Contractual Penalty. If an exhibitor is an entrepreneur in terms of § 14 of the Ger- man Civil Code, LMS is entitled to demand a contractual pen- alty from the exhibitor in the following cases:
14.1 In the event of noncompliance with the terms of 6.2 and
Contractual Penalty. If a contractual penalty has been agreed between the Par- ties and has accrued, Eberspächer may still assert this until the respective payment is due, without this reservation being required in accordance with § 341 paragraph 3 BGB.
Contractual Penalty. 7.16.1 If Contractor is in default of a Besondere Einkaufsbedingungen für Bauleistungen der TenneT TSO GmbH DATUM SEITE 1. Juli 2020 37 von 46 Special Terms of Purchase Order for the Execution of Construction Work of TenneT TSO GmbH Vertragsstrafe in Höhe von 0,2 % des auf die Teilleistungen, auf die sich die jeweilige Vertragsfrist bezieht, entfal- lenden Anteils an der Netto- Auftragssumme zu zahlen. Die Vertragsstrafe ist nicht verwirkt, wenn der Auftragnehmer die Firstüberschreitung nicht zu vertreten hat. Auf vorangehende Vertragsfristen verwirkte Vertragsstrafen werden bei Überschreitungen auch der nachfolgenden Vertragsfristen berücksichtigt, so dass eine Kumulierung der Einzelvertragsstrafen ausgeschlossen ist. Wegen Überschreitung von Zwischenfristen bereits verwirkte Vertragsstrafen entfallen nachträglich, sofern der Auftragnehmer dennoch den Gesamt-Fertigstellungstermin einhält.
6.2 Die Regelung dieser Ziffer 6.1 BEB Bau gilt ebenso im Falle der Vereinbarung einer neuen, von der ursprünglich vereinbarten Vertragsfrist abweichenden Vertragsfrist. Unerheblich ist, ob die Parteien die neue Vertragsfrist ausdrücklich einvernehmlich vereinbaren oder ob sie aus der Anwendung dieser BEB Bau oder des Gesetzes folgt, beispielsweise in Folge einer Verlängerung von Vertragsfristen wegen Behinderungen etc. contractual deadline agreed under clause
4.1 of these Special PO Terms for Construction, he must pay a contractual penalty in the amount of 0.2 % of the portion of the net amount of contract attributable to the partial performance to which the respective contractual period relates for each working day on which the deadline is exceeded. Contractual penalty is not forfeited, if Contractor is not accountable for exceeding contractual deadlines. Any forfeited contractual penalties for exceeded interim deadlines are taken into account in case of excess of the following contractual deadlines, so that any accumulation of separate contractual penalties is excluded. Contractual penalties forfeited for interim deadlines shall be omitted subsequently, if Contractor meets the overall completion deadline.
Contractual Penalty. 1. In the case of default OTT shall have the right to demand 0.5 percent of the value of the order per calendar day as a contractual penalty as long as the Contractor is in default.
2. The total sum of the penalty shall be limited to a maximum of 10 percent of the total value of the order. Even if XXX accepts delayed deliveries from the Contractor, OTT will nevertheless demand the penalty.
3. The deduction of the contractual penalty shall neither release the Contractor from its contractual obligations in relation to the goods/service nor will this exclude the assertion of claims for damages in excess of the penalty.
4. The penalty will be charged directly according to the schedule determined by XXX in the form of a debit note.
Contractual Penalty. 5.1 The Contractor shall pay the agreed contrac- tual penalty if a provisional deadline or comple- tion date named in the schedule or in the offer is exceeded. The payment of the contractual penalty shall affect neither the Contractor’s ob- ligations to supply the contractual services nor the Contractor’s obligations towards Arcadis regarding compensation of damages incurred by Arcadis.
5.2 Expense receipts shall only be reimbursed if this has been specifically agreed upon in writ- ing, and if the original receipts have been signed by the person named in the order for this, and are attached to the invoice.
5.3 Payments shall be effected within 30 days of receipt of invoices, unless otherwise agreed in the order. Arcadis shall not be held responsible for delays in payment which have arisen due to missing or incomplete invoice documentation, which shall effectively postpone the payment date.
5.4 Arcadis ist berechtigt, Zahlungen zurückzu- halten, wenn Anlass zu Beanstandungen der Lieferungen und Leistungen des Auftragneh- mers besteht. Eine Aufrechnung oder Gel- tendmachung von Zurückbehaltungsrechten gegen den Anspruch von Arcadis ist nur mit einer unbestrittenen oder rechtskräftig fest- gestellten Forderung zulässig. Eine Abtre- tung von An-sprüchen des Auftragnehmers an Dritte ist ausgeschlossen.
