- Mounting supports |
1 | |||||||||||||
- Boiler service platform |
1 | |||||||||||||
Bellows for exhaust gas boiler |
6 | x | ||||||||||||
Heat recovery container |
1 | x | ||||||||||||
- Feed water tank |
1 | |||||||||||||
- Feed water pump |
2 | |||||||||||||
- Chemical dosing unit |
1 | |||||||||||||
- Blow-down tank |
1 | |||||||||||||
- Local control panel |
1 | |||||||||||||
- Light fuel oil fired boiler for steam generation |
1 | |||||||||||||
- Oil detector |
1 | |||||||||||||
Steam header |
1 | x | ||||||||||||
Condensate tank. Integrated in barge hull |
1 | x | ||||||||||||
Boiler washing water tank. Integrated in barge hull |
1 | x | ||||||||||||
Boiler washing water pump |
1 | x | ||||||||||||
Piping, valves and insulation for steam generation
system for fuel
heating (set) |
1 | x | ||||||||||||
A7 | TOOLS |
|||||||||||||
Engine maintenance tools (set) |
1 | x | ||||||||||||
Engine hand tools (set) |
1 | x | ||||||||||||
Tools for turbocharger (set) |
1 | x | ||||||||||||
HFO separator tools (set) |
1 | x | ||||||||||||
Lubricating oil separator tools (set) |
1 | x | ||||||||||||
A8 | SPARE PARTS |
|||||||||||||
Commission consumable parts for 8 engines |
1 | x | ||||||||||||
A9 | CONSUMABLES
Initial fillings of lubricating oil (in engines and
other equipment), lot |
1 | x | |||||||||||
Initial fillings of lubricating oil tanks, lot |
1 | x | ||||||||||||
Initial fillings of grease, chemicals, water etc for
engines and other
equipment, lot |
1 | x | ||||||||||||
Initial fillings of water tanks, fire water tanks,
fuel oil tanks and
other tanks & storage tanks, lot |
1 | x | ||||||||||||
Fuel oil for commissioning at site |
1 | x | ||||||||||||
B | CIVIL WORKS:HULL (B1) AND STRUCTURES ON CARGO DECK
(B2) |
|||||||||||||
X0 | XXXX |
|||||||||||||
Power barge |
1 | x | ||||||||||||
Barge painting |
1 | x |
Page: 6 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Mooring equipment |
1 | x | ||||||||||||
Platforms, stairs and ladders under deck |
1 | x | ||||||||||||
Steels for mooring structure |
1 | x | ||||||||||||
Transformer area (on shore) |
1 | x | ||||||||||||
Structures under units |
1 | x | ||||||||||||
Manholes |
1 | x | ||||||||||||
Zinc anodes |
1 | x | ||||||||||||
ICCP (cathodic protection) |
1 | x | ||||||||||||
Staging |
1 | x | ||||||||||||
Rubber and teflon for mooring |
1 | x | ||||||||||||
Bollards (on barge) |
1 | x | ||||||||||||
Water tight doors |
1 | x | ||||||||||||
Electrification installation material |
1 | x | ||||||||||||
Towing bracket and Bridle |
1 | x | ||||||||||||
Emergency towing line |
1 | x | ||||||||||||
Remote readouts, operator, control valves for tanks
below deck |
1 | x | ||||||||||||
Level Indicators and alarms for under deck tanks |
1 | x | ||||||||||||
Navigation Lights, temporary for transportation |
1 | x | ||||||||||||
Overflow tank. Integrated in the barge hull |
2 | x | ||||||||||||
Sewage tank. Integrated in the barge hull |
1 | x | ||||||||||||
B2.1 –2.7 | SUPERSTRUCTURES ON CARGO DECK |
|||||||||||||
Power house steel frame and supporting structures |
1 | x | ||||||||||||
External walls |
1 | x | ||||||||||||
Internal walls |
1 | x | ||||||||||||
Intermediate floor |
1 | x | ||||||||||||
Roof |
1 | x | ||||||||||||
Doors |
1 | x | ||||||||||||
Windows |
1 | x | ||||||||||||
Finishing and furnishing |
1 | x | ||||||||||||
Sanitary Installations (inside buildings) |
1 | x | ||||||||||||
Process ventilation, Power plant buildings |
1 | x | ||||||||||||
Comfort ventilation and Air conditioning |
1 | x | ||||||||||||
Equipment (Cranes) |
1 | x | ||||||||||||
Unheated Emergency Safety Shower with additional body
spray
and eye wash. |
3 | x | ||||||||||||
B2.8 | AUXILIARY STRUCTURES |
|||||||||||||
Steel structures for charge air duct support (set) |
1 | x | ||||||||||||
Steel structures for auxiliary equipment support (set) |
1 | x | ||||||||||||
Railing outside building, Aux Platform and Shim
Plates for engine installation (set) |
1 | x | ||||||||||||
Steel structures outside the building (set) |
1 | x | ||||||||||||
Superstructures, exhaust gas stack (set) |
1 | x | ||||||||||||
Superstructures, boiler support (set) |
1 | x | ||||||||||||
B3 | WORKSHOP & WAREHOUSE |
|||||||||||||
Complete workshop & warehouse on land, if required |
1 | x | ||||||||||||
B5 | POWER TRANSMISSION AREAS |
|||||||||||||
B5.3 | SWITCHYARD AREAS |
|||||||||||||
Earthworks and substructures, switchyard |
1 | x |
Page: 7 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Switchyard surface covering |
1 | x | ||||||||||||
Fence, around switchyard |
1 | x | ||||||||||||
B6 | SITE WORKS |
|||||||||||||
Earthworks, soil stabilization (piles, soil reinforcement,
etc.) (if
required) |
1 | x | ||||||||||||
Existing elements on plot (demolition, protection, cleaning,
top soil
removal, etc.) (if required) |
1 | x | ||||||||||||
Earth excavation on plot (if required) |
1 | x | ||||||||||||
Rock excavation on plot (if required) |
1 | x | ||||||||||||
Filling on plot (if required) |
1 | x | ||||||||||||
Remedial work for the ground and / or groundwater
contamination
(if required) |
1 | x | ||||||||||||
Fuel pipes to Plant |
1 | x | ||||||||||||
Water pipe to Plant |
1 | x | ||||||||||||
Lubricating oil pipe to Plant |
1 | x | ||||||||||||
Trailing cables, high voltage (11 kV) and low voltage to/from
Plant |
1 | x | ||||||||||||
Sewage pipe from Plant |
1 | x | ||||||||||||
Telephone line to Plant |
1 | x | ||||||||||||
Access bridges between land and Plant (set) |
1 | x | ||||||||||||
C | SERVICES |
|||||||||||||
C1 | ENGINEERING |
|||||||||||||
Environmental study / modelling |
1 | x | ||||||||||||
Site investigation |
1 | x | ||||||||||||
Preliminary soil investigation |
1 | x | ||||||||||||
Preliminary engineering |
1 | x | ||||||||||||
Basic engineering |
1 | x | ||||||||||||
Detailed mechanical engineering for Supplier’s scope of supply |
1 | x | ||||||||||||
Detailed mechanical engineering for Buyer’s scope of supply |
1 | x | ||||||||||||
Detailed electrical engineering for Supplier’s scope of supply |
1 | x | ||||||||||||
Detailed electrical engineering for Buyer’s scope of supply |
1 | x | ||||||||||||
Detailed civil engineering for Supplier’s scope of supply |
1 | x | ||||||||||||
Detailed civil engineering for Buyer’s scope of supply |
1 | x | ||||||||||||
Detailed engineering of Barge Hull |
1 | x | ||||||||||||
C2 | TECHNICAL ASSISTANCE |
|||||||||||||
C2.1 | TECHNICAL ASSISTANCE DURING INSTALLATION |
|||||||||||||
Advisors during construction phase in the shipyard, lot |
1 | x | ||||||||||||
Travel, board and lodging, local transport and temporary
office for
Supplier’s personnel during the construction phase in the
shipyard,
lot |
1 | x | ||||||||||||
Office space for two Buyers personnel, at the Shipyard |
1 | x | ||||||||||||
Travel, board and lodging, local transport for Buyer’s
personnel
during the construction phase in the shipyard, lot |
1 | x | ||||||||||||
C3 | INSTALLATION AND CONSTRUCTION SERVICES AT SHIPYARD |
|||||||||||||
Installation of mechanical equipment |
1 | x | ||||||||||||
Installation of electrical equipment |
1 | x | ||||||||||||
Installation of safety earthing system |
1 | x | ||||||||||||
Installation of power barge superstructures |
1 | x | ||||||||||||
Installation of, by Buyer, supplied electrical equipment for
incorporation into the Plant |
1 | x |
Page: 8 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
C4 | TESTING AND PRE-COMMISSIONING |
|||||||||||||
C4.1 | WORKSHOP TESTS |
|||||||||||||
Engine test according to standard program |
8 | x | ||||||||||||
C4.3 | PRE-COMMISSIONING AT SHIPYARD |
|||||||||||||
No load tests |
1 | x | ||||||||||||
Advisors for pre-commissioning, lot |
1 | x | ||||||||||||
Travel, board and lodging, local transport and
temporary office for
Supplier’s personnel, lot |
1 | x | ||||||||||||
Office space for two Buyers personnel, at the Shipyard |
1 | x | ||||||||||||
Advisor(s) for pre-commissioning of, by Buyer,
delivered electrical
equipment, lot |
1 | x | ||||||||||||
Travel, board and lodging, local transport for Buyer’s
personnel, lot |
1 | x | ||||||||||||
C6 | DOCUMENTS |
|||||||||||||
C6.1 | PRELIMINARY DESIGN |
|||||||||||||
General site layouts |
3 | x | ||||||||||||
General power house layouts |
3 | x | ||||||||||||
General flow diagram drafts |
3 | x | ||||||||||||
General electrical single line diagram drafts |
3 | x | ||||||||||||
C6.2 | BASIC DESIGN |
|||||||||||||
General site layouts |
3 | x | ||||||||||||
General power house layouts |
3 | x | ||||||||||||
Flow diagram drafts |
3 | x | ||||||||||||
Electrical single line diagram drafts |
3 | x | ||||||||||||
C6.3 | DETAILED DESIGN |
|||||||||||||
Drawings (set) |
3 | x | ||||||||||||
Parts lists (set) |
3 | x | ||||||||||||
P&ID’s |
3 | x | ||||||||||||
C6.4 | FINAL DESIGN |
|||||||||||||
Drawings as built, only updates (set) |
3 | x | ||||||||||||
Electronic copy of as built drawings, only updates (set) |
1 | x | ||||||||||||
C6.5 | USER MANUALS |
|||||||||||||
Station manuals in English |
||||||||||||||
- As hard copy |
3 | x | ||||||||||||
- On digital media |
1 | x | ||||||||||||
- Installed into Wärtsilä Information System (WISE) |
1 | x | ||||||||||||
D | TAXES / DUTIES / PERMITS / INSURANCE |
|||||||||||||
As per contract |
||||||||||||||
Construction all risk insurance in shipyard |
1 | x | ||||||||||||
Construction all risk insurance at Lihir Site |
1 | x | ||||||||||||
E | TRANSPORTATION |
|||||||||||||
E1 | TRANSPORTATION OF ITEMS SUPPLIED BY SUPPLIER |
Page: 9 of 10
Respons | Respons | |||||||||||||
ibility of | ibility of | |||||||||||||
Section | Description | QTY | Supplier | Buyer | ||||||||||
Transportation of equipment from and to sub suppliers |
1 | x | ||||||||||||
Packing and marking of equipment |
1 | x | ||||||||||||
Loading of equipment at place of manufacturing |
1 | x | ||||||||||||
Transportation of equipment from place of manufacturing to
port
of shipment |
1 | x | ||||||||||||
Loading of equipment on ship at port of shipment |
1 | x | ||||||||||||
Ocean freight of equipment from port of shipment to port of
destination (shipyard) |
1 | x | ||||||||||||
Unloading of equipment at port of destination (shipyard) |
1 | x | ||||||||||||
Transportation of Plant from shipyard to Xxxxx Xxxxxxx, Lihir
Island |
1 | x | ||||||||||||
Transportation of Plant from DES Xxxxx Xxxxxxx to mooring
location |
1 | x | ||||||||||||
Freight insurance from place of manufacturing to shipyard |
1 | x | ||||||||||||
Freight insurance from shipyard to Xxxxx Xxxxxxx, Lihir Island |
1 | x | ||||||||||||
Freight Insurance from DES Xxxxx Xxxxxxx to mooring location |
1 | x |
Page: 10 of 10
TECHNICAL SPECIFICATION |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
TABLE OF CONTENTS | ||||||
0 | GENERAL |
5 | ||||
0.1 | EXECUTIVE SUMMARY |
5 | ||||
0.2 | TYPE OF PRODUCT |
6 | ||||
0.3 | MAIN DATA AND CONDITIONS |
6 | ||||
0.4 | OPERATION MEDIA |
6 | ||||
0.5 | SPECIAL FEATURES |
11 | ||||
0.6 | CODES AND STANDARDS |
13 | ||||
A | POWER GENERATION |
15 | ||||
A1 | GENERATING SET |
15 | ||||
A1.1 | ENGINE |
15 | ||||
A1.2 | GENERATOR |
19 | ||||
A1.3 | BASE FRAME |
21 | ||||
A1.4 | ELASTIC MOUNTING |
21 | ||||
A1.5 | COUPLING |
21 | ||||
A1.7 | CONNECTIONS |
21 | ||||
A1.8 | PLATFORMS |
22 | ||||
A2 | MECHANICAL AUXILIARY SYSTEMS |
22 | ||||
A2.0 | AUXILIARY MODULES |
22 | ||||
A2.1 | FUEL SYSTEM |
25 | ||||
A2.1.1 | LIGHT FUEL OIL SYSTEM |
25 | ||||
A2.1.3 | HEAVY FUEL OIL SYSTEM (designed for a maximum fuel viscosity of 180 cSt) |
25 | ||||
A2.2 | LUBRICATING OIL SYSTEM |
27 | ||||
A2.3 | COMPRESSED AIR SYSTEM |
29 | ||||
A2.4 | COOLING SYSTEM |
31 | ||||
A2.5 | CHARGE AIR SYSTEM |
32 | ||||
A2.6 | EXHAUST SYSTEM |
33 | ||||
A2.8 | STATION SUPPORT SYSTEM |
33 | ||||
A2.8.1 | OILY WATER SYSTEM |
33 | ||||
A2.8.2 | WATER TREATMENT SYSTEM |
35 | ||||
A2.8.3 | FIRE FIGHTING SYSTEM |
36 | ||||
A3 | ELECTRICAL SYSTEMS |
37 | ||||
A3.1 | MAIN SWITCHGEAR |
37 | ||||
A3.2 | STATION SERVICE SYSTEM |
38 | ||||
A3.3 | DC SYSTEM |
40 | ||||
A4 | AUTOMATION SYSTEM |
41 | ||||
A4.1 | OPERATOR’S STATION |
41 | ||||
A4.2 | CONTROL PANELS |
45 | ||||
A4.5 | CABLES AND ACCESSORIES |
49 | ||||
A5 | HEAT RECOVERY SYSTEM |
49 | ||||
A5.1 | STEAM GENERATION SYSTEM |
49 | ||||
A5.1.1 | STEAM GENERATION SYSTEM FOR FUEL HEATING |
49 |
This information is confidential and proprietary to Wärtsilä. | Page: 2 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
TABLE OF CONTENTS | ||||||
A7 | TOOLS |
52 | ||||
A8 | SPARE PARTS |
52 | ||||
B | CIVIL WORKS: HULL (B1) AND STRUCTURES ON CARGO DECK (B2) |
53 | ||||
B1 | HULL |
53 | ||||
B1.0 | CLASSIFICATION, REGISTRY AND REGULATIONS |
54 | ||||
B1.1 | TANK CAPACITIES, SHORE CONNECTIONS |
55 | ||||
B1.2 | HYDROSTATICS, STABILITY, PRELIMINARY |
56 | ||||
B1.3 | HULL, LARGE HULL FITTINGS, PAINTING AND CORROSION PROTECTION |
56 | ||||
B1.3.1 | CONSTRUCTION PRINCIPLES |
57 | ||||
B1.3.2 | LARGE HULL FITTINGS |
57 | ||||
B1.3.3. | PAINTING AND GALVANIZING |
57 | ||||
B1.3.4. | CATHODIC PROTECTION |
61 | ||||
B1.3.5. | DRAUGHT MARKS, NAME, MARKING OF PAINTING LINES |
61 | ||||
B1.3.6. | TOWING, BOLLARDS AND MOORING EQUIPMENT — PRELIMINARY INFORMATION |
61 | ||||
B1.3.7 | HULL AND DECK FITTINGS |
62 | ||||
B.2 | SUPERSTRUCTURES ON CARGO DECK |
63 | ||||
B2.1 | DESIGN DATA FOR ON DECK CARGO (POWER HOUSE, STRUCTURES etc.) |
63 | ||||
B2.1.1 | Explanation to abbreviations |
63 | ||||
B2.1.2 | Codes and standards for power barge deck cargo |
63 | ||||
B2.1.3 | Loads |
64 | ||||
B2.1.4 | Other design criteria |
64 | ||||
B2.1.5 | Indoor environment |
65 | ||||
B2.2 | POWER HOUSE — SUPPLY: |
66 | ||||
B2.2.1 | POWER HOUSE STEEL FRAME AND SUPPORTING STRUCTURES |
66 | ||||
B2.2.2 | EXTERNAL WALLS |
67 | ||||
B2.2.3 | INTERNAL WALLS |
68 | ||||
B2.2.4 | SEPARATION WALLS BETWEEN ENGINE 4 AND 5 (ADDITIONALLY PRICED) |
68 | ||||
B2.2.5 | INTERMEDIATE FLOOR |
69 | ||||
B2.2.6 | ROOF |
69 | ||||
B2.2.7 | DOORS |
70 | ||||
B2.2.8 | WINDOWS |
70 | ||||
B2.3 | FINISHING AND FURNISHING |
70 | ||||
B2.3.1 | EXTERNAL WALL FINISHING |
70 | ||||
B2.3.2 | INTERNAL WALL FINISHING |
70 | ||||
B.2.3.3 | FLOOR FINISHING |
70 | ||||
B2.3.5 | TECHNICAL SPACES AND FURNISHING ON MAIN DECK |
71 | ||||
B2.4 | SANITARY INSTALLATIONS AND SAFETY SHOWERS |
72 | ||||
B2.8 | AUXILIARY STRUCTURES |
76 | ||||
B2.8.1 | CHARGE AIR / EXHAUST GAS DUCTING AND BOILER SUPPORT STRUCTURES |
76 | ||||
B2.9 | INTERNAL COMMUNICATION SYSTEM |
77 | ||||
C | SERVICES |
78 | ||||
C1 | ENGINEERING |
78 | ||||
C2 | TECHNICAL ASSISTANCE |
78 |
This information is confidential and proprietary to Wärtsilä. | Page: 3 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
TABLE OF CONTENTS | ||||||
C2.1 | TECHNICAL ASSISTANCE DURING INSTALLATION |
78 | ||||
C2.2 | TECHNICAL ASSISTANCE DURING PRE-COMMISSIONING |
79 | ||||
C3 | INSTALLATION AND CONSTRUCTION SERVICES |
79 | ||||
C4 | TESTING AND COMMISSIONING |
79 | ||||
C4.1 | WORKSHOP TESTS |
79 | ||||
C4.3 | PRE-COMMISSIONING AT SHIPYARD |
79 | ||||
C6 | DOCUMENTS |
80 | ||||
C6.1 | PRELIMINARY DESIGN |
80 | ||||
C6.2 | BASIC DESIGN |
80 | ||||
C6.3 | DETAILED DESIGN |
80 | ||||
C6.4 | FINAL DESIGN |
80 | ||||
C6.5 | USER MANUALS |
81 |
This information is confidential and proprietary to Wärtsilä. | Page: 4 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
0 | GENERAL | |
0.1 | EXECUTIVE SUMMARY | |
General | ||
This technical specification provides the reader with the basic technical data and information required for evaluation of the plant’s technical features and performance, as well as Wärtsilä’s scope of supply. | ||
The proposed power barge is designed, engineered and will be delivered by Wärtsilä Finland Oy in accordance with this technical specification. | ||
The technical data stated in this document are for guidance and evaluation purpose only, any guaranteed performance data is separately stated in the supply contract. | ||
Design and construction | ||
The essence of the design is simplicity, safety and reliability. | ||
The equipment is designed to prevent accidental contact with moving, hot or tensional parts and to minimise ingress of dust and dirt. | ||
The structure and layout design of the Power Barge permits access to all parts for inspection, maintenance and repair. | ||
Wärtsilä quality procedures and test and inspection procedures are applied to ensure product quality throughout the design and manufacturing process. Special attention is paid to engine and auxiliary unit testing, as well as inspection and testing of the final installation. | ||
Wärtsilä’s quality and environmental management systems fulfil and are certified according to ISO 9001:2000 and ISO 14001:2004. | ||
Main parts and devices like panels, valves, pumps, etc. are marked with engraved name plates indicating their item codes used in Wärtsilä documentation and manuals. | ||
English is used in all documents, correspondence and nameplates. | ||
The SI units of measurement are used in all technical documents. | ||
The design and manufacture of Power Barge equipment supplied by Wärtsilä Finland Oy is subject to constant review, and due to improvements and optimisation of materials, design and tooling techniques, manufactured equipment may be improved from the specification given below. |
This information is confidential and proprietary to Wärtsilä. | Page: 5 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Deviations to assumptions made in this specification | ||
If the purchasers requirements, local building codes, zoning requirements, Grid/Interconnection Study, Environmental Impact Assessment, Building Permit Application, Soil investigation, Topographical survey, Contamination evaluation or site Demolition requirements or other random conditions deviate from the assumptions made herein and have an impact on Wärtsilä’s scope of supply, the scope of work shall be reviewed and Wärtsilä shall issue change order request(s) as per the relevant contract clauses. | ||
Project Management and Engineering | ||
The delivery of the power barge will be managed by a dedicated Project Team, comprising a Project Manager who has the overall responsibility for the delivery, who is assisted by Project Engineers for the main technical disciplines. | ||
The Project Team is the single point of contact with the purchaser’s organisation and has full authority to decide technical and commercial issues related to the project on behalf of Wärtsilä Finland Oy. | ||
0.2 | TYPE OF PRODUCT | |
The proposed power barge is designed for base load (cop) operation and is intended for power generation. | ||
Waste heat from the prime movers is used to produce thermal energy in the form of steam for fuel heating. | ||
The power barge is designed to use heavy fuel oil as the main fuel. | ||
Light Fuel Oil is used as alternative fuel. | ||
0.3 | MAIN DATA AND CONDITIONS | |
Configuration | ||
The Power barge is equipped with 8 engines of the Wärtsilä 20V32 type, as the prime mover. | ||
0.4 | OPERATION MEDIA | |
General | ||
To maintain the components and equipment power barge in good operating condition and to minimize wear and tear, it is of outmost importance that all operating media used are of good quality and within the specification given by Wärtsilä. | ||
Below are the main parameters for the major operating media of the power barge. The complete specification and requirements for all needed operating media are given in the Operation and Maintenance Manuals delivered for the power barge. | ||
Fuels | ||
Wärtsilä engines are designed and developed for continuous operation on fuels with a quality within the Recommended Limits described in the column “Engine” below. These values indicate |
This information is confidential and proprietary to Wärtsilä. | Page: 6 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
This information is confidential and proprietary to Wärtsilä. | Page: 7 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Fuel quality limit | ||||||||||
Parameter | Engine | Plant | Unit | Test Method reference | ||||||
Viscosity |
Minimum | CSt at 40°C | ISO 3104 | |||||||
Maximum | ||||||||||
Injection viscosity |
Minimum | Cst | ISO 3104 | |||||||
Maximum | Cst | ISO 3104 | ||||||||
Density |
Maximum | kg/m3 at 15°C | ISO 3675 or 12185 | |||||||
Water |
Maximum | % Vol. | ISO 3733 | |||||||
Sulphur |
Maximum | % mass | ISO 8754or 14596 | |||||||
Ash |
Maximum | % mass | ISO 6245 | |||||||
Vanadium |
Maximum | mg/kg | ISO 14597 or IP 501 or 470 | |||||||
Sodium |
Maximum | mg/kg | ISO 10478 | |||||||
Aluminium + silicon |
Maximum | mg/kg | ISO 14597 or IP 501 or 470 | |||||||
Carbon Residue |
Maximum | ISO 10370 | ||||||||
Asphaltenes |
Maximum | % mass | ASTMD 3279 | |||||||
Flash point (PMCC) |
Minimum | °C | ISO 2719 | |||||||
Pour point |
Maximum | °C | ISO 3016 | |||||||
Used lubricating oil2 |
||||||||||
- Calcium |
Maximum | mg/kg | IP 501 or 470 | |||||||
- Zinc |
Maximum | mg/kg | IP 501 or 470 | |||||||
- Phosphorus |
Maximum | mg/kg | IP 501 or 500 |
1 | Additional properties specified by the engine manufacturer | |
2 | A fuel shall be considered to be free of used lubricating oil (ULO), if one or more of the elements calcium, zinc and phosphorus are below or at the specified limits. All three elements shall exceed the same limits before a fuel shall be deemed to contain ULO. |
This information is confidential and proprietary to Wärtsilä. | Page: 8 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Fuel quality limit | Test Method reference | |||||||||
Parameter | Engine | Plant | Unit | Eq* = equivalent | ||||||
Viscosity |
Maximum | CSt at 50°C | ISO 3104 Eq*: ASTM D- 445 |
|||||||
Injection viscosity |
Minimum | Cst | ISO 3104 | |||||||
Maximum | Cst | ISO 3104 | ||||||||
Density |
Maximum | kg/m3 at 15°C | ISO 3675 or 12185 Eq*: ASTM D-1298 |
|||||||
CCAI-number |
Maximum | ISO 8217, Annex B | ||||||||
Water |
Maximum | % Vol. | ISO 3733 Eq*: ASTM D-95 | |||||||
Sulphur |
Maximum | % mass | ISO 8754 or 14596 Eq*: IP-336 |
|||||||
Ash |
Maximum | % mass | ISO 6245 Eq*: XXXX X- 000 |
|||||||
Xxxxxxxx |
Xxxxxxx | xx/xx | XXX 00000 or IP 501 or 470 Eq*: AAS |
|||||||
Sodium |
Maximum | mg/kg | ISO 10478 Eq*: AAS | |||||||
Aluminium + silicon |
Maximum | mg/kg | ISO 14597 or IP 501 or 470 | |||||||
Carbon Residue |
Maximum | ISO 10370 Eq*: XXXX X- 0000 |
||||||||
Xxxxxxxxxxx |
Xxxxxxx | % mass | ASTMD 3279-90 Eq*: IP143/90 |
|||||||
Flash point (PMCC) |
Minimum | °C | ISO 2719 Eq*: ASTM D-93 | |||||||
Pour point |
Maximum | °C | ISO 3016 Eq*: ASTM D-97 | |||||||
Total Sediment potential |
Maximum | % | ISO 10307-2 Eq*: ASTM D- 4870 |
|||||||
Used lubricating oil3 | ||||||||||
- Calcium |
Maximum | mg/kg | IP 501 or 470 | |||||||
- Zinc |
Maximum | mg/kg | IP 501 or 470 | |||||||
- Phosphorus |
Maximum | mg/kg | IP 501 or 500 |
- CIMAC 2003, Grade K 700
- ISO 8217:2005(E), ISO-F-RMK 700
3 | A fuel shall be considered to be free of used lubricating oil (ULO), if one or more of the elements calcium, zinc and phosphorus are below or at the specified limits. All three elements shall exceed the same limits before a fuel shall be deemed to contain ULO. |
This information is confidential and proprietary to Wärtsilä. | Page: 9 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Viscosity class |
||||||||||||
Viscosity Index (VI) |
minimum | |||||||||||
Alkalinity (BN)4, LFO operation |
mg KOH/g | |||||||||||
Alkalinity (BN)4, HFO operation |
mg KOH/g |
pH at 25°C |
— | |||||||
Conductivity
at 25°C (limit for turbine washing only) |
mS/m | |||||||
Total hardness Ca2+ + Mg2+ |
°dH | |||||||
Silica as
SiO2 |
mg/l | |||||||
Chlorides Cl- |
mg/l | |||||||
Sulphates as SO42- |
mg/l |
Chlorides (Cl-)
|
mg/Nm3 5 | |||||
mass-ppm | ||||||
Hydrogen Sulphide (H2S)
|
µg/Nm3 | |||||
vol.-ppm | ||||||
Sulphur Dioxide (SO2)
|
mg/Nm3 | |||||
vol.-ppm | ||||||
Ammonia (NH3)
|
mg/Nm3 | |||||
vol.-ppm | ||||||
Minimum filtration class
|
EN 779:2002 |
4 | Required alkalinity depends on the used fuel oil. | |
5 | Nm3 given at 0 °C and 1013 mbar |
This information is confidential and proprietary to Wärtsilä. | Page: 10 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
This information is confidential and proprietary to Wärtsilä.
|
Page: 11 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
This information is confidential and proprietary to Wärtsilä.
|
Page: 12 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Description | Code | |||
-
|
Engine test run | ISO 15550 | ||
-
|
Vibrations | ISO 8528 part 9 | ||
-
|
Design | EN 12100 | ||
-
|
Pipe design calculations | EN 13480 and DIN 2413 | ||
Note for Lihir Power Barge: piping on pre-fabricated units, modules, generating sets will be as per manufacturer’s standards. | ||||
Other external piping design standard will be made in accordance with ANSI standard system. | ||||
-
|
Welding | EN 1011 | ||
-
|
Stair and platforms | ISO | ||
-
|
Dimensional standards for installation materials (pipes, beams, etcetera) |
DIN, ISO, SFS and EN | ||
-
|
Pressure equipment | PED 97/23/EC | ||
-
|
Typical material standards | DIN and EN |
DIN:
|
German Standard (Deutsche Institute für Normung) | |
EN:
|
European Standard | |
ISO:
|
The International Organization for Standardization |
Description | Code | |||
-
|
Generator | IEC 60034 | ||
-
|
Transformer, oil type | IEC 60076 | ||
-
|
Transformer, dry type | IEC 60726 | ||
-
|
Enclosure protection | IEC 60529 | ||
-
|
WOIS workstation hardware | IEC 60950 | ||
-
|
WOIS workstation software | Applicable parts of VDE 3699 | ||
-
|
Earthing network | IEEE 80 | ||
-
|
Control panels | IEC 60439-1 | ||
-
|
PLC software | IEC 61131-3 | ||
-
|
Lighting installation | IEC 60589 | ||
-
|
Protection of structures against lightning | IEC 1024 |
This information is confidential and proprietary to Wärtsilä.
|
Page: 13 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
IEC:
|
International Electrotechnical Commission | |
IEEE:
|
Institute of Electrical and Electronics Engineers | |
EN:
|
European Standard | |
VDE:
|
The Association for Electrical, Electronic & Information Technologies |
This information is confidential and proprietary to Wärtsilä.
|
Page: 14 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Length |
||||||
Width |
||||||
Height |
||||||
Weight |
Configuration | V | engine form | ||||
Number of cylinders |
||||||
Cylinder bore |
||||||
Stroke |
6 | The dimensions and weight may vary depending on the generator make and type. |
This information is confidential and proprietary to Wärtsilä.
|
Page: 15 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Speed |
||||||
Mean piston speed |
||||||
Mean effective pressure |
||||||
Swept volume per cylinder |
||||||
Compression ratio |
||||||
Number of inlet valves |
||||||
Number of outlet valves |
||||||
Direction of rotation faced towards flywheel |
||||||
Length |
||||||
Width |
||||||
Height |
||||||
Weight |
This information is confidential and proprietary to Wärtsilä.
|
Page: 16 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
• | Low pressure pipes made of steel | ||
• | High pressure pipes, double wall with common leak alarm | ||
• | Injection pumps, individual for each cylinder | ||
• | Pneumatic stop cylinder at each injection pump | ||
• | Fuel injector in each cylinder | ||
• | Fuel limiter to limit smoke at start up | ||
• | Solenoid valve for fuel limiter at start up |
• | Pipes made of steel | ||
• | Oil sump of wet type | ||
• | Engine driven main lubricating oil pump with pressure regulating valve | ||
• | Pre-lubricating pump with electrical motor | ||
• | Lubricating oil cooler | ||
• | Lubricating oil thermostatic valve | ||
• | Lubricating oil automatic back-flushing fine filter, with integrated safety filter | ||
• | Centrifugal filter to clean the back-flushing oil from the automatic filter | ||
• | Start up/running in filters | ||
• | Non-return valves in oil supply pipes | ||
• | Crankcase ventilation pipe |
This information is confidential and proprietary to Wärtsilä.
|
Page: 17 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
• | Pipes made of steel | ||
• | Starting air master valve, electrically and manually operated | ||
• | Start blocking valve to prevent starting when turning gear is engaged | ||
• | Starting air distributor | ||
• | Starting air valves in A-bank cylinder heads | ||
• | Air container for emergency stop system | ||
• | Flame arrestors |
• | Pipes made of steel | ||
• | Engine driven pump for jacket cooling circuit | ||
• | Engine driven pump for low temperature cooling circuit | ||
• | Non-return valves after circulating pumps |
• | Compressor on the turbocharger | ||
• | 1st stage charge air cooler | ||
• | 2nd stage charge air cooler | ||
• | Fresh water cleaning device for the compressor |
• | Single Pipe Exhaust System (SPEX) exhaust manifold with bellows | ||
• | Flexibly mounted insulation box | ||
• | Turbine on the turbocharger | ||
• | Fresh water turbine washing system |
This information is confidential and proprietary to Wärtsilä.
|
Page: 18 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
• | Pneumatic starting fuel limiter and load ramp controller | ||
• | Electro-pneumatic overspeed trip device | ||
• | Speed measuring system, with magnetic pick-ups for engine an turbocharger speed |
• | Fuel oil before the engine | ||
• | Lubricating oil before lubricating oil cooler | ||
• | Lubricating oil after lubricating oil cooler | ||
• | Cooling water before engine | ||
• | Cooling water after turbocharger | ||
• | Cooling water after engine | ||
• | Cooling water before the charge air cooler | ||
• | Cooling water after charge air cooler | ||
• | Cooling water after the lubricating oil cooler | ||
• | Charge air in the air receiver | ||
• | Exhaust gas after each cylinder |
• | Flywheel with fixing bolts | ||
• | Electrical motor driven turning device | ||
• | Counter flanges for pipe connection | ||
• | Indicator valves in the cylinder heads | ||
• | Safety valves in cylinder head | ||
• | Terminal box for electric cables | ||
• | The engine has one coat of priming paint and one coat of finishing paint |
Generator apparent power |
|||||
Rated power factor |
|||||
Nominal voltage |
|||||
Rated current (In) |
|||||
Voltage adjustment range |
|||||
Frequency |
|||||
Speed |
|||||
Overspeed |
|||||
Continuous short circuit current |
This information is confidential and proprietary to Wärtsilä.
|
Page: 19 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Insulation class
|
F | |
Temperature rise
|
B | |
Cooling method
|
Air cooled | |
Enclosure
|
IP23 | |
Standard
|
IEC60034 |
Voltage regulation accuracy |
||
- within power range |
||
- within speed range |
||
Voltage setting range |
This information is confidential and proprietary to Wärtsilä.
|
Page: 20 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
6 | PT-100 elements in stator windings | ||
2 | PT-100 elements for bearings | ||
1 | Anti condensation heater | ||
1 | Voltage transformer for excitation power and measurement | ||
1 | Current transformer for measurement | ||
3 | Current transforms for protection |
This information is confidential and proprietary to Wärtsilä.
|
Page: 21 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
• | Starting/control air | ||
• | Cooling water | ||
• | Lubricating oil | ||
• | Exhaust gas | ||
• | Fuel | ||
• | Crankcase ventilation |
1 | Flexible hoses and gaskets (set) | ||
1 | Cooling water bellows (set) | ||
2 | Exhaust gas bellows | ||
2 | Charge air bellows compensator |
This information is confidential and proprietary to Wärtsilä.
|
Page: 22 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Fuel oil filter | ||
1 | Fuel booster pump | ||
1 | Return fuel pump | ||
1 | Fuel oil cooler | ||
1 | Return fuel tank | ||
1 | Pre heating unit | ||
1 | Thermostatic valve high temperature water system | ||
1 | Thermostatic valve low temperature water system | ||
1 | Steam heater | ||
1 | Piping and insulation | ||
1 | Valves and gauges | ||
1 | Module control panel: | ||
The module control panel includes breakers and controls for the electrical motors and heaters of the engine generator set as indicated below. It is also equipped with indicating lamps and alarms. The panel controls the following motors and heaters (if applicable): |
This information is confidential and proprietary to Wärtsilä.
|
Page: 23 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
§ | Generator anti-condensation heaters | ||
§ | Prelubricating oil pump | ||
§ | Fuel booster pump | ||
§ | Turning gear motor | ||
§ | Preheating circulating pump | ||
§ | High temperature cooling circuit preheaters | ||
• | Air filters (if motorised) | ||
§ | Outlet socket 16A |
2 | Charge air silencer | ||
1 | Exhaust gas branch pipe | ||
1 | Piping and insulation | ||
1 | Oil mist separator |
This information is confidential and proprietary to Wärtsilä.
|
Page: 24 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Electric motor driven light fuel oil feeder pump |
Capacity, each |
||||||
Pressure |
1 | Single strainers on feeder pump suction side | ||
2 | Pressure regulating valve | ||
1 | Local control panel | ||
1 | Steel frame | ||
1 | Set of interconnection pipes, flanges, seals and valves |
Accuracy |
This information is confidential and proprietary to Wärtsilä.
|
Page: 25 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Separator |
Capacity |
1 | Delivery pump | ||
1 | Strainer |
1 | Steam heater |
1 | Sludge tank | ||
1 | Sludge pump | ||
1 | Steel frame | ||
1 | Control panel |
1 | Interconnection pipes, flanges, seals and valves |
This information is confidential and proprietary to Wärtsilä.
|
Page: 26 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
2 | Heavy fuel oil feeder unit |
1
|
Electric motor driven heavy fuel oil feeder pump | |||||||
Capacity | m3/h | |||||||
Pressure | bar | |||||||
1
|
Single strainers on feeder pump suction side | |||||||
2
|
Pressure regulating valve | |||||||
1
|
Local control panel | |||||||
1
|
Steel frame | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves | |||||||
The following is included: |
1 | Heavy fuel oil feeder pump | ||
1 | Automatic filter | ||
1 | Manual by-pass filter | ||
1 | Viscosity control system | ||
2 | Heavy fuel oil flow meter for total fuel consumption measurement |
1 | Piping and valves heavy fuel oil system on Power Barge |
1 | Heavy fuel oil trace heating material on Power Barge |
A2.2 | LUBRICATING OIL SYSTEM | |
The lubricating oil system provides required lubrication for all moving parts on the engine. It consists of the engine related lubricating oil system which handles the cooling and filtration of the lubrication oil and the plant related lubricating oil system, with storage of new and old lubrication oil. | ||
The lubricating oil system consists of the following equipment: |
This information is confidential and proprietary to Wärtsilä. | Page: 27 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
8 | Lubricating oil separator unit |
1
|
Separators of automatic discharge type | |||||||
Capacity | m3/h | |||||||
1
|
Separator delivery pumps | |||||||
Single strainers on pump suction side | ||||||||
1
|
Steam heater for the lubricating oil | |||||||
1
|
Sludge tank | |||||||
1
|
Sludge pump | |||||||
1
|
Steel frame | |||||||
1
|
Local control panel for manual and automatic operation | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
1 | Lubricating oil unloading pump unit: fresh oil |
1
|
Electric motor driven unloading pumps | |||||||
Capacity, each | m3/h | |||||||
1 |
Pressure Suction filters on pump suction side |
bar | ||||||
1
|
Pressure gauges at inlet and outlet pipe | |||||||
1
|
Steel frame | |||||||
1
|
Local control panel | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
1 | Lubricating oil transfer pump unit (mobile) |
1
|
Electric motor driven transfer pump | |||||||
Capacity, each | m3/h | |||||||
Pressure | bar | |||||||
1
|
Single strainers on pump suction side | |||||||
1
|
Thermometer on pump suction side | |||||||
1
|
Local control panel | |||||||
1
|
Wheeled dolly | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
This information is confidential and proprietary to Wärtsilä. | Page: 28 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Lubricating oil transfer pump unit (stationary) |
2
|
Electric motor driven transfer pump | |||||||
Capacity, each | m3/h | |||||||
Pressure | bar | |||||||
1
|
Single strainer on pump suction side | |||||||
1
|
Local control panel | |||||||
1
|
Steel frame | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
1 | Lubricating oil unloading pump unit: used oil |
1
|
Electric motor driven unloading pumps | |||||||
Capacity, each | m3/h | |||||||
Pressure | bar | |||||||
1
|
Suction filters on pump suction side | |||||||
1
|
Pressure gauges at inlet and outlet pipe | |||||||
1
|
Steel frame | |||||||
1
|
Local control panel | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
1 | Piping and valves lubricating oil system inside Power Barge |
1 | Automatic lubricating oil top up system inside Power Barge |
A2.3 | COMPRESSED AIR SYSTEM | |
Compressed air is used for starting the engines and for control and instrument air. | ||
Starting air is produced by the starting air compressor unit. Compressed air from the starting air unit is stored in starting air bottles until it is used for starting the engine. The pressure equipment is designed, manufactured and tested according to the European Union directive 97/23/EC “Pressure Equipment Directive”. | ||
The starting air system consists of the following main equipment: |
This information is confidential and proprietary to Wärtsilä. | Page: 29 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
2 | Starting air bottle |
Capacity
|
m3 | |||||
Pressure
|
bar |
1 | Starting air compressor unit — double |
1
|
Electric motor driven air compressor | |||||||
Capacity, each | m3/h | |||||||
Pressure | bar | |||||||
1
|
Electric motor driven air compressor | |||||||
Capacity, each | m3/h | |||||||
Pressure | bar | |||||||
1
|
Pressure switch for starting and stopping the electrically driven air compressor (24/30 bar) | |||||||
1
|
Alarm switch for too low starting air pressure to engine (18 bar) | |||||||
1
|
Oil and water separator | |||||||
1
|
Control centre for manual and automatic operation | |||||||
1
|
Pressure reduction valve for control and working air (30/6 bar) | |||||||
1
|
Steel frame | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
This information is confidential and proprietary to Wärtsilä. | Page: 30 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
2 | Instrument air compressor unit |
1
|
Electrically driven air compressor | |||||||
Capacity, each | m3/h | |||||||
Pressure | bar | |||||||
1
|
Compressed air receiver | |||||||
Volume | m3 | |||||||
1
|
Refrigerated air dryer with control panel | |||||||
Dew point | °C | |||||||
1
|
Filter for removal of oil, water and particles | |||||||
1
|
Common control panel | |||||||
1
|
Steel frame | |||||||
1
|
Set of interconnection pipes, flanges, seals and valves |
2 | Instrument air bottle |
Capacity
|
m3 | |||||
Pressure
|
bar |
1 | Piping and valves compressed air system (set) |
This includes pipes, valves, flanges and gaskets for the compressed air system up to the interconnection point. | ||
A2.4 | COOLING SYSTEM | |
The main task of the cooling system is to provide adequate cooling of critical engine components such as cylinder jackets, cylinder heads and turbochargers as well as to cool the lubrication oil and charge air entering the cylinders after it has been compressed by the turbocharger. | ||
The engine cooling water cools the low temperature charge air cooler, lubricating oil cooler, high temperature charge air cooler and engine jackets in a common single-circuit radiator. | ||
The cooling system consists of the following main equipment: |
8 | Cooling radiator sets |
1
|
Radiator cooler circuit | |||
Frame material | ||||
Tube material | ||||
Fin material |
This information is confidential and proprietary to Wärtsilä. | Page: 31 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Noise level | 61 dB(A) at 40 m distance |
A2.5 | CHARGE AIR SYSTEM |
This information is confidential and proprietary to Wärtsilä. | Page: 32 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
A2.6 | EXHAUST SYSTEM |
Noise attenuation
|
Diameter
|
||||||
Material
|
||||||
Height above ground level
|
A2.8 | STATION SUPPORT SYSTEM | |
A2.8.1 | OILY WATER SYSTEM |
This information is confidential and proprietary to Wärtsilä. | Page: 33 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1
|
Oily water pump (air driven) | |||||||
Capacity | m3/h | |||||||
1
|
Local control panel for switch-over between manual and automatic operation | |||||||
1
|
Set of interconnecting pipes and equipment | |||||||
1
|
Steel frame |
1 | Oily water feed pump unit |
1 | Oily water treatment unit |
1
|
Set of interconnecting piping, valves and necessary gauges and sensors | |
1
|
Pump for transfer of oily sludge and separated bottom solids | |
1
|
Pump for transfer of pre-treated water to the stage two | |
1
|
Buffer tank or basin for separated oil with level controllers | |
1
|
Intermediate tank or basin for pre-treated water with level controllers | |
1
|
Discharge pump for treated water | |
1
|
Activated Carbon filter for final polishing of the effluent | |
1
|
Set of heating equipment | |
1
|
Set of pumps for chemical dosing | |
1
|
Local control panel |
1 | Sludge unloading pump unit |
1
|
Oily water pump (pneumatic) | |||||||
Capacity | m3/h | |||||||
1
|
Set of interconnecting pipes and equipment | |||||||
1
|
Local control panel for Manual operation |
This information is confidential and proprietary to Wärtsilä. | Page: 34 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Piping and valves oily water treatment system (set) |
A2.8.2 | WATER TREATMENT SYSTEM |
Capacity | m3/h | |||||||
1
|
Sand filters 2 x 100% capacity | |||||||
1
|
Softening unit with 2 x 100% capacity softeners (with NaCl tank) | |||||||
1
|
Safety cartridge filter with 5 micron mesh size | |||||||
1
|
Vertical multistage centrifugal high pressure feed pump | |||||||
1
|
Reverse osmosis housings and membranes | |||||||
1
|
Chemical cleaning tank and pump | |||||||
1
|
Local control panel for the system | |||||||
1
|
Set of interconnection pipes flanges and valves |
pH at 21°C
|
||||
Total dissolved solids
|
||||
Total hardness Ca2+ + Mg2+
|
||||
Silicate as SiO2
|
||||
Iron Fe
|
||||
Suspended solids
|
1
|
Pressure tank | |||||||
Capacity | l | |||||||
Pressure | bar(a) | |||||||
2
|
Multi stage centrifugal pump | |||||||
Capacity | m3/h | |||||||
Pressure | bar(a) |
This information is confidential and proprietary to Wärtsilä. | Page: 35 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1
|
Local control panel with frequency converters for pumps | |
1
|
Steel frame | |
1
|
Set of interconnection pipes flanges and valves |
1 | Piping and valves treated water system (set) |
A2.8.3 | FIRE FIGHTING SYSTEM |
This information is confidential and proprietary to Wärtsilä. | Page: 36 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Fire fighting room pump equipment | ||
1 | Foam systems for tanks | ||
1 | Engine’s + Fuel treatment water mist systems | ||
1 | Hydrants and hose cabinets inside | ||
3 | MFU’s | ||
1 | Hose reels and foam hose reels | ||
1 | Switchgear room, CO2 extinguishing system | ||
1 | Office, Canteen, Corridor sprinkler syst. | ||
1 | Workshop sprinkler syst. | ||
1 | Parts store sprinkler syst. | ||
1 | Outside hydrants and hose equipment | ||
1 | Detection (incl.tanks) | ||
1 | Fire fighting main piping and valves | ||
1 | Standpipe inside | ||
1 | Foam piping | ||
1 | All extinguishers (sets) | ||
2 | Firemans outfits and storage lockers | ||
1 | UHF radios | ||
1 | Fire fighting tank, 300 m3 |
A3 | ELECTRICAL SYSTEMS |
A3.1 | MAIN SWITCHGEAR |
8 | Neutral point cubicle |
Consisting of: |
1 | Neutral grounding resistor 5A, 10s | ||
1 | Single pole disconnector switch | ||
2 | Current transformer (single phase) for earth fault |
This information is confidential and proprietary to Wärtsilä. | Page: 37 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
8 | Generator cubicle cable (set) |
8 | Generator neutral point cable (set) |
1 | Trailing cable support systems |
1 | Cable terminations and cable fittings for Wärtsilä supplied cables |
A3.2 | STATION SERVICE SYSTEM |
2 | Station auxiliary transformer |
Rated power
|
kVA | |||||
Rated incoming voltage +2x2.5%
|
V | |||||
Rated outgoing voltage
|
V | |||||
Standard
|
||||||
Cooling
|
• | Voltage bushings | ||
• | Thermometer with two signal contacts | ||
• | Off-load tap changer, 5 positions, on MV-side | ||
• | Earthing terminal | ||
• | Rollers | ||
• | Lifting and towing lugs |
1 | Blackstart unit |
This information is confidential and proprietary to Wärtsilä. | Page: 38 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Diesel generating set |
Capacity
|
||
Frequency
|
1 | Light fuel oil tank | ||
1 | Radiator | ||
1 | Exhaust gas ducting and silencer | ||
1 | Interconnecting pipes, valves and flanges (set) | ||
1 | Electric panel |
• | Main breaker with short circuit and overload protection | ||
• | Control system for automatic start/stop at grid failure/recovery | ||
• | Alarm system with basic alarm functions | ||
• | Monitoring system |
1 | Steel frame | ||
1 | Container |
2 | Frequency converter (for heavy fuel oil feeder pump) | ||
1 | Frequency converter (for light fuel oil feeder pump) | ||
8 | Frequency converter (for cooling radiator) |
2 | Station auxiliary transformer medium voltage cables (set) |
2 | Station auxiliary transformer low voltage cables (set), (see low voltage cable section for details) |