Contractual Penalty. 6.1 If Contractor is in default of a contractual deadline agreed under clause 4.1 of these Special PO Terms for Construction, he must pay a contractual penalty in the amount of 0.2 % of the net amount of contract for each working day of the deadline overrun for which he is responsible. 6.2 The provisions of this clause 6 of these Special PO Terms for Construction also apply in the event that new deadlines at variance to the originally agreed deadline are agreed. It is of no relevance whether the parties mutually agree the new deadline or if it follows from the application of these Special PO Terms for Construction, such as in the case that a deadline is extended due to obstructions, etc. 6.3 TenneT may claim the contractual penalty as late as the final payment even if TenneT has not expressly reserved this right in the case of the acceptance (formal acceptance) or late delivery (performance). Any payable contractual penalties shall be deducted from the final invoice.
Contractual Penalty. 6.1. If the customer defaults in taking delivery of the purchased object by more than 10 days, and a grace period of 14 days fixed by ULTRATRONIK expires without outcome, ULTRATRONIK shall be entitled to demand a contractual penalty of 0.5% of the total net purchase price for each additional day of delay for a maximum of 5% of the total net purchase price, and to rescind from the agreement. The assertion of other compensation claims for default shall not be affected.
6.2. If the customer defaults in taking delivery of individual calls in call-off orders, the worth of the individual call-off amount shall be used in place of the total purchase price. In this case, the right of rescission shall be restricted to that portion of the call-off amount for which the customer defaults in taking delivery.
Contractual Penalty. For every single breach by the Co-operation Partner of its obligations under this Agreement BEULCO is entitled to demand a contractual penalty in the sum of 50,000.00 Euro. The Co-operation Partner shall be precluded from relying on the principles of continued breach as a defence. The contractual penalty payments are limited to a total amount of 150,000 Euro. Payment of the contractual penalty shall not preclude BEULCO from seeking injunctive relief or claiming additional damages upon evidence of the same. The contractual penalty shall be offset against damages claimed.
Contractual Penalty. If an exhibitor is an entrepreneur in terms of § 14 of the German Civil Code, LMS is entitled to demand a contractual penalty from the exhib- itor in the following cases:
14.1 In the event of noncompliance with the terms of 6.2 and 6.3 to the amount of 500.00 €, unless there is evidence of infringement according to 6.2.2 or 6.3.2, where this regulation remains
14.2 In the event of noncompliance with the terms of 7.1 to 7.5 and 7.7 to 7.9 in the amount of 5,500.00 €
14.3 In the event of noncompliance with the terms of 8.1 in the amount of 5,500.00 €
14.4 In the event of noncompliance with the terms of 9 in the amount of 1,000.00 €
14.5 bei Zuwiderhandlung gegen die Bestimmungen von 11 in Höhe von 2.500,00 €, mit Ausnahme eines Verstoßes gegen die Bestim- mungen von 11.2, bei dem ein Betrag von 5.500,00 € in Ansatz kommt und zwar für jeden Einzelfall der Zuwiderhandlung, unbeschadet des Rechts der Geltendmachung von Schadensersatzansprüchen. § 341 Abs. 3 BGB kommt nicht zur Anwendung.
Contractual Penalty. If the customer culpably violates his obligations under the confidentiality and secrecy regulations (see Sections
10.1 and 10.2), he undertakes to pay a contractual penalty to DiCommerce. The amount of the contractual penalty is up to 5,000 EUR per violation and is determined by DiCommerce at its reasonable discretion. The customer has the right to have the appropriateness of the determined contractual penalty reviewed by a court. DiCommerce reserves the right to assert further claims for damages, whereby the contractual penalty is offset against such a claim for damages. Xxxxxxxxxx 0, 00000 Xxxxxxx xx Xxxxx Registergericht Düsseldorf, HRB 97895 Steuernummer: 135/5717/1538 Ust-IdNr. DE354512865 Geschäftsführer: Xxxxxx Xxxxxxxxxxxx Tel: +49 (0) 2173 - 999 035 - 0 Mail: xxxx@xxxxxxxxxx.xx Web: xxx.xxxxxxxxxx.xx Bankverbindungen: VR Bank: XX00 0000 0000 0000 0000 00 Finom Bank: XX00 0000 0000 0000 0000 00 eines weitergehenden Schadens bleibt DiCommerce vorbehalten, wobei die Vertragsstrafe auf einen solchen Schadensersatzanspruch angerechnet wird.