This information is confidential and proprietary to Wärtsilä. | Page: 39 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
8 | Radiator panels | ||
1 | Low voltage cables on power barge (set) |
- phase L1
|
Red | |
- phase L2
|
White | |
- phase L3
|
Blue | |
- Neutral
|
Black (or light blue) | |
- Protect earthing, PE
|
Yellow/Green |
1 | Cable terminations and cable fittings for Wärtsilä supplied cables |
A3.3 | DC SYSTEM |
2 | DC system Power Barge control |
1 | Battery set |
|||||||||
Type
|
||||||||||
Capacity
|
Ah | |||||||||
Voltage (DC)
|
V | |||||||||
2 | Charger(s) |
|||||||||
Charging current each
|
A | |||||||||
1 | Distribution switchboard containing: |
|||||||||
Battery main switch |
||||||||||
DC system monitoring unit |
||||||||||
Miniature circuit breakers for DC feeders |
1 | DC cables on power barge (set), |
- ´+´ (positive)
|
Grey | |
- ´ -´ (negative)
|
Xxxxx |
This information is confidential and proprietary to Wärtsilä. | Page: 40 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
A4 | AUTOMATION SYSTEM |
• | MW mode — the generating set power is maintained at a preset value irrespective of system load or frequency. This is the typical operating mode for a base load Power Barge supplying an infinite grid. | ||
• | Isochronous load sharing — the generating set shares the load with other generating sets at a constant frequency. This is the typical operating mode when running in isolation from the grid. This operating mode requires that all the generating sets have speed controllers suitable for isochronous load sharing. | ||
• | Speed droop mode — the generating set shares the load with the grid or other generating sets according to a speed droop curve. This is the typical operating mode for smaller grids or in island operation. |
• | Constant Power Factor control — the generating sets power factor is maintained at a preset value and any changes are produced by the grid or other generating sets. This is the typical operating mode for a base load Power Barge supplying an infinite grid. | ||
• | Voltage droop compensation control — The generating set will share the reactive load with the other generating sets based on digital communication lines between the AVR’s when running in island mode. This is the typical operating mode when running in isolation from the grid. This operating mode requires that all the generating sets have voltage controllers suitable for voltage droop compensation control. | ||
• | Voltage droop mode — the generating set will share the reactive load with the grid and other generating sets equally in relation to the size of the units. This is the typical operating mode for smaller grids or in island operation. |
A4.1 | OPERATOR’S STATION |
This information is confidential and proprietary to Wärtsilä. | Page: 41 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
3 | WOIS workstation |
The Power Barge is controlled and supervised from the Wärtsilä Operator Interface System (WOIS workstation). All actions necessary for the normal operation, such as start and stop of the generating sets, load increase and load reduction are activated and supervised via the WOIS workstation, using a mouse, keyboard and display. The operator can also supervise key data from the plant such as various temperatures and pressures as well as measurements of electrical variables such as generator power, voltage and frequency. The WOIS workstation also includes a hardcopy laser printer. | ||
WOIS workstation includes the following functionality: |
• | Process status displays, where the status and operation of the processes are displayed using various dynamic objects, such as images of pumps, valves and other components and units. The status of these objects is displayed graphically. By interacting with an object, the function and operational status can be displayed. | ||
• | Process trends can be displayed as a free combination of six (6) measured values such as pressures, temperatures, speed, generating set load, etc. The operator may combine the values of interest in one graph to get a good view of the total process for further analysing. The trends are stored for up to 180 days, and the operator may call back a trend for any time interval within these limits. | ||
• | An alarm banner in the uppermost part of the displays informs about the latest occurred alarm. The active alarm list informs the operator of possible problems in the process. An alarm will remain on the active alarm list until the process has returned to normal state and the alarm has been acknowledged. Historical alarm and event lists can be called up for further evaluation of events. | ||
• | Any of the displays and the alarm list can be printed to the hard copy printer. |
This information is confidential and proprietary to Wärtsilä. | Page: 42 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Figure 8
|
The picture above is an example of a set of typical WOIS workstation displays; The Plant Overview display, a process displays, a sensor trend display, a historical trend display and the alarm event display |
1 | Desktop PC computer, 1 GB RAM, min. 80 GB HDD, min 2 GHz processor | ||
1 | Display, TFT Flatscreen 24” with the resolution of 1920x1200 | ||
1 | Keyboard and optical mouse | ||
1 | Operating system | ||
1 | Human-Machine-Interface (HMI) software |
1 | Laser printer for hardcopy and report printing | ||
1 | WISE workstation |
This information is confidential and proprietary to Wärtsilä. | Page: 43 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
• | Daily engine and plant reports of plant analogue measurement values. Daily minimum, maximum and average values are generated and stored for one year. | ||
• | Long term engine and plant performance tracking throughout trend displays of the reported analogue measurements. | ||
• | Daily production reports of generated active and reactive energy as well as hourly fuel consumption are generated and stored for one year. | ||
• | Monthly production reports (on daily level) are stored for 5 years and yearly production reports are generated and stored for 10 years. | ||
• | The production reports include minimum, maximum, average and total sum calculations for the period. | ||
• | Electronic log book with search possibilities for recording of operation and maintenance activities. |
Figure 9
|
The above picture shows a typical WISE workstation daily operation data, production report and Log book |
1 | Desktop PC, 1 GB RAM, min. 80 GB HDD, min 2 GHz processor | ||
1 | Display, TFT Flatscreen 24” with the resolution of 1920x1200 | ||
1 | Keyboard and optical mouse | ||
1 | Operating system software | ||
1 | Reporting interface software |
This information is confidential and proprietary to Wärtsilä. | Page: 44 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | Uninterrupted power supply (UPS) |
A4.2 | CONTROL PANELS |
1 | Central common control panel |
Figure 10 The above illustration shows an example of the central common control panel |
1 | Programmable Logic Controller (PLC) unit for plant control and supervision of the common systems of the plant. The high grade PLC integrates the control functions as required by the process and operation sequences. | ||
The PLC include the following units and devices: |
- | Power supply for CPU (110 VDC) | ||
- | Central Processing Unit (CPU) | ||
- | Communication card | ||
- | Digital input and output cards | ||
- | Analogue input cards |
This information is confidential and proprietary to Wärtsilä. | Page: 45 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | P1 Double frequency meter (for synchronising) | ||
1 | P2 Double voltage meter (for synchronising) | ||
1 | P3 Synchronoscope (for synchronising) | ||
1 | M2 Manual syncronisation control interface unit with: |
- | Synchronising mode selector switch (auto/manual) | ||
- | Synchronising breaker selector switch for generator and for incoming breaker | ||
- | Generating set voltage adjustment switch | ||
- | Generating set frequency adjustment switch | ||
- | Synchronising breaker close control pushbutton | ||
- | Synchronising order pushbutton for automatic synchronising |
1 | Auto-synchroniser | ||
1 | Check synchroniser relay | ||
1 | Safety relay for emergency circuit | ||
1 | Mimic diagram for the electrical system | ||
1 | S20 Emergency stop pushbutton | ||
1 | S10 Safety relay reset pushbutton |
8 | Central generating set control panel |
This information is confidential and proprietary to Wärtsilä. | Page: 46 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Figure 11 The above illustration shows an example of the central generating set control panel |
1 | Programmable Logic Controller (PLC) unit for control and supervision of the generating set. The high grade PLC integrates the control functions as required by the process and operation sequences. The PLC also handles the start/stop sequence, process measurements and alarms |
- | Power supply unit for CPU (110 VDC) | ||
- | Central Processing Unit (CPU) | ||
- | Communication card | ||
- | Analogue measurement Input — Output card | ||
- | Digital Input — Output cards |
1 | Set of conventional panel mounted meters for: |
- | P1-P3 Current meters, one per phase | ||
- | P4 Frequency meter | ||
- | P5 Voltage meter, with selector switch S21 | ||
- | P6 Engine and turbocharger speed (rpm), with selector switch S22 | ||
- | P7 Power factor meter | ||
- | P8 Reactive power (MVAr) meter | ||
- | P9 Active power (MW) meter |
This information is confidential and proprietary to Wärtsilä. | Page: 47 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
1 | S20 Generating set emergency stop push-button | ||
1 | P11 Power monitoring unit (PMU) | ||
The PMU is a digital power monitoring unit where the generating sets electrical measurements can be monitored and supervised. | |||
The PMU includes the following functions: |
- | Measurement of phase currents, with stored min and max | ||
- | Measurement of main and phase voltages, with stored min, max and average | ||
- | Measurement of frequency | ||
- | Calculation of Active, Reactive and Apparent power | ||
- | Calculation of Active and reactive Energy, imported, exported and total | ||
- | Calculation of harmonic distortions | ||
- | Calculation of power factor | ||
- | Measurement of engine running hours |
1 | K1 Generator protection relay | ||
The digital programmable multi-function protection relay is connected to current and voltage transformers in the generator cubicle and in the generators main terminal box. | |||
The protection relay has the following protection functions: |
- | Over and under voltage protections | ||
- | Over and under frequency protection | ||
- | Reverse power protection | ||
- | Over current and short circuit protection | ||
- | Stator earth fault protection | ||
- | Loss of excitation protection | ||
- | Negative sequence (unbalance) over current protection |
1 | K2 Differential protection relay | ||
1 | M1 Manual control interface unit with: |
- | Generator set control mode selector switch (Auto-Manual) | ||
- | Active power control mode selector switch (Speed droop-kW/isoch control ) | ||
- | Reactive power control mode selector switch (Voltage droop — p.f. control) | ||
- | Engine power control switch (decrease-increase) | ||
- | Generator voltage control switch (decrease-increase) | ||
- | Synchronising select and start of synchronisation control switch | ||
- | Engine start pushbutton with engine running indication light | ||
- | Engine stop pushbutton with engine stopped indication light | ||
- | Breaker close pushbutton with breaker closed indication light | ||
- | Breaker open pushbutton with breaker opened indication light | ||
- | Engine shutdown indication light with reset pushbutton | ||
- | Breaker trip indication light with reset pushbutton | ||
- | Indication lamp testing pushbutton |
8 | Local generating set control panel |
1 | Remote Input-Output unit for PLC |
- | Power supply unit (24 VDC) |
This information is confidential and proprietary to Wärtsilä. | Page: 48 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
- | Remote communication card | ||
- | Digital Input — Output cards | ||
- | Analogue Input — Output cards |
1 | Automatic voltage regulator (AVR) for the generator | ||
1 | S1 Emergency stop push-button | ||
1 | Safety relay for emergency circuit |
A4.5 | CABLES AND ACCESSORIES |
1 | Control and instrumentation cables (as per Wärtsilä standard) |
A5 | HEAT RECOVERY SYSTEM |
A5.1 | STEAM GENERATION SYSTEM |
A5.1.1 | STEAM GENERATION SYSTEM FOR FUEL HEATING |
3 | Exhaust gas boiler |
Steam generation
|
kg/h saturated steam | |
- at feed water temperature
|
°C | |
Working steam pressure
|
bar(a) |
1 | Inlet and outlet hoods with inspection doors | ||
1 | Modulating exhaust gas by-pass damper with actuator |
This information is confidential and proprietary to Wärtsilä. | Page: 49 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
1 | Manual steam soot blowing equipment | ||
1 | Shut-off valves | ||
1 | Blow-down drain | ||
1 | Safety valve | ||
1 | Relief valve | ||
1 | Pressure switches | ||
1 | Level switches | ||
1 | Level control device | ||
1 | Insulation and cladding | ||
1 | Counter flanges, bots, nuts and gaskets | ||
1 | Mounting supports | ||
1 | Boiler service platform |
This information is confidential and proprietary to Wärtsilä. | Page: 50 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
• | Evaporator section | ||
• | LFO burner | ||
• | LFO pump | ||
• | Combustion air fan | ||
• | Steam pressure gauge | ||
• | Pressure switches | ||
• | Temperature switches | ||
• | Level control device | ||
• | Main closing valve for steam | ||
• | Non-return valve at steam outlet | ||
• | Safety valves | ||
• | Local control panel | ||
• | Interconnection pipes, flanges and gaskets |
Steam generation | kg/h saturated steam | |||||||
- at feed water temperature | °C | |||||||
Working steam pressure | bar(a) |
This information is confidential and proprietary to Wärtsilä. | Page: 51 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
A7 | TOOLS |
A8 | SPARE PARTS |
This information is confidential and proprietary to Wärtsilä. | Page: 52 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
B | CIVIL WORKS: HULL (B1) AND STRUCTURES ON CARGO DECK (B2) | |
This Civil’s technical specification provides the reader with the basic technical data and information required for evaluation of the plant’s technical features and performance, as well as Wärtsilä’s Civil’s (Superstructure) scope of supply. | ||
The proposed project is designed, engineered and will be delivered by Wärtsilä Finland Oy in accordance with this technical specification. | ||
B1 | HULL | |
General | ||
The construction is made according to the requirements of Classification Society and considering the results of vibration and noise studies. The hull is designed for power generation. All structures, stiffening and reinforcements are designed to carry the actual loads of eight (8) W20V32 generating sets and related auxiliaries. | ||
Materials | ||
Mild steel, material grade A, is used for hull structures in general. All hull materials are approved by the Classification Society. | ||
Standard materials, fittings and equipment are used as far as practicable, if not otherwise mentioned, in order to achieve easy maintenance and low replacement cost. | ||
All materials, equipment, appurtenances and outfit which are supplied by the Wärtsilä are new, good quality, suitably selected for the purpose they are to serve and especially taking into account the service intended for the Barge and of well recognized make and of the latest type or model at the time of ordering within the limits of this specification. | ||
Construction tests | ||
Structural strength and watertightness of decks, bulkheads, hatchway covers, weather and splashtight doors, ventilator coamings, tanks and piping systems are tested to assure effective performance. tanks are tested using industrial fresh water. | ||
Workmanship and welding | ||
The hull is of fully welded construction corresponding to the requirements of the Classification Society. | ||
Below main deck rooms and technical spaces: |
• | Fuel treatment room | ||
• | Sewage room | ||
• | Bilge water central (preliminary); | ||
Containing bilge pump and valves. All compartions in the hull is connected by pipes to the bilge water central. The bilge water is pumped to the oily water settling tank.The preliminary location of the bilge water central is under the fuel treatment room. The access is from the fuel treatment room. | |||
• | Oily water treatment room | ||
• | Water treatment room | ||
• | Air-, sounding-, bilge-, (ballast if applicable) and draining pipes | ||
• | Tanks |
This information is confidential and proprietary to Wärtsilä. | Page: 53 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
Permanent stairs, ladders, doors, manholes, scuttles, bolted plates, etc. are provided for access. Ladders and stairs are bolted or otherwise easily removable in external and machinery spaces.
Battens and gratings in store rooms and other spaces and protective casings around pipes are made readily removable.
The class xxxx is:
• | International Convention on Load Lines 1966 (LL 1966) (701 81.01.E), Supplement relating to the LL 1966 (1971, 1975, 1979) (705 81.02.E) | ||
• | International Convention on Tonnage Measurement of Ship, 1969 (TONNAGE 1969) (713 70.81.E) |
This information is confidential and proprietary to Wärtsilä. | Page: 54 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
• | International Tonnage convention Oslo 1965 |
B1.1 | TANK CAPACITIES, SHORE CONNECTIONS | |
Filling volumes are (100%), total : |
Heavy fuel oil buffer tanks (1)
|
||
Heavy fuel oil day tank (1+1)
|
||
Diesel oil day tank (1)
|
||
New lubricating oil storage tank (1)
|
||
Used lubricating oil tank (1)
|
||
Maintenance (service) lubricating oil tank (1)
|
||
Sludge tank (1)
|
||
Maintenance water tank (1)
|
||
Raw water tank (1)
|
||
Fresh water tank (1)
|
||
Treated water tank (for fresh water) (1)
|
||
Sewage tank (1)
|
||
Over flow tank (2)
|
||
Boiler washing tank (1)
|
||
Oily water tank (1)
|
This information is confidential and proprietary to Wärtsilä. | Page: 55 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
Fire fighting tank (1)
|
||
Ballast water tanks
|
If required is depending of on final design |
Used lubrication oil / sludge | DN65 | |||
Lubrication oil filling | DN50 | |||
Diesel oil filling | XX00 | |||
XXX filling | DN100 | |||
Fire water | DN80 |
Sewage | DN65 | |||
Fresh water filling | DN50 |
B1.2 | HYDROSTATICS, STABILITY, PRELIMINARY | |
The possible ballasting is executed according to the stability and trim calculations. The calculation, design and need of ballast tanks are depending on final design. | ||
B1.3 | HULL, LARGE HULL FITTINGS, PAINTING AND CORROSION PROTECTION |
This information is confidential and proprietary to Wärtsilä. | Page: 56 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
B1.3.1 | CONSTRUCTION PRINCIPLES | |
Strength and material thicknesses of the hull | ||
Hull strength criteria is according to Classification Rules. | ||
Plates exposed to compression stresses are provided with adequate buckling strength. | ||
Preliminary hull thicknesses: side plate 10 mm, bottom plate 12 mm and deck plate 12 mm | ||
B1.3.2 | LARGE HULL FITTINGS | |
Engine foundations | ||
Generator set foundations are integrated to steel structure | ||
Machinery foundations | ||
Foundations are fabricated of steel plates and rolled sections. | ||
Girders or extra webs are fitted below heavy machinery and power house supporting pillars. | ||
B1.3.3. | PAINTING AND GALVANIZING | |
General | ||
All steel material with thickness of 4 mm and over is shot blasted to Sa21/2 according to International standard ISO 8501-1 and primed with 2-component zincrich prefabrication primer 12 — 20 my. | ||
The detailed painting specification will be subject to the shipyard finally selected as the constructor and their used paint manufacturer. However, please find below preliminary specification. The detailed painting specification will be sent to the Owners for approval a reasonable time before painting work is started. | ||
The specification states the accuracy for the treatment of surfaces, the type of paint, colour scheme, number of coats and coating thickness. | ||
Data given by the paint manufacturer regarding the specified painting systems is
followed. Where painting is not specified, it is done according to the Shipyard’s practice after Owners’ approval. |
||
Preparation system according to International standards ISO 8501-1, ISO 8501-2 Dry film thickness (DFT) is the thickness of coating remaining on surface when coating is hardened. Nominal dry film thickness (NDFT) is specified for each coat or for the whole paint system to achieve the required durability. |
||
Measurement of total dry film thickness is done according to ISO 12944-5 standard. |
This information is confidential and proprietary to Wärtsilä. | Page: 57 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
Before top | ||||||
Preparation | coats | Final inspection | ||||
Exterior |
||||||
Below WL
|
BPO | BPO | BPO | |||
Above WL
|
BPO | BPO | BPO | |||
Decks
|
BPO | BPO | BPO | |||
Interior |
||||||
Fresh water tanks
|
BPO | BPO | BPO | |||
Water and dry tanks
|
BPO | B O | B O | |||
Oil tanks
|
BPO | B O | BPO | |||
Other spaces
|
B O | B O |
The Builder and Paint Manufacturer make control of weather conditions.
ISO 8501-01 | Light wire brushing Weld spatter not to be removed No chamfering |
ISO 8501-1 | Wire brushing to St 2 Loose spatter to be removed No chamfering |
This information is confidential and proprietary to Wärtsilä. | Page: 58 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
ISO 8501-1 | Blasting to Sa 2 Loose spatter to be removed No chamfering |
ISO 8501-1 | Blasting to Sa 2.5 – 2 Loose spatter to be removed Light chamfering |
Cleaning grade | Sa 2.5 – 2 | |||||
Painting (typical) | Jotamastic 87 Aluminium | 1 × 150 µm | ||||
Jotamastic 87 grey | 1 × 150 µm | |||||
total | 300 µm |
Cleaning grade | St 2 | |||||
Painting (typical) | Jotamastic 87 grey | 1 × 150 µm | ||||
Hardtop AS, polyurethane topcoat |
||||||
1 × 50 µm | ||||||
total | 200 µm |
Cleaning grade | St 2 | |||||
Painting (typical) | Jotamastic 87 grey | 1 × 125 µm | ||||
Jotamastic 87 | 1 × 125 µm | |||||
total | 250 µm |
This information is confidential and proprietary to Wärtsilä. | Page: 59 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
Cleaning grade | St 2 | |||||
Painting (typical) | Balloxy HB Light | 2 × 150 µm | ||||
total | 300 µm |
Cleaning grade | St 2 | |||||
Painting (typical) | Balloxy HB Light | 2 × 150 µm | ||||
total | 300 µm |
Cleaning grade | St 2 | |||||
Painting (typical) | Balloxy HB Light | 2 × 150 µm | ||||
total | 300 µm |
Cleaning grade | St 2 | |||||
Painting (typical) | Jotun alkyd primer | 1 × 60 µm | ||||
Total | 60 µm |
Cleaning grade | St 2 |
This information is confidential and proprietary to Wärtsilä. | Page: 60 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: | August 25, 2009 |
Painting (typical) | Balloxy HB Light | 2 × 150 µm | ||||
Total | 300 µm |
Cleaning grade | St 2 | |||||
Painting (typical) | Jotun alkyd primer | 1 × 50 µm | ||||
Pilot II | 1 × 50 µm | |||||
total | 100 µm |
B1.3.4. | CATHODIC PROTECTION | |
Cathodic protection system | ||
To avoid need for docking the hull is protected against corrosion by means of Impressed Current type Cathodic protection system (ICCP), Corrpro brand or equal internationally recognized brand. Using ICCP is an arrangement of hull mounted anode(s) (type and number at final design) and four reference cells (number at final design) connected to a control panel, the ICCP system produces a powerful impressed external current to suppress the natural electrochemical activity on the wetted surface of the hull. | ||
B1.3.5. | DRAUGHT MARKS, NAME, MARKING OF PAINTING LINES | |
Draught marks | ||
Draught marks fore, aft and midship, freeboard and loadline marks are made of steel plate continuously welded on the shell and painted. Draught marks are indicated in metric numbers. | ||
Name | ||
The name is fitted on each side of bow. Name and port of registry is fitted on aft transom centerline. Names are made of steel plate continuously welded on the shell and painted. The Seaboard name will be placed on both sides of the power plant building, made of steel plate, approximately 1 meter high letter size. | ||
B1.3.6. | TOWING, BOLLARDS AND MOORING EQUIPMENT – PRELIMINARY INFORMATION | |
General | ||
According to ABS or GL rules. |
This information is confidential and proprietary to Wärtsilä. | Page: 61 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Towing and brackets | ||
• Two xxxxx brackets are installed on the bow for towing the Power Barge |
||
• One emergency towing line |
||
Bollards | ||
• 3 bollards are installed on each side of the hull for mooring |
||
Mooring arrangement and equipment on Power Barge | ||
The design of the mooring system to be based on actual conditions on the final location of the Barge. | ||
• One set of rubber and teflon for mooring, if required |
||
B1.3.7
|
HULL AND DECK FITTINGS | |
In general, fittings and connections on weather deck are protected by painting. | ||
Exterior Steel Doors, part of hull | ||
Doors are constructed and installed according to rules and standards. Watertight doors are equipped with rubber packing, two hinges and six latches, an eyelet for padlock and hand grip. | ||
• clear width min.750 mm |
||
• minimum height 1900 mm from the deck |
||
• sill height in way of watertight doors according to rules |
||
Manholes | ||
Manhole and ladder are arranged for all tanks as required. Clear opening is minimum 400 * 600 mm. All manholes are clearly and permanently marked with a name and number of tank/space. | ||
Access and Service Hatches, Inspection Openings | ||
Clear opening is minimum 600 x 600 mm. Sill height minimum 400 mm if not otherwise required by the rules. | ||
Stair, Ladders and Steps | ||
Ladders or steps are provided in way of manholes or access opening where necessary, width 400 mm minimum. Short ladders may be arranged by hook steps welded to the hull. Stairs, ladders and steps are arranged according to general drawings. | ||
Platforms | ||
Platforms are arranged in technical spaces. Platforms are made of chequered steel plate or steel grating fastened with screws. | ||
Railings | ||
The height of rail or bulwark above the deck is about 1100 mm around the hull. Stanchions and wire ropes or chains are arranged in a way of bollards and where necessary but only in limited length. |
This information is confidential and proprietary to Wärtsilä. | Page: 62 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Drain Plugs | ||||
Drain plugs of stainless steel are provided to all tanks to the lowest point with clear markings. | ||||
Lifting Eyes | ||||
Lifting eyes are provided above all heavy equipment and elsewhere where necessary. | ||||
B.2 | SUPERSTRUCTURES ON CARGO DECK | |||
B2.1 | DESIGN DATA FOR ON DECK CARGO (POWER HOUSE, STRUCTURES etc.) | |||
B2.1.1 | Explanation to abbreviations | |||
ASHRAE: | American Society of Heating, Refrigeration and Air-Conditioning Engineers | |||
EN: | European Standard | |||
ENV: | European Pre-standard | |||
FEM: | European Federation of Materials Handling and Storage Equipment | |||
ISO: | International Organization for Standardization | |||
SFS: | Finnish Standards Association | |||
AISI | American Iron and Steel Insitute | |||
UBC: | Uniform Building Code |
B2.1.2 | Codes and standards for power barge deck cargo | |||||||
The Power House superstructures are designed, manufactured, constructed and installed to applicable parts according to the following standards: | ||||||||
Description | Code | Note | ||||||
- | Wind load, seismic load | UBC 1997 | ||||||
- | Steel structures | SFS-ENV 1993-1-1...4 | Eurocode 3 | |||||
- | Self supporting double skin metal faced insulating panels-Factory made products- Specifications (wall panels) |
EN 14509 | ||||||
- | Installation of pre-manufactured buildings | European Norms and ISO standards | ||||||
- | Ventilation | ASHRAE 62.1-2004 | ||||||
- | Air conditioning | ASHRAE 55-2004 | ||||||
- | Crane classification and design | FEM | ||||||
- | Painting of steel structures | EN ISO 12944 | ||||||
Galvanization | EN ISO 1461 | |||||||
- | Stairs and platforms (standard) | EN ISO 14122 | Fixed stairs and platforms | |||||
- | Noise measurement | ISO 1996, Acoustics Description, measurements and assessment of environmental noise, Part 1-3 |
This information is confidential and proprietary to Wärtsilä. | Page: 63 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
B2.1.3
|
Loads | |
The civil works and structures are designed for the following loads: |
Description | Value | Unit | Code | Note | ||||||||
Wind | ||||||||||||
- |
Basic wind speed | mph | UBC1997 | Measured as 3 sec. gust | ||||||||
- |
Exposure | |||||||||||
- |
Importance factor | |||||||||||
Earthquake | UBC1997 | |||||||||||
Note! Concerns only mooring | ||||||||||||
system. The Barge and Power | ||||||||||||
- |
Seismic zone | House is not designed for earth | ||||||||||
quake loads | ||||||||||||
- |
Occupancy category | |||||||||||
- |
Soil profile | |||||||||||
- |
Importance factor | |||||||||||
- |
Seismic source, type | |||||||||||
- |
Min. distance to fault | km | ||||||||||
Live load | ||||||||||||
- |
Roof | kN/m2 | UBC1997 | Including snow load | ||||||||
- |
Floor (Barge Deck) | kN/m2 | Distributed load | |||||||||
kN | Concentrated 200x200 mm2 | |||||||||||
- |
Intermediate floor | UBC1997 | ||||||||||
Store area | kN/m2 | Distributed load | ||||||||||
kN | Concentrated 200x200 mm2 | |||||||||||
Control Room / office | ||||||||||||
area | kN/m2 | Distributed load | ||||||||||
kN | Concentrated 200x200 mm2 | |||||||||||
- |
Working platforms | kN/m2 | UBC1997 | |||||||||
kN | Distributed load | |||||||||||
Concentrated 200x200 mm2 | ||||||||||||
Dead load | ||||||||||||
- |
Material | According to material weights | ||||||||||
- |
Equipment | According to Wärtsilä and other manufacturer specifications |
||||||||||
Load combinations | UBC1997 |
Wärtsilä Power Barge design fulfil general international requirements for structural safety. |
This information is confidential and proprietary to Wärtsilä. | Page: 64 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
B2.1.4
|
Other design criteria |
Description | Value | Unit | Code | Note | ||||||||||
Noise | ||||||||||||||
- |
Noise level | dB(A) | ISO 1996 | At 100 m from wall | ||||||||||
- |
Noise level in Control | dB(A) | ISO 1996 | |||||||||||
Room and offices | ||||||||||||||
Temperatures and relative humidity | ||||||||||||||
- |
Max. ambient air | °C | Design ambient 30 °C | |||||||||||
temperature | ||||||||||||||
- |
Min. ambient air | °C | ||||||||||||
temperature | ||||||||||||||
- |
Dimensioning relative | % | At 30 °C ambient | |||||||||||
humidity, RH | ||||||||||||||
Rainfall | ||||||||||||||
- |
Maximum rainfall | mm/h | ||||||||||||
Other | ||||||||||||||
- |
Dust level |
* | ISO 1996 Acoustics — Description, measurement and assessment of environmental noise, Parts 1-3 |
B2.1.5
|
Indoor environment |
Maximum | ||||||||||||||
noise | Min. / max. | Illumination | ||||||||||||
level | temperature | level | ||||||||||||
Area | dB(A) | °C | AC | Ventilation | Lux | |||||||||
Engine Hall
|
— | Ambient /Ambient+10 (except for hot spots) | No | Mechanical | 200 | |||||||||
Engine hall, maintenance platform, Auxiliary
equipment areas
|
— | Ambient /Ambient+10 (except for hot spots) | No | Mechanical | 300 | |||||||||
Fuel treatment room/pump
rooms
|
— | Ambient /Ambient+10 (except for hot spots) | No | Mechanical | 300 | |||||||||
Switchgear room(s)
|
85 | 20-28 | Yes | Mechanical | 250 | |||||||||
Control room
|
65 | 20-24 | Yes | Mechanical | 500 | |||||||||
Offices (and corresponding)
|
65 | 20-24 | Yes | Mechanical | 500 | |||||||||
Canteen (and correcponding)
|
65 | 20-24 | Yes | Mechanical | 150 – 200 | |||||||||
Changing room(s), toilet(s),
cleaning cupboard(s)
|
65 | 22-26 | Yes | Mechanical | 150 – 200 | |||||||||
Battery room
|
65 | 18 °C/ Ambient+5 |
No | Mechanical | 150 – 200 | |||||||||
Workshop)s), Store room(s), Technical rooms |
— | 18 °C/ Ambient+10 |
No | Mechanical | 150 – 200 | |||||||||
Electrical Workshop
|
— | Ambient | Yes | Mechanical | 150 – 200 | |||||||||
Stairhall
|
85 | 22-26 | Yes | Mechanical | 150 – 200 |
This information is confidential and proprietary to Wärtsilä. | Page: 65 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
B2.2 | POWER HOUSE — SUPPLY: | |||||
1 | Power house steel frame and supporting structures (set) — see B2.2.1 for more details | |||||
1 | External walls (set) — see B2.2.2 for more details | |||||
1 | Internal walls (set) — see B2.2.3 for more details | |||||
1 | Separation walls between engine 4 and 5 (set) — see B2.2.4 for more details | |||||
1 | Intermediate floor (set) — see B2.2.5 for more details | |||||
1 | Roof (set) — see B2.2.6 for more details | |||||
1 | Doors (set) — see B2.2.7 for more details | |||||
1 | Windows (set) — see B2.2.8 for more details | |||||
1 | Finishing and furnishing — see B2.3 for more details | |||||
1 | Heating and Sanitary Installations (inside buildings) (set) — see B2.4 for more details | |||||
1 | Process ventilation, Power plant buildings (set) — see B2.5 for more details | |||||
1 | Comfort ventilation and Air conditioning (set) — see B2.6 for more details | |||||
1 | Equipment (cranes etc) — see B2.7 for more details | |||||
B2.2.1 | POWER HOUSE STEEL FRAME AND SUPPORTING STRUCTURES | |||||
Material for building steel frame and other steel structures | ||||||
The material characteristics are: |
Description | Grade | Code | Note | |||||
Steel profiles and fasteners | ||||||||
-
|
Steel plates > 3 mm | EN10025 | ||||||
-
|
I, H and U sections | EN10025 | ||||||
-
|
L sections | EN10025 | Primary profiles | |||||
EN10025 | Secondary profiles | |||||||
-
|
Welded hollow sections | EN10219 | ||||||
-
|
Bolts | EN ISO 4014 | Hot-dip galvanized | |||||
-
|
Nuts | EN ISO 4032 | Hot-dip galvanized | |||||
-
|
Washers | EN ISO 7091 | Hot-dip galvanized |
Surface treatment | ||
Surface treatment is based on the quality document “Anti-corrosive treatment instructions for auxiliary equipment” for Wärtsilä Power Barge. Actual document is made based on ISO standards 8501 (Pre-treatment), 12944 (Corrosion protection of steel structures by protective paint system, 2808 (Determination of film thickness). |
This information is confidential and proprietary to Wärtsilä. | Page: 66 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
The surface treatment for indoor structural steel frame components | ||
The painting system for indoor steel structures, , fulfill corrosivity categories C2M, C3L. according to EN ISO 12944 (treatment EP120/2-FESa2,5 or equivalent). The preliminary treatment class is FeSa2,5 according to EN ISO 8501. | ||
The surface treatment for outdoor structural steel frame components | ||
The painting system for outdoor steel structures, fulfill corrosivity category C5-M according to EN ISO 12944: treatment EPZn(R)EPPUR240/4-FESa2,5 or equivalent – note: additionally priced. The preliminary treatment class is FeSa2,5 according to EN ISO 8501 The steel frame is made of shop painted shopfabricated steel profiles. Installation is done with bolted connections. The columns are welded to the deck. | ||
STAIRS AND PLATFORMS | ||
In the engine hall, on the xxxxx wall, fixed to the steel frame, is a service platform for the overhead crane. Other platforms are ventilation unit / charge air platform and stack platform. Generally platforms are included where so required from maintenance point of view. The frame material and surface treatment of the platform frame and railing are similar to structural steel frame. The landings and platforms inside power house are covered with hot-dip galvanized gratings (Class A, approximately 80 microns – EN ISO 1461). The landings and platforms outside are painted. | ||
B2.2.2
|
EXTERNAL WALLS | |
External walls of light weight sandwich panels | ||
Material characteristics | ||
The material characteristics for the wall sandwich panel materials are: |
Description | Grade | Code | Note | |||||
-
|
Outer steel sheet face | EN10147 | Galvanized and PVDF-HB coil coated and lacquer | |||||
-
|
Structural mineral wool | Load bearing capacity | ||||||
-
|
Inner steel sheet face | EN10147 | Galvanized PE coil coated |
The technical information for the sandwich panels are: |
Description, 100 mm panels | Value | Unit | ||||||
-
|
Fire rating | 60 minutes | ||||||
-
|
Noise reduction, RW | dB | ||||||
-
|
Thermal insulation l | W / m2K |
This information is confidential and proprietary to Wärtsilä. | Page: 67 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
External walls of light weight sandwich panels | ||
The external walls are made of shopfabricated mineral wool insulated lightweight sandwich type panels. The surface metal sheets are bonded to the structural mineral wool to form an integrated structural sandwich panel. The panel thickness is 100 mm | ||
The panels are fixed with bolts or screws to the steel frame. The joints between the frame and panels are sealed with elastic rubber packing. The vertical joints between the panels are sealed up with mineral wool strips and covered with shaped steel flashings. The surface metal sheets of the panels and steel sheet flashings are galvanized and plastic coil coated at shop. | ||
B2.2.3
|
INTERNAL WALLS | |
Walls of light weight sandwich panels | ||
The material characteristics for the wall sandwich panel materials are: |
Description | Grade | Code | Note | |||||
-
|
Structural mineral wool | Load bearing capacity | ||||||
-
|
steel sheet faces (both sides) | EN10147 | Galvanized PE coil coated |
The technical information for the standard 100 mm thick sandwich panels are: |
Description | Value | Unit | ||||||
-
|
Fire rating | minutes | ||||||
-
|
Noise reduction, RW | dB | ||||||
-
|
Thermal insulation l | W / m2K |
The internal walls are made of shopfabricated mineral wool insulated lightweight sandwich type panels, similar to the external walls. The panel thickness is 100 mm | ||
The panels are fixed with bolts or screws to the steel frame. The joints between the frame and panels are sealed with elastic rubber packing. The vertical joints between the panels are sealed up with mineral wool strips and covered with shaped steel flashings. The surface metal sheets of the panels and steel sheet flashings are galvanized and plastic coil coated at shop. | ||
Wall between engine hall and control room | ||
In wall between the Engine Hall and the Control room and office area is fire rated 1 hour (EI 60). | ||
Noise requirement 65 dB(A) in Control room/ office areas | ||
The wall is a double light weight panel wall with 50 mm thick mineral wool in the airgap in between. The mineral wool boards are fastened to the Control room / office side wall. | ||
B2.2.4
|
SEPARATION WALLS BETWEEN ENGINE 4 AND 5 (ADDITIONALLY PRICED) | |
The engine hall will be separated by installing two walls between engine #4 and #5. The central common access / lay-down area between the separation walls is enlarged (final width according to the plan layout). The lower part of the walls are made with light weight wall panels (same as |
This information is confidential and proprietary to Wärtsilä. | Page: 68 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
other walls). The upper part is openable to allow overhead crane and load to traverse when required. The noise reduction is in the region of 25...30 dB(A). | ||||
B2.2.5 | INTERMEDIATE FLOOR | |||
The intermediate floor secondary structures are generally made with steel cassettes (steel sheets with stiffeners) on secondary steel frame The joints between the cassettes are welded. | ||||
The cassettes are used as such in the Store areas abobe the workshop. If necessary checkered plates may be used. | ||||
The intermediate floor for the Workshop as well as the whole Control room / Office / Canteen area is build “floating” as follows: | ||||
- | Steel cassettes on secondary steel frame | |||
- | Hard mineral wool 30 mm (15 kPa) | |||
- | Plywood boards 21 mm, tongued and grooved, glued to each other | |||
- | Plastic carpet (see finishing part) | |||
The material characteristics are: |
Description | Grade | Code | Note | |||||
-
|
Steel plates, L- and U- sections | EN10025 | ||||||
-
|
Structural mineral wool | Load bearing capacity |
The changing rooms, toilets and shower are are with a sloped concrete slab (40...70 mm) on top of the steel cassettes. | ||
B2.2.6
|
ROOF | |
Roof structure, Engine Hall with radiators on the roof | ||
The roof structure consists of load bearing steel profiles, perforated (15 %) for noise attenuation. The structure is insulated with mineral wool 100 mm. The roofing is with welded plain metal sheets 5 mm, sandblasted and painted after installation, the painting system is the same as for outdoor steel structures (note: additional paint supply will be additionally priced) | ||
Material characteristics |
Description | Grade | Code | Note | ||||||
-
|
Steel plates | EN10025 | |||||||
-
|
mineral wool | ||||||||
-
|
Load bearing steel sheet | EN10147 | Galvanized |
This information is confidential and proprietary to Wärtsilä. | Page: 69 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 August 25, 2009 |
Gutters and downpipes | ||
The eave gutters and down spouts are, where used, made of coil coated metal sheets. | ||
B2.2.7
|
DOORS | |
The doors are metal plated mineral wool insulated steel doors. Doors between Engine Hall and surrounding areas are fire rated. Other fire rated doors where required. The doors will be supplied with handles and hinges with bearings. Part of the doors are supplied with shutter and lock with serial keys. The material characteristics of the door frame and metal plates are similar to the structural steel frame. | ||
Surface treatment is based on the quality document “Anti-corrosive treatment instructions for auxiliary equipment” for Wärtsilä Power Barge. Actual document is made based on ISO standards 8501 (Pre-treatment), 12944 (Corrosion protection of steel structures by protective paint system, 2808 (Determination of film thickness). The painting treatment for doors fulfill the same corrosity category as for the surrounding steel frame (Note: if treatment EPZn(R)EPPUR240/4-FESa2,5 or equivalent it will be additionally priced). | ||
B2.2.8
|
WINDOWS | |
The windows are with shop painted aluminium profile frame and double glazing. Part of the windows are fixed, part with casement. | ||
Windows between Engine Hall and surrounding areas are fire rated. If the wall between the engine hall and other areas is a double wall the windows are double with separate frames. | ||
B2.3
|
FINISHING AND FURNISHING | |
B2.3.1
|
EXTERNAL WALL FINISHING | |
Light weight wall panels | ||
Panels are coil coated at shop. | ||
B2.3.2
|
INTERNAL WALL FINISHING | |
Light weight panels | ||
Panels are coil coated at shop. | ||
B.2.3.3
|
FLOOR FINISHING | |
Painted floors in buildings | ||
Floors are painted 2 times with an epoxy paint. | ||
Following rooms are with epoxy painting: Engine Hall, Workshops, Store rooms and areas of similar use. |
This information is confidential and proprietary to Wärtsilä. | Page: 70 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: Document creation date: |
Power Supply Upgrade. LGL P0900329 Q0900869 XXX000 Xxxxxx 00, 0000 |
Xxxxx with plastic carpet | ||
The carpet used is a 2 mm thick homogenous plastic carpet with welded seams.
Following rooms are with plastic carpet Control room, office areas, canteen, corridor(s), Electrical Workshop, changing rooms and toilets. |
||
Raised floor | ||
The switchgear room(s) has a raised floor (access floor) with a steel structure supporting the floor and the electrical panels | ||
The floor surface is a 2 mm thick antistatic plastic carpet with welded seams on plywood boards | ||
B2.3.4
|
CEILING | |
Suspended ceiling | ||
The acoustical panels are used in the suspended ceiling of the control room, office areas,
canteen corridors, changing room and toilet areas. The panels are on mineral wool base.
The suspended ceiling in changing room and toilet areas are moisture resistive. |
||
Other | ||
Ceiling of other areas are unpainted. |
B2.3.5 | TECHNICAL SPACES AND FURNISHING ON MAIN DECK | |||||||||
• | Switchgear room | |||||||||
• | Locker room with toilets: | |||||||||
The changing rooms have lockers and benches | ||||||||||
• | Store for parts: | |||||||||
Light duty rack section (Xxxxxx or equivalent), 8 pcs., estimated size: 715x715X900 | ||||||||||
o | Robust design | |||||||||
o | Easy to assemble | |||||||||
o | 7 shelf levels | |||||||||
• | Mechanical workshop: | |||||||||
Heavy duty workbench with boxes, 4 pcs., estimated size: 1500x700 | ||||||||||
o | Top of workbench covered with sheet metal | |||||||||
o | Including heavy duty set of drawers. | |||||||||
Heavy duty closet with boxes, 2 pcs., estimated size: 715x715X900 |
This information is confidential and proprietary to Wärtsilä. | Page: 71 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
o | Robust design | ||
o | Including heavy duty set of drawers. | ||
o | Equipped with wheels. |
• | Electrical workshop: |
o | Robust design | ||
o | Easy to assemble | ||
o | 7 shelf levels |
• | Compressor air room | ||
• | Office: |
• | Toilets |
• | Canteen |
• | Control room: |
• | Open storage area: |
o | Robust design | ||
o | 7 shelf levels |
B2.4 | SANITARY INSTALLATIONS AND SAFETY SHOWERS |
Emergency shower / eye washing station is installed in Engine Hall and Workshop.
This information is confidential and proprietary to Wärtsilä. | Page: 72 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
3 | Emergency Safety Shower |
B2.5 | PROCESS VENTILATION, POWER BARGE BUILDINGS |
- | Electric motor (frequency converter controlled) driven axial fan Air flow per unit 30,0 m3/s Static pressure 150 Pa |
||
- | Silencer, to achieve max 65dB(A) at 100m. | ||
- | Damper | ||
- | Hood |
This information is confidential and proprietary to Wärtsilä. | Page: 73 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
B2.6 | COMFORT VENTILATION AND AIRCONDITIONING |
This information is confidential and proprietary to Wärtsilä. | Page: 74 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
The air-conditioning units shall be installed in a reserved roof area.
For avoiding pressure drop duct work shall be as short is possible. Ducts are of galvanized steel, all ducts are insulated. The duct fittings will be manufactured from material equal to the ducts The covering sheet of the ducts is air- and water-tight (moisture barried).
- | Common alarms from each Rooftop Unit. | ||
- | Common alarms from each overheat protection. | ||
- | A common alarm from MCB’s if they trip. |
B2.7 | EQUIPMENT (Cranes) |
This information is confidential and proprietary to Wärtsilä. | Page: 75 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
Description | Value | Unit | Note | |||||||
Speed | ||||||||||
- | Hoisting speed |
m/min | 2-speed | |||||||
- | Traversing speed |
m/min | 2-speed+inverter control | |||||||
- | Travelling speed |
m/min | 2-speed+inverter control | |||||||
Classification | ||||||||||
- | Crane group |
|||||||||
- | Hoist machinery group |
|||||||||
- | Bridge travel group |
Overhead cranes are supplied as follows: | ||||||||
Engine hall (electrically, push button operated): | ||||||||
• | Overhead crane, lifting capacity of 2,0 ton | 1 pc | ||||||
Workshop (electrically operated) | ||||||||
• | Lifting rail with hoist, 1,0 t | 1 pc | ||||||
Fuel treatment / Pump room (manually operated traversing, electrically operated hoisting) | ||||||||
• | Lifting rail with hoist 0,5 ton | 1 pc |
B2.8 | AUXILIARY STRUCTURES | |
B2.8.1 | CHARGE AIR / EXHAUST GAS DUCTING AND BOILER SUPPORT STRUCTURES |
1 | Steel structures for charge air duct support (set) | ||
1 | Steel structures for auxiliary equipment support (set) | ||
1 | Railing outside building and auxiliary platform (set) | ||
1 | Steel structures outside the building (set) |
7 | The listed speeds may vary slightly depending on the local electrical grid system characteristics |
This information is confidential and proprietary to Wärtsilä. | Page: 76 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
1 | Superstructures, exhaust gas stack (set) | ||
1 | Superstructures, boiler support (set) | ||
1 | Steel frame for fire wall and other supporting structures (set) |
Description | Grade | Code | Note | |||||
Steel profiles and fasteners | ||||||||
- | Steel plates > 3 mm |
EN10025 | ||||||
- | I, H and U sections |
EN10025 | ||||||
- | L sections |
EN10025 | Primary profiles | |||||
Welded hollow sections |
EN10025 | Secondary profiles | ||||||
- | EN10219 | |||||||
- | Bolts |
EN ISO 4014 | Hot-dip galvanized | |||||
- | Nuts |
EN ISO 4032 | Hot-dip galvanized | |||||
- | Washers |
EN ISO 7091 | Hot-dip galvanized |
B2.9 | INTERNAL COMMUNICATION SYSTEM |
This information is confidential and proprietary to Wärtsilä. | Page: 77 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
C | SERVICES C1 ENGINEERING |
|
C1 | ENGINEERING |
1 | Preliminary engineering of power barge |
• | Draft power house layout | ||
• | Draft engine generator set foundation drawing | ||
• | Estimated total power demand | ||
• | Estimated ventilation demand | ||
• | Estimated dimensions and weights of main equipment |
1 | Basic engineering of power barge |
• | General engineering information | ||
• | Flow diagrams | ||
• | Power house layouts | ||
• | Barge hull layouts | ||
• | Main dimensions and weights for major equipment | ||
• | Electrical system layouts |
1 | Detailed mechanical engineering for Wärtsilä scope of supply | ||
1 | Detailed electrical engineering for Wärtsilä scope of supply | ||
1 | Detailed civil engineering for Wärtsilä scope of supply | ||
1 | Engineering of Barge Hull |
C2 | TECHNICAL ASSISTANCE | |
C2.1 | TECHNICAL ASSISTANCE DURING INSTALLATION |
This information is confidential and proprietary to Wärtsilä. | Page: 78 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
C2.2 | C2.2 TECHNICAL ASSISTANCE DURING PRE-COMMISSIONING |
C3 | INSTALLATION AND CONSTRUCTION SERVICES |
1 | Installation of mechanical equipment | ||
1 | Installation of electrical equipment | ||
1 | Installation of safety earthing system | ||
1 | Installation of power barge superstructures |
C4 | TESTING AND COMMISSIONING | |
C4.1 | WORKSHOP TESTS |
8 | Engine test according to standard program |
Duration | Load | |||||||||||
Item | [min] | [%] | Notes | |||||||||
1. | 15 | Start test and heating up |
||||||||||
2. | 45 | 60 | Site output, main fuel |
|||||||||
3. | 45 | 85 | Site output, main fuel |
|||||||||
4. | 45 | 100 | Site output, main fuel |
|||||||||
5. | 45 | 100 | Site output, alternative fuel (if applicable) |
|||||||||
6. | 15 | Test of overspeed devices |
C4.3 | PRE-COMMISSIONING AT SHIPYARD |
This information is confidential and proprietary to Wärtsilä. | Page: 79 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
1 | No load test No |
• | Check of installation | ||
• | Tests to prove correct operation of interlocks, alarm and tripping circuits. | ||
• | Rotational tests on all motors | ||
• | Check of overspeed trip devices. |
C6 | DOCUMENTS | |
C6.1 | PRELIMINARY DESIGN |
3 | General site layouts | ||
3 | General power house layouts | ||
3 | General flow diagram drafts |
C6.2 | BASIC DESIGN |
3 | General site layouts | ||
3 | General power house layouts | ||
3 | Flow diagram drafts |
C6.3 | DETAILED DESIGN |
3 | Drawings (set) | ||
3 | Parts lists (set) | ||
3 | P&ID’s |
C6.4 | FINAL DESIGN |
3 | Drawings as built, only updates (set) | ||
1 | Electronic copy of as built drawings, only updates (set) |
This information is confidential and proprietary to Wärtsilä. | Page: 80 of 81 |
Project name: Project number: Quotation number: Created by: Document Id: |
Power Supply Upgrade. LGL P0900329 Q0900869 MNO002 |
|||
Document creation date: |
August 25, 2009 |
C6.5 | USER MANUALS |
1 | Station manuals in English (set) |
• | Operation | ||
• | Maintenance | ||
• | Spare parts | ||
• | Quality records |
3 | As hard copy | ||
1 | On digital media | ||
1 | Installed into Wärtsilä Information System (WISE) |
This information is confidential and proprietary to Wärtsilä. | Page: 81 of 81 |
Doc. | Classification: — | |||||||||||||||
Title: | Lihir Power Barge Fire Protection | Xxx.XX: | DBAB103090 | |||||||||||||
Revision: | - | |||||||||||||||
Author: | Xxxxx Xxxxxxxxx/ 04-Aug-2009 | Status: | Finalised | |||||||||||||
Finalised by: | Xxxxx Xxxxxxxxx / 04-Aug-2009 | Pages: | 1(15) | |||||||||||||
- General |
Project: | - Lihir | ||||||||||||||
Power Plants |
Description: | Power Supply Uppgrade, LGL 8 x W20V32 | ||||||||||||||
Type: | Description |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 2(15) |
• | Skilled personnel attend the Power Plant 24 hours a day. | ||
• | Experience on execution of similar Power Plants | ||
• | Power Generation not to be interrupted due to false alarms and failures in an automatic system. | ||
• | Regular training of personnel in correct operating procedures | ||
• | Plant shall be well maintained and kept in good order | ||
• | Maintenance work including welding and cutting shall be done with appropriate precautions and instructions | ||
• | Installed fire protection equipment shall be maintained and perioidically tested |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 3(15) |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 4(15) |
• | automatic fire alarm (optical smoke detectors) | ||
• | standpipe with water hydrants and fire hose equipment |
• | 2 mobile foam unit (with 100 l foam concentrate, mixing ratio 3%, water flow 200 l/min) | ||
• | 27 portable 12 kg dry powder extinguishers in the hall (some of them at engine platforms) |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 5(15) |
• | automatic smoke alarm | ||
• | Gaseous extinguishing system (CO2 or equivalent) with manual remote release from control room after adequate evacuation time. | ||
• | 4 portable 5 kg CO2 extinguishers | ||
• | 1 trolley type 22 kg CO2 extinguisher |
• | automatic smoke alarm | ||
• | 1 hose reel with 1” hose (corridor downstairs) | ||
• | 1 portable 6 kg dry powder extinguishers |
• | automatic smoke alarm | ||
• | 1 portable 6 kg dry powder extinguisher |
• | automatic smoke alarm | ||
• | 3 portable 5 kg CO2 extinguishers |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 6(15) |
• | Wet pipe sprinkler system | ||
• | automatic smoke alarm system in each room | ||
• | 1 hose reel with 1” hose (corridor) | ||
• | 3 portable 6 kg dry powder extinguishers (located in office, corridor and canteen) |
• | automatic heat alarm | ||
• | 1 portable 12 kg dry powder extinguisher | ||
• | Fire fighting equipment from engine room and from deck can be used. |
• | Wet pipe sprinkler system | ||
• | automatic heat alarm | ||
• | 1 hose reel with 1” hose | ||
• | 2 portable 12 kg dry powder extinguishers |
• | Wet pipe sprinkler system (in same loop with workshop) | ||
• | automatic heat alarm | ||
• | 1 portable 12 kg dry powder extinguishers |
• | automatic smoke alarm | ||
• | 1 hose reel with 1” hose | ||
• | 3 portable 12 kg dry powder extinguishers |
• | automatic smoke alarm | ||
• | 1 portable 5 kg CO2 extinguishers |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 7(15) |
• | automatic heat alarm | ||
• | water mist system utilising same high pressure water supply as for the engines | ||
• | 4 portable 12 kg dry powder extinguishers | ||
• | 1 wheeled type 50 kg dry powder extinguisher | ||
• | 2 foam hose reels with 1” hose and 25 litre foam container |
• | automatic smoke alarm | ||
• | 2 portable 12 kg dry powder extinguishers |
• | automatic heat alarm | ||
• | wet pipe sprinkler system | ||
• | 1 portable 12 kg dry powder extinguishers |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 8(15) |
• | automatic heat alarm | ||
• | fixed low expansion foam application into the tanks with remote manual release from control room. Application rate 4,1 l/min/m2 . |
• | automatic heat alarm | ||
• | fixed low expansion foam application into the tanks with remote manual release from control room. Application rate 4,1 l/min/m2 . |
• | automatic heat alarm | ||
• | fixed low expansion foam application into the tanks with remote manual release from control room. Application rate 4,1 l/min/m2 . |
• | automatic heat alarm | ||
• | fixed low expansion foam application into the tanks with remote manual release from control room. Application rate 4,1 l/min/m2 . |
• | 1 portable 12 kg dry powder extinguisher per transformer at safe distance | ||
• | 1 portable 5 kg CO2 extinguisher per transformer at safe distance | ||
• | water hydrant and fire hose equipment from deck may be used. The neighboring hose cabinet shall be equipped with foam mixing possibility to the hose stream. |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 9(15) |
• | automatic heat alarm | ||
• | 1 portable 12 kg dry powder extinguisher | ||
• | water hydrant and fire hose equipment from deck may be used. The neighboring hose cabinet shall be equipped with foam mixing possibility to the hose stream. |
• | automatic heat alarm | ||
• | 1 portable 12 kg dry powder extinguisher | ||
• | water hydrant and fire hose equipment from deck may be used. The neighboring hose cabinet shall be equipped with foam mixing possibility to the hose stream. |
• | 2 self contained breathing apparatus (min. 30 minutes capacity) | ||
• | 2 fire proof life lines | ||
• | 2 sets of protective clothing | ||
• | 2 sets of boots and gloves (electrically non conducting) | ||
• | 2 helmets | ||
• | 2 electric safety lamps (min. 3 hour capacity) | ||
• | 2 axes with high voltage insulation | ||
• | UHF radio set (5 radios) | ||
• | 2 storage lockers (two distant locations) for the outfits in a safe area |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 10(15) |
¥ | a fire alarm center including a supervision unit, a display unit, input and output terminal units, a power supply unit, and a message transfer unit | ||
¥ | fire detectors and manual call points connected to the fire alarm center | ||
¥ | alarm devices (bells, sirens, flashing lights) connected to the fire alarm center |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 11(15) |
¥ | The fire alarm center shall be placed in a continuously manned room. In a power plant this is the control room. | ||
¥ | The supervised rooms should be divided into alarm zones to ease locating the fire. | ||
¥ | Every room must be provided with a suitable amount and type of detectors. | ||
¥ | Alarm bells, sirens and flashing lights must be situated so that they can be heard or seen everywhere inside and where needed outside the buildings. | ||
¥ | An average ambient sound level greater than 105 dBA shall require the use of a visible notification appliances |
¥ | Separate buildings | ||
¥ | Separate floors (except stairways which may encompass several floors) | ||
¥ | Rooms separated by fire walls | ||
¥ | Areas of different fire classes | ||
¥ | Rooms or areas of essentially different heights | ||
¥ | Rooms that cannot be accessed without passing through other zones |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 12(15) |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 13(15) |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 14(15) |
¥ | Alarm bells (92 – 95 dB) | ||
¥ | Flashing lights (1 Hz, 1W) | ||
¥ | Alarm sirens (about 115 dB) where feasible |
Engine room
|
Alarm devices (flashing lights) visible between every engine. | |
Control room
|
One audible alarm device (alarm xxxx). | |
Other rooms
|
Audible alarm devices should be placed so that they can be heard in all rooms where people stay more than temporarily. The sound level should be at least 15 dBA above the average sound level in the room or 5 dBA above the maximum sound having a duration of at least 60 seconds whichever is greater, measured 1.5 m above the floor. | |
Outdoors
|
One audible alarm device on each side of the power house. |
Doc. Classification: Internal DocID: DBAB103090 Revision: - 15(15) |
¥ | 230 VAC taken from the LV switchgear (or public grid) | ||
¥ | One or more batteries (generally 24 VDC) with battery charger. |
EXHIBIT A: TECHNICAL DATA SHEET | Page 1(11) |
Item | Description | Supplier’s comments | ||||
Equipment title |
||||||
LGL equipment number
|
||||||
SYSTEM |
||||||
System Normal Voltage
|
Ok | |||||
System Highest Voltage
|
||||||
Frequency
|
Ok | |||||
Phases
|
Ok | |||||
System Earthing
|
Ok | |||||
Fault Level
|
||||||
Single Line Drawing Number
|
6647-SKETCH-02 | See singel line diagram in Exhibit A | ||||
SERVICE CONDITIONS |
||||||
Design Ambient Temperature Outdoor
|
||||||
Extreme Ambient Temperature
|
Max | |||||
Min | ||||||
Altitude
|
||||||
Design Relative Humidity Outdoor
|
||||||
Other
|
||||||
GENERATORS |
||||||
Quantity
|
(N Configuration) | Spinning reserve by existing plant |
||||
Plant Installed kW
|
See Contract Exhibit B “Performance Guarantees” | |||||
Individual Generator kW Rating (min/max)
|
See Contract Exhibit B “Performance |
EXHIBIT A: TECHNICAL DATA SHEET | Page 2(11) |
Item | Description | Supplier’s comments | ||
Guarantees” | ||||
Frequency
|
Ok | |||
Generator Voltage
|
Ok | |||
Rated Power Factor at MCR
|
Ok | |||
Auxiliaries Voltage
|
Ok | |||
Control Circuit Voltage
|
||||
FUEL SPECIFICATION
|
Refer Specification |
EXHIBIT A: TECHNICAL DATA SHEET | Page 3(11) |
Item | Description | Supplier’s comments | ||
Equipment Title |
||||
LGL equipment number |
||||
SYSTEM |
||||
Manufacturer
|
||||
Type
|
||||
Number of Poles
|
||||
Rated Voltage
|
||||
Frequency
|
||||
Rating of each Generating Set
|
||||
Quantity of Generating Sets
|
||||
GENERATORS SETS |
||||
Maximum Continuous Rating at Alternator
Terminals (0.8pf, 40°C outdoors)
|
||||
Generator Overload Capability (%/ duration)
|
||||
Auxiliary Power Usage at MCR
|
EXHIBIT A: TECHNICAL DATA SHEET | Page 4(11) |
Item | Description | Supplier’s comments | ||
Fuel Consumption at 100% MCR
|
||||
Fuel Consumption at 75% MCR
|
||||
Fuel Consumption at 50% MCR
|
||||
Fuel Type Required
|
||||
Fuel Quality Required
|
||||
Engine Make/Model
|
||||
Engine Type/No. of Cylinders
|
||||
Engine Speed
|
||||
Alternator Make/Model
|
||||
Voltage Regulator Make /Model
|
||||
Alternator Reactance % at 11000V, 100%
|
||||
-Subtransient, positive/negative/zero |
||||
-Transient, synchronous/zero sequence
|
EXHIBIT A: TECHNICAL DATA SHEET | Page 5(11) |
Item | Description | Supplier’s comments | ||
Alternator Reactance % at 11000V, 70%
|
||||
-Subtransient, positive/negative/zero |
||||
-Transient, synchronous/zero sequence |
||||
Auxiliary Electric Motors Type/Quantity
|
||||
Auxiliary Electric Motors Size
|
||||
Generator Overall Mass (including fuel/oil/water)
|
||||
Engine Running Hours at MCR between major
overhauls
|
||||
Accessories Provided
|
||||
DIMENSIONS |
||||
Generator dimensions (mmLx mmWx mmH)
|
||||
Generator Mass (kg)
|
||||
Barge Qty
|
||||
Barge Dimensions (length, beam, draft, height)
|
||||
Barge Displacement (T each)
|
||||
AUXILIARIES |
||||
Light fuel oil unloading pump unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / |
EXHIBIT A: TECHNICAL DATA SHEET | Page 6(11) |
Item | Description | Supplier’s comments | ||
Light fuel oil tank — qty/capacity (m3)
|
/ | |||
Light fuel oil transfer pump unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Light fuel oil day tank, qty/capacity (m3)
|
/ | |||
Heavy fuel oil unloading pump unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Heavy fuel oil storage tank — qty/capacity (m3)
|
/ | |||
Heavy fuel oil transfer pump unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ | |||
Heavy fuel oil buffer tank — qty/capacity (m3)
|
/ | |||
Heavy
fuel oil separator unit, — separator —
qty/capacity (m3/h)
|
/ | |||
Heavy fuel oil day tank — qty/capacity (m3)
|
/ | |||
Heavy fuel oil booster unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
EXHIBIT A: TECHNICAL DATA SHEET | Page 7(11) |
Item | Description | Supplier’s comments | ||
Heavy / light fuel oil feeder unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Light fuel oil feeder pump — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Heavy fuel oil fuel oil unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Lubricating oil separator unit separator —
qty/capacity (m3/h)
|
/ | |||
Lubricating oil unloading pump unit: fresh oil —
qty/capacity (m3/h)/Pressure (bar)
|
/ / | |||
Lubricating oil storage tank: fresh oil —
Qty/Capacity m3
|
/ | |||
Lubricating oil service tank — Qty/Capacity m3
|
/ | |||
Lubricating oil transfer pump unit (mobile) — qty/capacity (m3/h)/Pressure (bar)
|
/ / | |||
EXHIBIT A: TECHNICAL DATA SHEET | Page 8(11) |
Item | Description | Supplier’s comments | ||
Lubricating oil transfer pump unit (stationary) —
qty/capacity (m3/h)/Pressure (bar)
|
/ / | |||
Lubricating oil storage tank: used oil —
Qty/Capacity m3
|
/ | |||
Lubricating oil unloading pump unit: used oil —
qty/capacity (m3/h)/Pressure (bar)
|
/ / | |||
Starting air bottle — qty/capacity (m3/h)/Pressure
(bar)
|
/ / | |||
Starting air compressor unit — double —
qty/capacity (m3/h)/Pressure (bar)
|
/ / | |||
Instrument air compressor unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Compressed air receiver — qty/volume m3
|
/ | |||
Refrigerated air dryer with control panel —
Qty/Dew Point °C
|
/ | |||
Radiator cooler circuit — Frame material /Tube
material /Fin material /Noise level dB(A) at 40 m distance
|
/ / |
|||
Low temperature expansion tank — qty/vol m3
|
/ | |||
Jacket water expansion tank — qty/vol m3
|
/ |
EXHIBIT A: TECHNICAL DATA SHEET | Page 9(11) |
Item | Description | Supplier’s comments | ||
Maintenance water tank — qty/vol m3
|
/ | |||
Maintenance water tank discharge pump —
qty/capacity (m3/h)/Pressure (bar)
|
/ / | |||
Charge air silencer — qty/ Noise attenuation dB(A)
|
/ | |||
Exhaust gas silencer — qty/Noise attenuation
dB(A)
|
/ | |||
Exhaust gas stack — qty/Diameter
/Material/Height above ground level m
|
/ / |
|||
Exhaust gas boilers — qty/ Steam generation kg/h
saturated steam/ Working steam pressure bar(a)
|
/ / |
EXHIBIT A: TECHNICAL DATA SHEET | Page 10(11) |
Item | Description | Supplier’s comments | ||
Light fuel oil fired boiler for steam generation —
qty/ Steam generation kg/h saturated steam/Working
steam pressure bar(a)
|
/ / | |||
Oily water pump (air driven) — qty/capacity m3/h
|
/ | |||
Oily water buffer tank — Qty/Capacity m3
|
/ | |||
Sludge tank — Qty/Capacity m3
|
/ | |||
Sludge loading pump unit — (air driven) —
qty/capacity m3/h
|
/ | |||
Water treatment unit — qty/Capacity m3/h
|
/ | |||
Treated water storage tank — Qty/Capacity m3
|
/ | |||
Water booster units Pressure tank — qty/capacity
(m3/h)/Pressure (bar)
|
/ / |
EXHIBIT A: TECHNICAL DATA SHEET | Page 11(11) |
Item | Description | Supplier’s comments | ||
Water booster units Pump Unit — qty/capacity
(m3/h)/Pressure (bar)
|
/ / | |||
Black start unit — qty/kW rating
|
/ | |||
Title: | Supplier list | DocID: Revision: |
WDAAA041238 y |
|||||
Author: | Xxxxxx Xxxxxxx / 16-Oct-2008 | Sheets: | 1 | |||||
Wärtsilä Finland Oy
|
Approved by: | Xxxx Xxxxx / 29-Oct-2008 | Status: | Approved | ||||
Power Plants
|
Project: | IN100 Power Plants | ||||||
Description: | Wärtsilä Power Plants preferred suppliers | |||||||
Type: | List |
System | Section | Equipment | Supplier name | Supplier country | ||||
A1 EG-SET
|
A1.1 Genset / Engine | Engine related equipment | Finland | |||||
U.K. | ||||||||
A1.2 Genset / Alternator | Alternator | Finland | ||||||
United Kingdom | ||||||||
Germany | ||||||||
France | ||||||||
A1.3 Genset / Base frame | Base frame | Finland | ||||||
Finland | ||||||||
Finland | ||||||||
A1.4 Genset / Elastic mounts | Elastic mounts | Netherlands | ||||||
Sweden | ||||||||
A1.5 Genset / Coupling, flywheel | Coupling | Germany | ||||||
Germany | ||||||||
U.K. | ||||||||
Germany | ||||||||
Germany | ||||||||
Flywheel cover | Finland | |||||||
A1.6 Genset / Flexible connections | Flexible connections | Denmark | ||||||
Finland | ||||||||
A1.7 Genset / Platform | Platforms | Finland | ||||||
Poland | ||||||||
A2 AUXILIARY MODULES
|
A2 Auxiliary units and modules | Auxiliary units and modules | Finland / India | |||||
A2.0.1 Auxiliary module / components | Auxiliary module control panels | Finland | ||||||
Finland | ||||||||
Finland | ||||||||
Centrifugal pumps | Finland | |||||||
Finland | ||||||||
Filters | Italy | |||||||
Germany | ||||||||
Finland | ||||||||
Heaters | Denmark | |||||||
Italy | ||||||||
Finland | ||||||||
U.K. | ||||||||
Other auxiliary module components | Germany | |||||||
Norway | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Plate heat exchangers | Finland | |||||||
Denmark | ||||||||
Germany | ||||||||
Pre-heating units | Denmark | |||||||
Germany | ||||||||
Pumps | Finland | |||||||
Sweden | ||||||||
Austria | ||||||||
Germany | ||||||||
Finland | ||||||||
Thermostatic valves | U.K. | |||||||
Germany | ||||||||
Valves | Finland | |||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
A2.1 FUEL SYSTEM
|
A2.1.1/A2.1.2 Light/Heavy fuel oil system | Boosters | Finland/ China | |||||
Finland | ||||||||
Finland/ India | ||||||||
Flow meters | Finland (Netherlands) | |||||||
Finland (Switzerland) | ||||||||
Finland | ||||||||
Tanks | Finland | |||||||
Finland | ||||||||
A2.1.2 Heavy fuel oil system | Separator modules | India | ||||||
Finland | ||||||||
Germany |
Document Classification: | ||||
Confidential | Page: 1/3 |
System | Section | Equipment | Supplier name | Supplier country | ||||
A2.1.5 Gas system | Gas compressors | New Zeeland | ||||||
Italy | ||||||||
Italy | ||||||||
Gas flow measuring unit | Finland | |||||||
Germany | ||||||||
Italy | ||||||||
Gas regulating units | USA | |||||||
Germany | ||||||||
A2.2 LUBE OIL SYSTEM
|
A2.2 Lube oil system | Oil mist coalescer | Finland | |||||
Oil mist separator | Finland | |||||||
Separator modules | India | |||||||
Finland | ||||||||
Germany | ||||||||
Tanks | Finland | |||||||
A2.3 COMPRESSED AIR SYSTEM
|
A2.3 Compressed air system | Control and working air comp. units | Germany | |||||
Finland | ||||||||
Starting air pressure vessels | Germany | |||||||
Finland | ||||||||
Starting air units | Finland | |||||||
Germany | ||||||||
Germany | ||||||||
Norway | ||||||||
A2.4 COOLING SYSTEM
|
A2.4 Cooling system | Centrifugal pumps | Spain | |||||
Spain | ||||||||
Denmark | ||||||||
Finland | ||||||||
Cooling towers | Germany | |||||||
France | ||||||||
Italy | ||||||||
Denmark | ||||||||
Radiators | Italy | |||||||
Finland | ||||||||
Sweden | ||||||||
Germany | ||||||||
A2.5 CHARGE AIR SYSTEM
|
A2.5 Charge air system | 3-way damper | Denmark | |||||
Charge air filters | France | |||||||
U.K. | ||||||||
Finland | ||||||||
Charge air silencers | Finland | |||||||
A2.6 EXHAUST GAS SYSTEM
|
A2.6 Exhaust gas system | Exhaust gas silencers | Netherlands | |||||
Finland | ||||||||
Mexico (USA) | ||||||||
Exhaust gas system equipment | Belgium | |||||||
Finland | ||||||||
Finland | ||||||||
A2.8 STATION SUPPORT SYSTEM
|
A2.8.1 Oily water treatment system | Incinerators | Denmark | |||||
Norway | ||||||||
Sludge treatment | Sweden | |||||||
Sweden | ||||||||
Tanks | Finland | |||||||
A2.8.2 Treated water system | Water treatment | Finland | ||||||
Denmark | ||||||||
Finland | ||||||||
A2.8.3 Fire fighting system | Fire fighting equipment | Finland | ||||||
Finland | ||||||||
Mechanical protection and fighting | Finland | |||||||
England | ||||||||
A2.9
AUX. STEEL STRUCTURES, [ILLEGIBLE]
|
A2.9 Aux. Steel structure, piping, etc. | Pipe material | Finland | |||||
Finland | ||||||||
Finland | ||||||||
Piping & building signs | Finland | |||||||
A3 ELECTRICAL EQUIPMENT
|
A3.1 MV-Equipment | Earthing Transformer | Finland | |||||
France | ||||||||
MV-cables | Belgium | |||||||
Germany | ||||||||
France | ||||||||
Finland | ||||||||
Finland | ||||||||
MV-switchgear | Czeck | |||||||
Finland | ||||||||
USA | ||||||||
France | ||||||||
Neutral point cabinet | Finland | |||||||
France | ||||||||
France | ||||||||
USA | ||||||||
France | ||||||||
Unit (block) transformer | Spain | |||||||
Turkey | ||||||||
France | ||||||||
Bulgaria | ||||||||
France | ||||||||
A3.2 Station service system | Black start unit | USA | ||||||
Denmark | ||||||||
Distribution Transformer | France | |||||||
Turkey | ||||||||
Frequency converter | Finland |
Document Classification: | ||||
Confidential | Page: 2/3 |
System | Section | Equipment | Supplier name | Supplier country | ||||
LV-cables | Finland | |||||||
Finland | ||||||||
Finland | ||||||||
Belgium | ||||||||
France | ||||||||
France | ||||||||
Finland | ||||||||
LV-Switchgear | Finland | |||||||
USA | ||||||||
Finland | ||||||||
A3.3 DC system | DC system | Finland | ||||||
Finland | ||||||||
USA | ||||||||
A3.5 Outdoor switchyard | HV-cables | France | ||||||
Finland | ||||||||
Outdoor switchyard | Finland | |||||||
Power transformers | Finland | |||||||
Turkey | ||||||||
India | ||||||||
India | ||||||||
Bulgaria | ||||||||
Italy | ||||||||
A4 AUTOMATION EQUIPMENT
|
A4.2 Control panels | Control panel main components | Switzerland | |||||
Finland | ||||||||
Finland | ||||||||
France | ||||||||
Germany | ||||||||
Finland | ||||||||
Finland | ||||||||
Control panels | Finland | |||||||
Finland | ||||||||
A4.3 Operators station | Computer peripherals, Firewalls, Modems etc. | Finland | ||||||
Finland | ||||||||
Finland | ||||||||
Operator panels | Finland | |||||||
Norway | ||||||||
A5 HEAT RECOVERY SYSTEM
|
A5.1 Steam generation system | Steam equipment | Finland | |||||
Finland | ||||||||
Steam turbines | Netherlands | |||||||
U.K. | ||||||||
France | ||||||||
India | ||||||||
Tanks | Finland | |||||||
Waste heat recovery system | Finland | |||||||
Germany | ||||||||
Norway | ||||||||
India | ||||||||
Denmark | ||||||||
A5.2 Hot water generation system | Exhaust gas heat recovery heat exchanger / Hot | Germany | ||||||
Denmark | ||||||||
A6 EMISSION CONTROL SYSTEM
|
A6 Emission control system | Oxidation catalysts | Finland | |||||
Switzerland | ||||||||
SCR (DeNOx) | Germany | |||||||
Switzerland | ||||||||
B CIVIL WORKS & STRUCTURES
|
B Civil works & Structures | Doors | Finland | |||||
Finland | ||||||||
Electrical installation material | Finland | |||||||
Finland | ||||||||
Finland | ||||||||
Furnitures | Finland | |||||||
HVAC and Piping material | Finland | |||||||
Insulation | Finland | |||||||
Miscellaneous civil material | Finland | |||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Overhead travelling cranes and workstation [ILLEGIBLE] | Finland | |||||||
Roofing sheets, wall panels, flashings | Finland | |||||||
Sewage piping and plumbing | Finland | |||||||
Steel structures | Finland | |||||||
Poland | ||||||||
Finland | ||||||||
Substructure material | Finland | |||||||
Finland | ||||||||
Surface treatment | Finland | |||||||
Finland | ||||||||
Ventilation | Finland | |||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Windows | Finland | |||||||
C4 COMMISSIONING AND TESTING
|
C4 Commissioning and testing | Commissioning Engineers | Finland | |||||
Finland | ||||||||
C6 DOCUMENTS
|
C6 Documents | Design | Finland | |||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Finland | ||||||||
Design and O&M Manuals | Finland |
Document Classification: | ||||
Confidential | Page: 3/3 |
Guaranteed performance | ||
The guaranteed performance in below article 1.2 is based on the Site conditions, article 1.3, and the heavy fuel given in article 1.4. If the conditions of 1.3 and/or 1.4 changes the power and heat rate adjustments may apply. These adjustment procedures are further defined in document WDAAA245063 “Electrical Power & Heat Rate Test — Diesel Engine”. | ||
1.1 | General Data |
Engine Type
|
Wärtsilä 20V32 | |||||
Engine speed
|
rpm | |||||
Compression Ratio
|
- | |||||
Genset Maximum Electrical Power at Site
|
kW | |||||
Cooling method
|
- | |||||
Cooling circuit
|
- |
1.2 | Performance Data |
Electrical Power Guarantee
|
kW | |||||||
Minimum Electrical Power Guarantee
|
kW | |||||||
Electrical Power Guarantee Point
|
Generator terminals | |||||||
Power factor
|
Cos fi | |||||||
Heat Rate Guarantee
|
kJ/kWh | |||||||
Specific fuel oil consumption (only as general information) |
g/kWh | |||||||
Maximum Heat Rate Guarantee
|
kJ/kWh | |||||||
Heat Rate Guarantee Point
|
Generator terminals | |||||||
Heat rate and electrical power tolerance
|
% | |||||||
Measurement tolerance
|
Depends on measurement equipment. Calculated as per Performance test guideline | |||||||
Lubricating Oil Consumption Guarantee
|
kg/h |
1.3 | Site ( Contract ) Conditions |
Altitude / Total barometric pressure |
m / kPa | 101.3 kPa | ||||||
Ambient air temperature |
oC | 32 | ||||||
LT charge air cooler water inlet temperature |
oC | 51.2 | ||||||
Relative Humidity |
% | 80 |
1.4 | Heavy fuel oil |
Lower Heating Value (LHV) ,
( at 0
oC and
100 kPa)
|
MJ/kg | |||||
Fuel specification is according to Wärtsilä Technical Specification. | ||||||
Viscocity
|
cSt, 50 ºC |
2. | ISO 3046 — Standard and Manufacturers Substitute Reference Conditions (These are the reference conditions for calculating Electrical output and heatrate and Lube Oil consumption for Reciprocating internal combustion engines running in Diesel mode) |
Standard reference conditions
(Conditions from where Heat Rate is de-rated) |
||||||||
Ambient air temperature |
oC | 25 | ||||||
Charge Air coolant temperature |
oC | 25 | ||||||
Total Barometric pressure |
kPa | 100 | ||||||
Relative Humidity at Ambient air temperature |
% | 30 | ||||||
Substitute reference conditions
(Conditions from where electrical output is de-rated) |
||||||||
Ambient air temp. |
oC | 35 | ||||||
Charge Air coolant temperature |
oC | 45 |
3. | Exhaust Gas Emissions | |
Reference is made to Emission data, document DBAA992527 attached to this Exhibit B. The measurement procedure are described in Exhibit C “Performance Test Guidelines”, documet DAAB195899 “Stack Emission Test”. | ||
4. | Duration of Performance Test | |
The Performance test practical testing details are described in Exhibit C “Performance Test Guidelines”: |
- | WDAAA245063 “Electrical Power & Heat Rate Test — Diesel Engine”, and | ||
- | DAAB184367 “Lubricating oil consumption test”, and | ||
- | DAAB195899 “Stack Emissions Test” |
Duration of Electrical Power Test |
hours | 2 | ||||||
Duration of Heat Rate Test |
hours | 2 | ||||||
Duration of Emission Test |
hours | Depends on the test requirements | ||||||
Duration of Lube Oil Test |
hours | 48 |
Title:
|
Lihir, Papua New Guinea | Xxx.XX: | DBAA992527 | |||
Revision: | - | |||||
Author:
|
Status: | Finalised | ||||
Finalised by:
|
/ 16-Apr-2009 | Pages: | 1 (1) | |||
Project:
|
- | |||||
Description:
|
Emission data | |||||
Type:
|
Emission data sheet |
Engine: | Wärtsilä® 20V32 at 750 RPM (constant speed) |
- max. total pressure drop in air intake and flue gas system 5 kPa |
- intake air or ambient temperature |
32 | °C | ||||||
- LT charge air coolant temperature (max.) |
45 | °C | ||||||
- altitude above sea level |
0 | m | ||||||
- minimum absolute humidity |
6 | gwater/kgdry air |
- max. nitrogen content |
(dry) | |||||||||||
- max. density |
(at 15 °C) | |||||||||||
- max. kinematic viscosity |
(at 50 °C) | |||||||||||
- max. sulphur content |
(dry) | |||||||||||
- max. ash content |
(dry) | |||||||||||
- min. LHV |
(instrumental analyzer method). Or principally similar other methods.
Title:
|
2. Electrical Power & Heat Rate Test - | Xxx.XX: | WDAAA245063 | |||
Diesel Engine (Euro version) | Revision: | c.9 | ||||
Author:
|
KEN004/ 20-Aug-2008 | Status: | Draft | |||
Draft by:
|
/ 17-Apr-2009 | Pages: | 1 (11) | |||
Project:
|
- | |||||
Description: | Electrical power and Heat Rate Tests — Diesel, GD or DF Engine running in diesel mode | |||||
Type:
|
Contract/ Agreement |
1 Objective |
2 | |||
2 Symbols |
2 | |||
3 Measurements |
4 | |||
4 Electrical Power Test |
5 | |||
4.1 General |
5 | |||
4.2 Adjustment of electrical power for ambient conditions |
5 | |||
4.3 Measurement tolerances in electrical power test |
7 | |||
4.4 Electrical Power |
7 | |||
5 Heat rate test |
8 | |||
5.1 General |
8 | |||
5.2 Recalculation of heat rate for ambient conditions |
8 | |||
5.3 Measuring tolerances in Heat Rate test |
10 | |||
5.4 Heat Rate |
10 | |||
5.5 List of auxiliary equipment operational status during tests |
11 |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 2(11) |
1 | Objective |
2 | Symbols |
Symbol | Definition | Unit | ||
b | Specific fuel consumption |
kg/kWh | ||
k | Ratio of indicated power |
1 | ||
m | Exponent of the dry air pressure ratio or total barometric pressure
ratio |
1 | ||
n | Exponent of the ambient air thermodynamic temperature ratio |
1 | ||
p | Total barometric pressure |
kPa | ||
P | Power |
kW | ||
s | Exponent of the charge air coolant thermodynamic temperature
ratio |
1 | ||
tc | Charge air coolant temperature at inlet to cooler |
C | ||
t | Ambient air temperature |
C | ||
Tc | Charge air coolant thermodynamic temperature |
K | ||
T | Ambient air thermodynamic temperature |
K | ||
a | Power adjustment factor |
1 | ||
b | Fuel consumption recalculation factor |
1 | ||
hm | Mechanical efficiency |
1 | ||
Pg | Electrical power at generator terminals |
kW | ||
Po | Electrical power for own consumption |
kW | ||
Psu | High voltage transformer losses |
kW | ||
Phv | Electrical power at high voltage side of step up transformer |
kW | ||
Pmv | Electrical power at medium voltage side of step up transformer |
kW | ||
Ep | Electrical energy for power test |
kWh | ||
Ehr | Electrical energy for heat rate test |
kWh | ||
Eg | Electrical energy at generator terminals |
kWh | ||
Eo | Electrical energy for own consumption |
kWh | ||
Esu | High voltage transformer losses, energy |
kWh | ||
Ehv | Electrical energy at high voltage side of step up transformer |
kWh | ||
Emv | Electrical energy at medium voltage side of step up transformer |
kWh | ||
mfin | Mass of fuel in to engine |
kg |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 3(11) |
mfout | Mass of fuel out from engine |
kg | ||
mfmeasured | Mass of fuel, measured |
kg | ||
mfleak | Mass of leak fuel |
kg | ||
mf,net | Mass of net fuel consumed by engine |
kg | ||
Fnet | Net fuel energy consumed by engine |
kJ | ||
LHVtest | Lower heating value of fuel during test |
MJ/kg | ||
LHVguarantee | Lower heating value of fuel used in fuel consumption guarantee |
MJ/kg | ||
r | Heat rate |
kJ/kWh | ||
tt | Time |
h | ||
N | Number of periods in test |
1 | ||
EMUtol | Tolerance of electrical energy measuring unit |
% | ||
LHVtol | Tolerance of lower heating value of fuel |
% | ||
mftol | Tolerance of fuel mass metering |
% | ||
Itransf,tol | Tolerance of measuring transformer, current |
% | ||
Utransf,tol | Tolerance of measuring transformer, voltage |
% |
m
|
Mechanical | |
r
|
Standard reference conditions | |
ra
|
Substitute reference conditions | |
x
|
Contractual Reference Conditions (Site conditions) | |
y
|
Test day conditions | |
guaranteed
|
Guaranteed value | |
Min
|
Minimum | |
Max
|
Maximum | |
average
|
Average |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 4(11) |
3 | Measurements |
ISO | Wartsila | |||||||||
Tolerance, | Tolerance, | |||||||||
Symbol | Definition | Measuring point | Unit | max | max 1) | |||||
py
|
Total barometric pressure | At engine air intake filter | kPa | ± 0,5 % | ± 0,2 % | |||||
ty
|
Ambient air thermodynamic temperature | At engine air intake filter | K | ± 2 K | ± 1 K | |||||
tcy
|
Chare air coolant thermodynamic temperature | At charge air cooler inlet | K | ± 2 K | ± 1 K | |||||
mfin
|
Mass of fuel in to engine | Engine/Plant specific mass flow meter | kg | ± 3 % | ± 0,5 % | |||||
mfout
|
Mass of fuel out from engine | Engine/Plant specific mass flow meter | kg | ± 0,5 % | ||||||
mfleak
|
Mass of leak fuel | kg | ± 1,0 % | |||||||
LHV
|
Lower heating value | at Engine/Plant specific mass flow meter | MJ/kg | ± 0,5 % | ||||||
E
|
Electrical energy | PMU / EMU 2) | kWh | ± 0,5 % | ||||||
tt
|
time | s | ± 0,1 % |
1) | Wärtsilä recommends equipments with these accuracies, however actual tolerances of measuring equipment used during the test(s), shall be used for calculating Electrical Power and Heat rate as per section 4.4 and 5.4 respectively. | |
2) | This is the point of measurement as per agreement between the Contractor and Owner. |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 5(11) |
4 | Electrical Power Test |
4.1 | General |
The engines involved in the test shall run for 2 (two) hours at full load prior to the start of the test in order to achieve stable conditions in all engine components and external systems.
The final guaranteed power and heat rate during the full test, is the average of the adjusted powers and the average of the recalculated heat rates, which are calculated separately for each hourly test period.
4.2 | Adjustment of electrical power for ambient conditions |
Engine type: Diesel engines and dual fuel compression-ignition engines operating on liquid fuel, Conditions: Turbocharged with charge air cooling, Low and medium speed four-stroke engines, Formula reference: D
Doc. Classification: DocID: WDAAA245063 Revision: c.9 6(11) |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 7(11) |
||
4.3 | Measurement tolerances in electrical power test |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 8(11) |
5 | Heat rate test |
5.1 | General |
The guaranteed electrical power and heat rate for each hourly test period is adjusted for the ambient conditions prevailing and measured at the start of each hourly test period.
The standard reference conditions are : |
||||||||
Ambient air barometric pressure |
= | 100 kPa | ||||||
Ambient air temperature |
= | 25 C | ||||||
LT Coolant temperature |
= | 25 C |
5.2 | Recalculation of heat rate for ambient conditions |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 9(11) |
Doc. Classification: DocID: WDAAA245063 Revision: c.9 10(11) |
5.3 | Measuring tolerances in Heat Rate test |
5.4 | Heat Rate |
DocID: WDAAA245063 | Revision: c.9 | 11(11) |
System | Equipment | Auto Mode | Shut down | |||
Cooling System |
Radiators | X | ||||
Cooling System |
Pre-heater unit | X | ||||
Fuel System |
Fuel unloading pump | X | ||||
Fuel System |
HFO Transfer pump unit | X | ||||
Fuel System |
HFO feeder pump unit | X | ||||
Fuel System |
Booster unit | X | ||||
Fuel System |
LFO Unloading pump unit | X | ||||
Fuel System |
LFO feeder pump unit | X | ||||
Fuel System |
HFO separator module | X | ||||
Lube oil System |
Pre-lube pump unit | X | ||||
Lube oil System |
Lube oil transfer pump unit | X | ||||
Lube oil System |
Lube oil Separator | X | ||||
Air System |
Starting air compressor | X | ||||
Air System |
Working air compressor | X | ||||
Charge air System |
Charge air filter | X | ||||
Plant |
Control and Monitoring | X | ||||
Plant |
Lighting | X | ||||
Plant |
Ventilation | X | ||||
Plant |
Workshop | X | ||||
Plant |
Overhead crane | X | ||||
Plant |
Laboratory | X | ||||
Steam system |
Feed water pump unit | X | ||||
Steam system |
Circulation pump | X | ||||
.... |
.... | |||||
.... |
.... |
Title:
|
3. Lubricating oil consumption test | Xxx.XX: | DAAB184367 | |||
Revision: | b.6 | |||||
Author:
|
JNO005/ 20-Aug-2008 | Status: | Draft | |||
Draft by:
|
Xxxxxxx Xxxxxxx / 24-Nov-2008 | Pages: | 1 (2) | |||
Project:
|
- | |||||
Description:
|
Lubricating Oil Consumption Test | |||||
Type:
|
Guideline |
1 | Objective |
1 | ||||
2 | Symbols |
1 | ||||
3 | Definitions |
1 | ||||
4 | Duration |
2 | ||||
5 | Lube Oil Consumption Measurements |
2 |
1 | Objective | |
The objective of this performance test is to measure the lube oil consumption of the engines. | ||
2 | Symbols |
SYMBOL | DESCRIPTION | UNIT | ||
tt
|
Duration of test | h | ||
V
|
Volume of lube oil | m3 | ||
clo
|
Lube oil consumption | kg/h | ||
mlo
|
Mass of lube oil | kg | ||
r
|
Density of lube oil | kg/m3 | ||
b
|
Expansion co-efficient | — |
3 | Definitions | |
Density of lubricating oil changes as a function of temperature. This must be taken into account when measuring lubricating oil consumption. Lubricating oil density is normally given at 15 oC temperature and the product specific value can be found from the Product Data Sheet of the lubricating oil in question. Following formula is used when calculating lubricating oil density at different temperature. | ||
DocID: DAAB184367 | Revision: b.6 | 2(2) |
4 | Duration | |
The lube oil consumption test will be run during a minimum 48 h period. | ||
5 | Lube Oil Consumption Measurements | |
If possible its recommended to run other tests before this test to have the engine running hours as high as possible. 100 running hours or more will give more reliable lube oil consumption figures. | ||
The engines should be run at a minimum of 85 % of maximum site power during the test. | ||
The lube oil separator should not run during the Lube Oil consumption test, because the Lube Oil consumption guarantee is based on the Engine consumption only, otherwise the oil discharged by the separator would be included in the engine oil consumption. However the maximum recommended time for running without Separator and new Lube Oil is 48 Hours on Heavy Fuel Oil. If longer Lube Oil test intervals is required, the Lube Oil test must be done running on LFO, to prevent that the oil quality deteriorates below limits. | ||
The temperature of the oil and the amount of air bubbles in the oil will affect the readings. In order to improve the accuracy of the measurements the conditions at the beginning and end of the test should be kept similar. The engine should run for a minimum of two hours at minimum 85 % load before the first reading is taken. The reading is taken 20 min after the engine has been stopped according to the normal shut down procedure. The final reading is similarly taken 20 min after the engine has stopped after the test. All pumps and separators in the lube oil system will be stopped at the same time as the engine. | ||
The level of oil will be recorded before and after the test with the dipstick in the engine oil sump. The Lube Oil consumption is calculated based on the differences on the oil level. The consumed oil amount is a function of the dipstick level difference and can be found as a reference document to the project specific test procedures. |
Title:
|
4. Stack Emissions Test | Xxx.XX: | DAAB195899 | |||||
Revision: | b.10 | |||||||
Author:
|
A Suominen / K Reunamo/ 20-elo-2008 | Status: | Draft | |||||
Draft by:
|
Xxxxxxx Xxxxxxx / 27-Mar-2009 | Pages: | 1 (4) | |||||
Project:
|
- | |||||||
Description:
|
Stack Emission Test | |||||||
Type:
|
Guideline |
1 | Objective |
1 | ||||
2 | Testing Procedures and Conditions |
1 | ||||
3 | Measurement Methods |
2 | ||||
4 | Calibration |
3 | ||||
5 | Uncertainty Assessment and Acceptance |
4 |
DocID: DAAB195899 | Revision: b.10 | 2(4) |
o | Gaseous components (analyser procedures): Emissions are calculated based on a minimum averaging time of 60 minutes. The period can differ somewhat from one hour without affecting the accuracy of the test. | ||
o | Gaseous components (discrete sampling): The emissions are calculated based on the average of minimum three samples. A minimum sampling time of 30 minutes per sample is recommended. Note that some methods may necessitate shorter sampling times. In such cases, the sampling times shall be checked case by case. | ||
o | Particle emissions: The particle emissions are calculated based on the average of minimum three samples. For heavy fuel oil a minimum sampling time per sample of 30 minutes is recommended. For light fuel oil 60 minutes is recommended, while for gas fired engines a minimum sampling time of 90 minutes is recommended. |
DocID: DAAB195899 | Revision: b.10 | 3(4) |
o | If the flue gas temperature exceeds 160 °C in the point of PM sampling, an in-stack filter shall be used for collecting the PM samples. | ||
o | In case the flue gas temperature is equal to or less than 160 °C at the point of PM sampling, a heated out-stack filter shall be applied. |
DocID: DAAB195899 | Revision: b.10 | 4(4) |
o | Instrument calibration drift of 2-5 % of calibration gas concentration: the results shall be corrected using the determined drift figures. | ||
o | If instrument calibration drift of more than 5 % of calibration gas concentration is determined, the reason for the drift shall be determined and the tests shall be re-performed. |
1. | We refer to the supply contract No. < > dated < > (hereinafter referred to as “the Contract”) signed between your corporation <Company name and address> (hereinafter referred to as “the Buyer”) and <Name and address of Wärtsilä Company> (hereinafter referred to as “the “the Supplier”) for supply and delivery of equipment for power plant, as more specifically determined in the Contract (hereinafter referred to as “the Goods”) for the total contract price of EUR <Price in figures> (say < > only) (hereinafter referred to as “the Contract Price”). | |
2. | In consideration of your agreeing to pay in advance an amount of EUR <Amount in figures> (say < > only) (hereinafter referred to as “the Advance Payment”) representing < > % (< > percent) of the Contract Price to the Supplier, and in consideration of you having agreed to accept this Guarantee covering Supplier’s fulfilment of its contractual obligations towards you, we <the bank>, being the Guarantor under this Guarantee, hereby irrevocably and unconditionally undertake to pay you, without any notice, reference or recourse to the Supplier or to any other person or entity, on receipt of your first written demand (hereinafter referred to as “the Demand”), any sum or sums up to an aggregate maximum amount up to but not exceeding EUR <Guarantee Amount> (say < > only); provided that any such Demand shall be accompanied by your duly signed statement stating: |
i) | that the Supplier is in breach of its obligation(s) under the underlying Contract; and | ||
ii) | the respect in which the Supplier is in breach and that the claimed amount for the described breach is due and payable by the Supplier in terms of the Contract, and, that you have given a notice of the breach to the Supplier according to the Contract and still the Supplier has not performed its obligations in accordance with the Contract. |
For the purpose of identification and authentication, the Buyer’s claim and the accompanied document(s) shall have to be presented to the Guarantor through the intermediary of Buyer’s Banker confirming that the signatures thereon are those of the authorised signatories of the Buyer. | ||
3. | We further agree that notwithstanding any claims, demands or objections by Supplier, any amount(s) claimed in the aggregate within <insert Guarantee Amount> notified by you as due and payable by Supplier in accordance with the terms of the Contract shall be accepted by us as conclusive evidence of the |
claimed amount being due and payable by us under this Guarantee without you needing otherwise to prove or show ground or reason for your demand of the sum specified therein. | ||
4. | We shall be entitled and obliged to rely and shall rely upon your demand presented hereunder and shall be under no duty to nor shall we inquire into any circumstances relating to any demand. We hereby waive any right we may have of first requiring the Buyer to pursue its legal remedies against Supplier. | |
5. | It is a condition for payment of any claim under this Guarantee that the Advance Payment of Euro <Amount in figures> (say < >) has been received by the Supplier to its account number <account number> with <Supplier’s Designated Bank>, in <City, Country> (Swift Code/BIC: <Swift Code/BIC of Supplier’s Designated Bank>). | |
7. | Upon our receipt from the Supplier of copies of invoices and delivery documents, indicating the value of delivered goods, the present guarantee shall be reduced, against receipt of such documents as conclusive evidence, by < advance payment in percent of equipment price> % of the gross invoice value for each set of these documents. | |
8. | This Guarantee shall remain in full force until: |
i) | our (Guarantor’s) receipt of, from the Supplier, executed copy of the Substantial Completion Certificate,; or | ||
ii) | <dd.mm.yyyy>1;or | ||
iii) | this advance payment guarantee is returned to the Guarantor by the Buyer; or | ||
iv) | payment by the Guarantor to the Buyer of the whole of the sum. |
whichever is the earlier (the “Expiry Date”). | ||
Consequently any claim thereof should be made and received by the above Expiry Date at the latest. Should we receive no claim from you by that date our liability will cease “ipso facto” and the present letter of Guarantee, whether returned to us or not, will definitely become null and void. | ||
9. | Multiple drawings and claims may be made by you under this Guarantee. | |
10. | We hereby agree that any part of the Contract may be amended, renewed, extended, modified, compromised, released or discharged by mutual agreement between you and the Supplierwithout in any way impairing or affecting our liabilities hereunder without notice to us and without the necessity for any additional endorsement, consent or guarantee by us, provided, however that the sum guaranteed shall not be decreased or increased. | |
11. | Any reference in this Guarantee to any contract, agreement, document or any other instrument is for ease of reference only. | |
12. | This guarantee is personal to you and not assignable. The beneficiary may not assign / transfer any benefit of this guarantee without our written consent which we will not unreasonably withhold or delay |
1 | The expiration date expressed in form of a calendar date shall be set to the date 60 days after, in the contract stipulated, delivery date. |
Page 2 of 3
13. | Except insofar as otherwise expressly stated, this Guarantee is subject to the Uniform Rules for Demand Guarantees, published as number 458 by the International Chamber of Commerce, and as to matters not covered by URDG458 shall be governed and construed in accordance with the laws of <the domicile country of the Guarantor> and all disputes arising hereunder shall be finally settled by arbitration under the Rules of Arbitration of the International Chamber of Commerce. |
Page 3 of 3
1. | We refer to the supply contract No. [ ] dated [ ](hereinafter referred to as “the Contract”) signed between your corporation [_Company name and address] (hereinafter referred to as “The Buyer”) and <Name and address of Wärtsilä Company> (hereinafter referred to as “the Supplier”) for supply and delivery of equipment for power plant, as more specifically determined in the Contract (hereinafter referred to as “the Goods”) for the total contract price of EUR[<Price in figures>] (say only) (hereinafter referred to as “the Contract Price”). | |
2. | We <the Guarantor> hereby issue in your favour our performance security being irrevocable guarantee for an amount up to but not exceeding <currency and amount> (say <currency and amount in words>) (hereinafter referred to as “Guarantee”) representing <______>% (<___> percent) of the Contract value, covering Supplier’s fulfilment of its obligations under the Contract. Any claims up to the above said aggregate shall be payable by us to you on receipt of your first written demand and your written statement stating: |
(i) | that the Supplier is in breach of its obligation(s) under the underlying Contract; | ||
(ii) | the respect in which the Supplier is in breach and that the claimed amount for the described breach is due and payable by the Supplier in terms of the Contract, and, that you have given a notice of the breach to the Supplier according to the Contract and still the Supplier has not performed its obligations in accordance with the Contract; and |
For the purpose of identification and authentication, the Buyer’s claim and the accompanied document(s) shall have to be presented to the Guarantor through the intermediary of Buyer’s Banker confirming that the signatures thereon are those of the authorised signatories of the Buyer | ||
3. | We further agree that notwithstanding any claims, demands or objections by Supplier, any amount(s) claimed in the aggregate within [insert Guarantee Amount] notified by you as due and payable by Supplier in accordance with the terms of the Contract shall be accepted by us as conclusive evidence of the claimed amount being due and payable by us under this Guarantee without you needing otherwise to prove or show ground or reason for your demand of the sum specified therein. | |
4. | We shall be entitled and obliged to rely and shall rely upon your demand presented hereunder and shall be under no duty to nor shall we inquire into any circumstances relating to any demand. We hereby waive any right we may have of first requiring the Buyer to pursue its legal remedies against Supplier and waive presentment, demand, protest or notice of any kind whatsoever. |
5. | The maximum amount of this guarantee shall be adjusted, automatically, following our receipt from the Supplier of a copy of the Buyer’s approved Performance Test Completion Certificate purportedly signed by its authorized officer(s), in value so that the outstanding value of the Guarantee equals Euro <insert % of contract price> (say:Euros ___) (the “Adjusted Guaranteed Amount”).] |
6. | Not in use |
7. | This Guarantee will expire on the earlier of (the “Expiry Date”): |
(i) | 30 days after the end of primary warranty period lapsing under the Contract [twelve (12)] months from the issue of Performance Test Completion Certificate or 15 months from the Delivery in accordance with clause 5.2(a), whichever first occur; or | ||
(ii) | <dd.mm.yyyy> in Helsinki, Finland.1; or | ||
iii) | this advance payment guarantee is returned to the Guarantor by the Buyer; or | ||
iv) | payment by the Guarantor to the Buyer of the whole of the sum. |
Consequently any claim thereof should be made to us by the above Expiry Date at the latest. Should we receive no claim from you by the Expiry Date our liability will cease “ipso facto” and the present Guarantee will whether returned to us or not definitely become null and void. | ||
8. | This Guarantee is personal to you and not assignable. The beneficiary may not assign / transfer any benefit of this guarantee without our written consent which we will not unreasonably withhold or delay | |
9. | Multiple drawings and claims may be made by you under this Guarantee. | |
10. | We hereby agree that any part of the Contract may be amended, renewed, extended, modified, compromised, released or discharged by mutual agreement between you and the Supplier without in any way impairing or affecting our liabilities hereunder without notice to us and without the necessity for any additional endorsement, consent or guarantee by us, provided, however that the sum guaranteed shall not be decreased or increased. | |
11. | Except insofar as otherwise expressly stated, this Guarantee is subject to Uniform Rules for Demand Guarantees, published as number 458 by the International Chamber of Commerce, and as to matters not covered by URDG458 shall be governed and construed in accordance with the laws of [<the domicile country of the Guarantor>] and all disputes arising hereunder shall be finally settled by arbitration under the Rules of Arbitration of the International Chamber of Commerce. |
1 | To be expressed as a calendar date, being 60 days after the projected date of end of Warranty period 12 months from the date of the scheduled performance tests in accordance with project time schedule |
Bank Guarantee |
G | |||||||||
To | FAVOUREE (‘Favouree’) Security for obligations of CLIENT (Customer) |
<<INSERT AMOUNT IN WORDS>> |
$ | 0.00 |
• | the Bank receives written notification from the Favouree that this guarantee is no longer required; | ||
• | the return of this guarantee to the Bank; | ||
• | payment to the Favouree by the Bank of the whole of the Guaranteed Amount or such lesser sum as may be required by the Favouree; | ||
• | the arrival of the Expiry Date namely #########, and no demand may be made on the Bank unless made and delivered to the Bank prior to the Expiry Date. |
Dated at
|
<<INSERT PLACE OF ISSUE>> | <<DAY>> | ||||
day of
|
<<INSERT MONTH>> | <<YEAR>> |
Commonwealth Bank of Australia
Premium Business Services
Institutional Lending Support
Xxxxx 0, 00 Xxxxxx Xxxxx Xxxxxx XXX 0000
Manager, Bank Guarantees
Institutional Lending Support
Manager
- General Power Plants |
Doc. Classification: | Confidential | |||||
Title:
|
Quality plan / ITP for Power Supply Uppgrade, LGL | DocID: | DBAB082233 | |||
(extended scope) | Revision: | -.7 | ||||
Author:
|
Xxxxxx Xxxxxxx / 09-Jul-2009 | Sheets: | 1 | |||
Draft by:
|
Xxxxxx Xxxxxxx / 14-Aug-2009 | Status: | Draft | |||
Xxxxx Xxxxx / 25-Aug-2009 | ||||||
Project:
|
P0900329 Lihir Power Barge | |||||
Description:
|
Quality Assurance | |||||
Type:
|
Quality Plan / ITP | |||||
plant project with the aim of achieving customer confidence in the provided power plant delivery.
Confidential
Page 1/8
Confidential
Page 2/8
Confidential
Page 3/8
Customer name: | Lihir Gold Mine | Project name: | Power Supply Uppgrade. LGL | |||
Project location: | Papua New Guinea | Project reference: | P0900329 |
Inspection code | |||||||||||||||||||||
Reference document/ | Test Method/ | Customer+ | Record/ | Remarks/ | |||||||||||||||||
Item | Equipment | Acceptance criteria | Checking criteria | Wärtsilä | Wärtsilä | Format | Notes | ||||||||||||||
A
|
POWER GENERATION | ||||||||||||||||||||
A1
|
GENERATING SET | ||||||||||||||||||||
A1.1
|
ENGINE | ||||||||||||||||||||
Factory acceptance test | IOS, specifications and Wärtsilä FAT procedure Manufacturers procedures | According to ISO 3046-1 standard | H | W | Test run protocol | sample attached | |||||||||||||||
Final inspection and protection | Manufacturers procedures | R | Inspection records | ||||||||||||||||||
A1.2
|
GENERATOR | ||||||||||||||||||||
Routine test | Drawings, specifications, IEC and Manufacturers routine test procedure | Routine test according to IEC and Visual inspection | W | Manufacturers routine test record | sample attached | ||||||||||||||||
A2
|
MECHANICAL AUXILIARY SYSTEMS | ||||||||||||||||||||
A2.0
|
AUXILIARY MODULES | ||||||||||||||||||||
Engine auxiliary module | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Fuel oil filter | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Fuel booster pump | Drawings, specifications and Manufacturers procedures | Functional test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Return fuel pump | Drawings, specifications and Manufacturers procedures | Functional test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Return fuel tank | Drawings, specifications and Manufacturers procedures | Leakage test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Pre heating unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Thermostatic valves | Drawings, specifications and Manufacturers procedures | Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Pressure increasing pump | Drawings, specifications and Manufacturers procedures | Functional test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Steam heater | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Module control panel | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Exhaust gas module | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Low temperature expansion tank | Drawings, specifications and Manufacturers procedures | Leakage test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Charge air silencer | Drawings, specifications and Manufacturers procedures | Visual inspection | W | Manufacturers Work shop report | |||||||||||||||||
Oil mist separator | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Work shop certificate |
Confidential
Page 4/8
Customer name: | Lihir Gold Mine | Project name: | Power Supply Uppgrade. LGL | |||
Project location: | Papua New Guinea | Project reference: | P0900329 |
Inspection code | |||||||||||||||||||||
Reference document/ | Test Method/ | Customer+ | Record/ | Remarks/ | |||||||||||||||||
Item | Equipment | Acceptance criteria | Checking criteria | Wärtsilä | Wärtsilä | Format | Notes | ||||||||||||||
A2.1
|
FUEL SYSTEM | ||||||||||||||||||||
A2.1.2
|
HEAVY FUEL OIL SYSTEM | ||||||||||||||||||||
Heavy fuel oil separator unit | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Heavy / light fuel oil feeder unit | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
A2.2
|
LUBRICATING OIL SYSTEM | ||||||||||||||||||||
Lubricating oil separator unit | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Lubricating oil transfer pump unit (mobile) | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Lubricating oil transfer pump unit (stationary) | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
A2.3
|
COMPRESSED AIR SYSTEM | ||||||||||||||||||||
Starting air bottle | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Starting air compressor unit | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Instrument air compressor unit | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
A2.4
|
COOLING SYSTEM | ||||||||||||||||||||
Cooling radiator | Drawings, specifications and Manufacturers procedures | Pressure test, Functional test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
A2.5
|
CHARGE AIR SYSTEM | ||||||||||||||||||||
Charge air filter | Drawings, specifications and Manufacturers procedures | Tightness check and Visual inspection | W | Manufacturers Work shop report | |||||||||||||||||
A2.6
|
EXHAUST SYSTEM | ||||||||||||||||||||
Exhaust gas silencer | Drawings, specifications and Manufacturers procedures | Visual inspection | W | Manufacturers Work shop report | |||||||||||||||||
A2.8
|
STATION SUPPORT SYSTEM | ||||||||||||||||||||
A2.8.1
|
OILY WATER TREATMENT SYSTEM | ||||||||||||||||||||
Oily water transfer pump unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Oily water feed pump unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate |
Confidential
Page 5/8
Customer name: | Lihir Gold Mine | Project name: | Power Supply Uppgrade. LGL | |||
Project location: | Papua New Guinea | Project reference: | P0900329 |
Inspection code | |||||||||||||||||||||
Reference document/ | Test Method/ | Customer+ | Record/ | Remarks/ | |||||||||||||||||
Item | Equipment | Acceptance criteria | Checking criteria | Wärtsilä | Wärtsilä | Format | Notes | ||||||||||||||
Oily water treatment unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Sludge loading pump unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
A2.8.2
|
WATER TREATMENT SYSTEM | ||||||||||||||||||||
Water treatment unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Water booster unit | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
A3
|
ELECTRICAL SYSTEM | ||||||||||||||||||||
A3.2
|
STATION SUPPORT SYSTEM | ||||||||||||||||||||
Station auxiliary transformer | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Black start unit | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Low voltage switchboard | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Frequency converter (for radiator) | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Engine auxiliary panel | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
A3.3
|
DC-SYSTEM | ||||||||||||||||||||
DC-system power plant control | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
A4
|
AUTOMATION SYSTEM | ||||||||||||||||||||
A4.2
|
CONTROL PANELS | ||||||||||||||||||||
Central common control panel | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Central generating set control panel | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Local generating set control panel | Drawings, specifications, IEC and Manufacturers FAT procedures | Factory test according to IEC and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
A5
|
HEAT RECOVERY SYSTEM | ||||||||||||||||||||
A5.1
|
STEAM GENERATION SYSTEM | ||||||||||||||||||||
A5.1.1
|
STEAM GENERATION SYSTEM FOR FUEL HEATING |
Confidential
Page 6/8
Customer name: | Lihir Gold Mine | Project name: | Power Supply Uppgrade. LGL | |||
Project location: | Papua New Guinea | Project reference: | P0900329 |
Inspection code | |||||||||||||||||||||
Reference document/ | Test Method/ | Customer+ | Record/ | Remarks/ | |||||||||||||||||
Item | Equipment | Acceptance criteria | Checking criteria | Wärtsilä | Wärtsilä | Format | Notes | ||||||||||||||
Exhaust gas boiler | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Heat recovery container | Drawings, specifications and Manufacturers procedures | Pressure test, Factory test and Visual Inspection | W | Manufacturers Factory test record | |||||||||||||||||
Steam header | Drawings, specifications and Manufacturers procedures | Pressure test and Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
B1
|
HULL | ||||||||||||||||||||
XXX | XXX | XXX | XXX | The hull construction is made according to the requirements of | |||||||||||||||||
Classification society, minor modifications of the layout | |||||||||||||||||||||
of the hull can be advised by Buyer, and if the Supplier accepts, and the modifications are not in conflict with the requirements from the Classification society, these modifications will implemented. | |||||||||||||||||||||
B2
|
CIVIL WORKS AND STRUCTURES | ||||||||||||||||||||
Material for substructures | Specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Superstructures pre-fabrication | Drawings, specifications and Manufacturers Procedures | Visual inspection | W | Manufacturers Work shop certificate | |||||||||||||||||
Ventilation units | Drawings, specifications and Manufacturers Procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Material for plumbing and sanitary installations | Specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Material for electrification | Specifications, IEC and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Material for gas detection | Specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Material for fire detection | Specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Material for fire fighting system | Specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Cranes and hoists | Specifications and Manufacturers procedures | Factory test and Visual inspection | W | Manufacturers Factory test record | |||||||||||||||||
Air conditioning units | Drawings, specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance | |||||||||||||||||
Oily water collection sump | Drawings, specifications and Manufacturers procedures | Leakage test and Visual inspection | W | Manufacturers Test record | |||||||||||||||||
Material for site works | Specifications and Manufacturers procedures | Visual inspection | W | Manufacturers certificate of compliance |
Confidential
Page 7/8
Customer name: | Lihir Gold Mine | Project name: | Power Supply Uppgrade. LGL | |||
Project location: | Papua New Guinea | Project reference: | P0900329 |
Inspection code | |||||||||||||||||||||
Reference document/ | Test Method/ | Customer+ | Record/ | Remarks/ | |||||||||||||||||
Item | Equipment | Acceptance criteria | Checking criteria | Wärtsilä | Wärtsilä | Format | Notes | ||||||||||||||
C
|
ENGINEERING | ||||||||||||||||||||
Tank diagram | W | Tank diagram | |||||||||||||||||||
Lightweight survey | W | Lightweight survey | |||||||||||||||||||
Stability booklet | W | Stability booklet |
Confidential
Page 8/8
Project: |
||
Engine No.: |
||
Engine Type:
|
W20V32 | |
Date(s): |
||
Third Party Inspection: |
Test protocol no Report Version: 3.0.0.2 Printed |
ENGINE DATA |
||||
Customer: |
||||
Type: |
W20V32 | |||
Manufacturing number: |
||||
Cylinder bore [mm]: |
||||
Piston stroke [mm]: |
||||
Rated power [kW]: |
||||
Nominal power [kW]: |
||||
Nominal speed [rpm]: |
||||
Direction of rotation: |
||||
INSTALLATION |
||||
Type: |
||||
Name: |
||||
Number |
||||
LOADING /AVR |
o | Alternator, in house | ||
o | Alternator, project (see specification below) | |||
o | Water brake (see specification below) | |||
o | AVR, in house | |||
o | AVR, project | |||
Manufacturer: |
||||
Type: |
||||
Number: |
||||
ENGINE COMPONENTS |
||||
Turbocharger: |
||||
Serial no.(s): |
||||
Air cooler: |
||||
Number(s): |
||||
Governor type: |
||||
Designation no: |
||||
Serial no.: |
Density at | Temp | Viscosity at | Temp | Lower Heating Value | ||||||||||||||||
Quality | [kg / l] | [C°] | [mm2 / s] | [C°] | [MJ/kg] | |||||||||||||||
HFO |
15 | 50 | ||||||||||||||||||
LFO |
15 | 40 |
LUBRICATING OIL |
Quality: Shell Argina T 40 |
Test protocol no Report Version: 3.0.0.2 Printed |
Order number: |
||||
Engine number: |
||||
Engine type: |
W20V32 | |||
Test run date(s): |
Engine | Load | |||||||||||||||||||||
Time: | Dur: | Speed | Shaft load | power | power | Oper. | ||||||||||||||||
Start | Stop | [min] | [rpm] | [%] | [kW] | h | [kW] | Fuel | data | Notice | ||||||||||||
13:35
|
13:40 | 5 | 750 | 0 | LFO | Verification of lube oil pressure shutdown. | ||||||||||||||||
13:40 | 13:55 | 15 | 750 | 0 | 25 | LFO | ||||||||||||||||
13:55 | 14:10 | 15 | 750 | 25 | LFO | |||||||||||||||||
14:10 | 14:15 | 5 | 750 | 0 | LFO | |||||||||||||||||
14:15 | 14:30 | 15 | 750 | 0 | 50 | LFO | ||||||||||||||||
14:30 | 14:50 | 20 | 750 | 50 | LFO | |||||||||||||||||
14:50 | 14:55 | 5 | 750 | 0 | LFO | |||||||||||||||||
14:55 | 15:10 | 15 | 750 | 0 | 75 | LFO | ||||||||||||||||
15:10 | 15:30 | 20 | 750 | 75 | LFO | |||||||||||||||||
15:30 | 15:35 | 5 | 750 | 0 | LFO | |||||||||||||||||
15:35 | 16:20 | 45 | 750 | 60 | HFO | X | ||||||||||||||||
16:20 | 17:05 | 45 | 750 | 85 | HFO | X | ||||||||||||||||
18:35 | 19:20 | 45 | 750 | 100 | HFO | X | ||||||||||||||||
19:20 | 20:05 | 45 | 750 | 100 | LFO | X |
Test Protocol No. Report Version: 3.0.0.3 Printed |
Test run date(s): |
07.01.2009 |
Mode | ||||||||||||||
Loadpoint: Power/ Torque |
60 | 85 | 100 | 100 | ||||||||||
Time |
||||||||||||||
Fuel |
HFO | HFO | HFO | LFO | ||||||||||
Ambient Data |
||||||||||||||
Total barometric pressure |
APT210 | hPa | ||||||||||||
Temperature of intake air |
ATE210 | C | ||||||||||||
Relative humidity of intake air |
AHR210 | % | ||||||||||||
Alternator data |
||||||||||||||
Alternator efficiency |
||||||||||||||
Alternator power |
kW | |||||||||||||
Alternator voltage, nominal |
V | |||||||||||||
Alternator current, nominal |
A | |||||||||||||
Engine Data |
||||||||||||||
General Data |
||||||||||||||
Power |
kW | |||||||||||||
Speed |
rpm | |||||||||||||
Load indicator position |
GT178 | |||||||||||||
Fuel rack position, A-bank |
GT165 | mm | ||||||||||||
Fuel rack position, B-bank |
GT165-2 | mm | ||||||||||||
Charge air system |
||||||||||||||
Turbocharger speed, A-bank |
SE518 | rpm | ||||||||||||
Turbocharger speed, B-bank |
SE528 | rpm | ||||||||||||
Charge air pressure |
PT601 | bar | ||||||||||||
Charge air temp, in air receiver |
TE601 | °C | ||||||||||||
Exhaust gas system |
||||||||||||||
Exh. gas temp, cylinder X0 |
XX0000X | |||||||||||||
Xxx. gas temp, cylinder A2 |
TE5021A | °C | ||||||||||||
Exh. gas temp, cylinder A3 |
TE5031A | °C | ||||||||||||
Exh. gas temp, cylinder A4 |
TE5041A | °C | ||||||||||||
Exh. gas temp, cylinder A5 |
TE5051A | °C | ||||||||||||
Exh. gas temp, cylinder A6 |
TE5061A | °C | ||||||||||||
Exh. gas temp, cylinder A7 |
TE5071A | °C | ||||||||||||
Exh. gas temp, cylinder A8 |
TE5081A | °C | ||||||||||||
Exh. gas temp, cylinder A9 |
TE5091A | °C | ||||||||||||
Exh. gas temp, cylinder A10 |
TE5101A | °C | ||||||||||||
Mean value |
°C | |||||||||||||
Exh. gas temp, cylinder B1 |
TE5011B | °C | ||||||||||||
Exh. gas temp, cylinder B2 |
TE5021B | °C | ||||||||||||
Exh. gas temp, cylinder B3 |
TE5031B | °C | ||||||||||||
Exh. gas temp, cylinder B4 |
TE5041B | °C | ||||||||||||
Exh. gas temp, cylinder B5 |
TE5051B | °C | ||||||||||||
Exh. gas temp, cylinder B6 |
TE5061B | °C | ||||||||||||
Exh. gas temp, cylinder B7 |
TE5071B | °C | ||||||||||||
Exh. gas temp, cylinder B8 |
TE5081B | °C | ||||||||||||
Exh. gas temp, cylinder B9 |
TE5091B | °C | ||||||||||||
Exh. gas temp, cylinder B10 |
TE5101B | °C | ||||||||||||
Mean value |
°C | |||||||||||||
Exh. gas temp. bef. TC, A-bank |
TE511 | °C | ||||||||||||
Exh. gas temp. bef. TC, B-bank |
TE521 | °C | ||||||||||||
Cylinder pressure |
||||||||||||||
Firing pressure, cylinder A1 |
bar | |||||||||||||
Firing pressure, cylinder A2 |
bar | |||||||||||||
Firing pressure, cylinder A3 |
bar | |||||||||||||
Firing pressure, cylinder A4 |
bar | |||||||||||||
Firing pressure, cylinder A5 |
bar | |||||||||||||
Firing pressure, cylinder A6 |
bar | |||||||||||||
Firing pressure, cylinder A7 |
bar | |||||||||||||
Firing pressure, cylinder A8 |
bar | |||||||||||||
Firing pressure, cylinder A9 |
bar | |||||||||||||
Firing pressure, cylinder A10 |
bar | |||||||||||||
Mean value |
bar | |||||||||||||
Firing pressure, cylinder B1 |
bar | |||||||||||||
Firing pressure, cylinder B2 |
bar | |||||||||||||
Firing pressure, cylinder B3 |
bar |
Test Protocol No. Report Version: 3.0.0.3 Printed |
PAAE138971 RA_058.QRP 09.01.2009 |
Test run date(s): |
07.01.2009 |
Mode | ||||||||||||||
Loadpoint: Power/ Torque |
60 | 85 | 100 | 100 | ||||||||||
Time |
||||||||||||||
Fuel |
HFO | HFO | HFO | LFO | ||||||||||
Firing pressure, cylinder B4 |
bar | |||||||||||||
Firing pressure, cylinder B5 |
bar | |||||||||||||
Firing pressure, cylinder B6 |
bar | |||||||||||||
Firing pressure, cylinder B7 |
bar | |||||||||||||
Firing pressure, cylinder B8 |
bar | |||||||||||||
Firing pressure, cylinder B9 |
bar | |||||||||||||
Firing pressure, cylinder B10 |
bar | |||||||||||||
Mean value |
bar | |||||||||||||
Installation data |
||||||||||||||
HT-water pressure |
PT401 | bar | ||||||||||||
LT-water pressure |
PT471 | bar | ||||||||||||
Lub. oil pressure |
PT201 | bar | ||||||||||||
Fuel oil pressure |
PT101 | bar | ||||||||||||
HT-water temp, bef. engine |
TE401 | °C | ||||||||||||
HT-water temp. aft. engine |
TE402 | °C | ||||||||||||
LT-water temp. bef. CAC |
TE471 | °C | ||||||||||||
LT-water temp. aft. LOG |
TE482 | °C | ||||||||||||
Lub. oil temp. bef. LOG |
TE231 | °C | ||||||||||||
Lub. oil temp. aft. LOC |
TE232 | °C | ||||||||||||
Fuel oil temperature |
TE101 | °C | ||||||||||||
Main bearings |
||||||||||||||
Main bearing temp, bearing 0 |
TE700 | °C | ||||||||||||
Main bearing temp, bearing 1 |
TE701 | °C | ||||||||||||
Main bearing temp, bearing 2 |
TE702 | °C | ||||||||||||
Main bearing temp, bearing 3 |
TE703 | °C | ||||||||||||
Main bearing temp, bearing 4 |
TE704 | °C | ||||||||||||
Main bearing temp, bearing 5 |
TE705 | °C | ||||||||||||
Main bearing temp, bearing 6 |
TE706 | °C | ||||||||||||
Main bearing temp, bearing 7 |
TE707 | °C | ||||||||||||
Main bearing temp, bearing 8 |
TE708 | °C | ||||||||||||
Main bearing temp, bearing 9 |
TE709 | °C | ||||||||||||
Main bearing temp, bearing 10 |
TE710 | °C | ||||||||||||
Main bearing temp, bearing 11 |
TE711 | °C | ||||||||||||
Mean value |
°C | |||||||||||||
Extra Measurements |
Test protocol no Report Version: 3.0.0.2 Printed |
PAAE138971 RA_0591.QRP 09.01.2009 |
ADJUSTMENT OF STOP SWITCHES:
|
Meas. | |
Alarm for low prelubrication oil pressure (bar) |
||
Stop for low lubrication oil pressure (bar) |
||
Engine overspeed device 1 (rpm) |
||
Engine overspeed device 2 (rpm) |
Meas. | ||||
ADJUSTMENT OF FUEL PUMPS:
|
Work value for the fuel rack (mm) | |||
Safety device released, the fuel rack (mm) | ||||
Stop value for the fuel rack (mm) | ||||
No load value for the fuel rack (mm) | ||||
No load value for governor |
A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |||||||||||||||||||||||||||||||||||||||||||||||
Del. comm. before TDC |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
B | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |||||||||||||||||||||||||||||||||||||||||||||||
Del. comm. before TDC |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||
PRESENT AT THE TEST RUN |
||
WÄRTSILÄ Finland Oy
|
Customer(s) |
Wärtsilä Finland Oy |
||
Vaasa Factory W 32 |
||
Test Run Manager, Delivery Centre Vaasa |
Test protocol no Report Version: 3.0.0.2 Printed |
PAAE138971 RA_060.QRP 09.01.2009 |
Room temperature when values were measured [°C]:
Initials:
Engine running continuosly before indicating [h]:
The time between stop and indicating [min]:
Temperature of lubricating oil [°C]:
Temperature of cooling water before engine [°C]:
Cylinder | ||||||||||||||||||||||||||||||||
Gauge | ||||||||||||||||||||||||||||||||
Position | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | ||||||||||||||||||||||
Rear side top Takasivu ylhäällä |
||||||||||||||||||||||||||||||||
Rear side Takasivulla |
||||||||||||||||||||||||||||||||
Bottom Alhaalla |
||||||||||||||||||||||||||||||||
Operating side KäyttösivulIa |
||||||||||||||||||||||||||||||||
Operating side top Käyttösivu ylhäällä |
||||||||||||||||||||||||||||||||
Room temperature when values were measured [°C]: 21 °C
Initials: PK
Cylinder | ||||||||||||||||||||||||||||||||||||||||||||||||||||
Guage | ||||||||||||||||||||||||||||||||||||||||||||||||||||
Position | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | ||||||||||||||||||||||||||||||||||||||||||
Rear side top Takasivu ylhäällä |
||||||||||||||||||||||||||||||||||||||||||||||||||||
Rear side Takasivulla |
||||||||||||||||||||||||||||||||||||||||||||||||||||
Bottom Alhaalla |
||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating side Käyöttdsivulla |
||||||||||||||||||||||||||||||||||||||||||||||||||||
Operating side top Käyttösivu ylhäällä |
||||||||||||||||||||||||||||||||||||||||||||||||||||
Test xxxxxxxx xx | XXXX000000 | |||
Report | RA_061.QRP | |||
Version: 3.0.0.2 | ||||
Printed | 09.01.2009 |
Order number:
Engine type:
Engine number:
Classification society:
Test run date(s)
Inspections: | Results: | |||
Big end bearing No. |
B4 | OK | ||
Main bearing No. |
7 | OK | ||
Thrust bearing |
Yes | OK | ||
Opening of covers |
Yes | OK |
WÄRTSILÄ Finland Oy
|
Customer(s) |
Vaasa Factory W 32
Test protocol no | PAAE138971 | |||
Report | RA_062.QRP | |||
Version: 3.0.0.3 | ||||
Printed | 09.01.2009 |
Engine number: |
||
Project: |
||
Order number: |
||
Engine type:
|
W20V32 | |
Output/100% [kW]: |
||
Speed [rpm]: |
||
Test run date(s): |
K
|
= | ratio of indicated power | s | = | 1 exponent | |||||
a
|
= | power adjustment factor | Mek | = | mechanical efficiency | |||||
Px
|
= | barometric pressure during test [hPa] | Qtest | = | lower heating value of the fuel oil during test [MJ/kg] | |||||
Pra
|
= | standard reference barometric pressure [1000 hPa] | Qiso | = | lower heating value of the fuel oil (ISO) [MJ / kg] | |||||
m
|
= | 0,7 exponent | Be | = | fuel oil consumption on test bed [g / kWh] | |||||
Tra
|
= | reference air temperature [298 K] | BISO | = | fuel oil consumption according to ISO [g / kWh] | |||||
Tx
|
= | air temperature during test [K] | M | = | measured fuel quantity [g] | |||||
n
|
= | 1,2 exponent | MLS | = | flow of clean leak fuel [g / s] | |||||
Tcr
|
= | reference charge air coolant temperature [298 K] | P | = | output [kW] | |||||
Tcx
|
= | charge air coolant temperature during test [K] | S | = | time [s] | |||||
EDP | = | engine driven pumps [g / kWh] (calculated with or without EDP according to the contract) | ||||||||
Air | Air | Coolant | Meas.fuel | Meas. con- | Clean | Eng.drlven | ||||||||||||||||||||||
Test | Load | Power | press. | temp | temp | amount | Mean | sumption | leak fuel | pumps | Be | Biso | ||||||||||||||||
no | % | Speed | Fuel | kW | hPa | °c | °C | kg | times | kg / h | kg / h | g / kWh | g / kWh | g / kWh | ||||||||||||||
1 | 100 |
Lower heating value (ISO) [MJ/kg]:
Mechanical efficiency:
TEST REPORT |
Order reference
Work nr:
Serial nr
Approved on the behalf of manufacturer | ABB Oy | |||
Machines | ||||
Final Testing |
Visiting Address
|
Postal Address | Telefax(Group) | ||
Xxxxxxxxxxxxxx 0 X
|
X.X.Xxx 000 | x000 00 00 00000 | ||
00380 XXXXXXXX
|
XX-00000 Xxxxxxxx | Telefax(Test floor) | ||
FINLAND | x000 00 00 00000 |
TEST REPORT |
Customer
|
Machine | Page | ||||
2 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
Standards
|
Classification society | |
Insulation class
|
Mounting | |
Temperature class
|
Protection class | |
Ambient temp. max
|
Duty |
Usage | Conn | Sn/Pn[kVA] | Un [V] | In [A] | p.f. | f [Hz] | Um [V] | Im [A] | Direction | n [rpm] |
1) | Visual inspection | ||
2) | Air gap measurement and bearing clearance | ||
3) | Insulation resistances before tests | ||
4) | Resistance measurement of windings and elements | ||
5) | First running | ||
6) | Direction of rotation, checking of phase sequence | ||
7) | No-load point | ||
8) | Short-circuit point | ||
9) | No-load and short circuit curve, U1 = f(Im) and I1 = f(Im) | ||
10) | Tests with regulator | ||
11) | Overspeed test | ||
12) | Vibration measurement after overspeed | ||
13) | High voltage test | ||
14) | Insulation resistances with Polarization index |
TEST REPORT |
Customer
|
Machine | Page | ||||
3 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
1) | Visual inspection |
Version | Notes | |||
A |
2) | Air gap measurement and bearing clearance |
Airgap | Bearing clearance | |||||||
Min [mm] | Max [mm] | [mm] | ||||||
Machine | D | |||||||
Exciter | N.D |
3) | Insulation resistances before tests |
Winding | R [Mohm] | U [V] | t1 [s] | ||||||||||||
Stator |
1000 | 60 | |||||||||||||
Rotor |
1000 | 60 | |||||||||||||
Exciter |
1000 | ||||||||||||||
Auxiliaries |
|||||||||||||||
Space heater |
500 | ||||||||||||||
Temperature detectors |
|||||||||||||||
Stator |
500 | ||||||||||||||
Bearing |
500 |
4) | Resistance measurement of windings and elements |
Resistances of windings | ||||||||||
T = 20 °C | ||||||||||
Armature windings | Ruv [ohm] | Ruw [ohm] | Rvw [ohm] | |||||||
Stator | ||||||||||
Rotor | ||||||||||
Exciter | ||||||||||
Stator | ||||||||||
Rotor: |
TEST REPORT |
Customer
|
Machine | Page | ||||
4 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
Resistances of detectors and space heaters | ||||||||||
T = |
Terminal box | Terminals | Position | R [ohm] | Xxxxxxxx | ||||
X0X
|
0XX0 — 1HE2 | Space heater | ||||||
X0X
|
0XX0 — 0XX0 | Xxxxx xxxxxx | ||||||
X0X
|
0X0 — 1R2 | Stator winding X | Xx-000 | |||||
X0X
|
0X0 — 0X0 | Xxxxxx xxxxxxx X | Xx-000 | |||||
X0X
|
0X0 — 3R2 | Stator winding W | Pt-100 | |||||
B3A
|
4R1 — 4R2 | Stator winding U (spare) | Pt-100 | |||||
B3A
|
5R1 — 5R2 | Stator winding V (spare) | Pt-100 | |||||
B3A
|
6R1 — 6R2 | Stator winding W (spare) | Pt-100 | |||||
B3A
|
30R1 — 30R2 | Bearing D-end | Pt-100 | |||||
B3A
|
40R1 — 40R2 | Bearing N.D-end | Pt-100 |
5) | First running |
6) | Direction of rotation, checking of phase sequence |
7) | No-load point |
n [rpm] | T [°C] | U1 [V] | Im [A] |
Voltage balances | ||||||||||
Stator | Uuv [V] | Uuw [V] | Uvw [V] | |||||||
1 |
8) | Short-circuit point |
n [rpm] | T [°C] | I1 [A] | Im [A] |
Current balances | ||||||||||
Stator | Iu [A] | Iv [A] | Iw [A] | |||||||
1 |
TEST REPORT |
Customer
|
Machine | Page | ||||
5 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
9) | No-load and short circuit curve, U1 = f(Im) and I1 = f(Im) |
Ratings U1 = I1 = n = No-load curve T = n = Im [A] U1 [p.u.] Short-circuit curve T = n = Im [A] I1 [p.u.] |
TEST REPORT |
Customer
|
Machine | Page | ||||
6 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
10) | Tests with regulator |
Version | ||||||||||||||||||
Position | ||||||||||||||||||
Manufacturer | ||||||||||||||||||
Type | ||||||||||||||||||
Serial nr | ||||||||||||||||||
Drawing nr | ||||||||||||||||||
Sustained short-circuit test | ||||||||||||||||||
I1, max = | ||||||||||||||||||
Im, max = | ||||||||||||||||||
n, min = | ||||||||||||||||||
ECL-10(Pos nr) = | Terminals | |||||||||||||||||
4 – 5 | 5 – 6 | 6 – 7 | 7 – 8 | 9 – 10 | 10 – 11 | 11 – 12 | 12 – 13 | |||||||||||
Other settings | ||||||||||||||||||
Remanence voltage, U = | ||||||||||||||||||
Voltage transformer | ||||||||||||||||||
Auxliary voltage, Uaux = | ||||||||||||||||||
Pulse Width of UM | ||||||||||||||||||
Direction of Permanent Magnet | ||||||||||||||||||
Voltage build-up and regulation at no-load |
TEST REPORT |
Customer
|
Machine | Page | ||||
7 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
11) | Overspeed test |
12) | Vibration measurement after overspeed |
Bearing position | U [V] | I [A] | n [rpm] | Horizontal | Vertical | Axial | Unit |
TEST REPORT |
Customer
|
Machine | Page | ||||
8 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
13) | High voltage test |
Winding | U [V] | t [s] | f [Hz] | |||||||
Stator | ||||||||||
Rotor | ||||||||||
Exciter | ||||||||||
Auxiliaries | ||||||||||
Space heater | ||||||||||
Temperature detectors | ||||||||||
Stator | ||||||||||
Bearing |
14) | Insulation resistances with Polarization index |
T = | ||||||||||||||
Winding | R [Mohm] | U [V] | t [s] | R2 [Mohm] | t2 [s] | R/R2 | ||||||||
Rotor | ||||||||||||||
Exciter | ||||||||||||||
Auxiliaries | ||||||||||||||
Space | ||||||||||||||
heater | ||||||||||||||
Temperature detectors | ||||||||||||||
Stator | ||||||||||||||
Bearing |
TEST REPORT |
Customer
|
Machine | Page | ||||
A1/1 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
1) | Tests with regulator_Basic settings |
TEST REPORT |
Customer
|
Machine | Page | ||||
A1/2 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
TEST REPORT |
Customer
|
Machine | Page | ||||
A1/3 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
TEST REPORT |
Customer
|
Machine | Page | ||||
A1/4 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
TEST REPORT |
Customer
|
Machine | Page | ||||
A1/5 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
TEST REPORT |
Customer
|
Machine | Page | ||||
A1/6 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
TEST REPORT |
Customer
|
Machine | Page | ||||
15 | ||||||
Order reference
|
Work nr: | Serial nr | Revision | |||
A | ||||||
Project
|
Approved | Report rev: | ||||
A |
Test bay |
||
Author |
||
Printed: 16.7.2009 | ||
Number of pages 15 |
||
2.1/18 |
By:
Title:
CONTRACTOR
By:
Title:
CERTIFICATE
or
[calculated the amount of liquidated damages payable to Buyer ]
or
[calculated the bonus to be received from Buyer ]
The calculations are described in Exhibit C — Performance test guidelines
The amounts of any such liquidated damages / bonuses are according to article 8 of this Contract.
By: