Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.
Notice of Completion means a document issued by the Department or Delegated Agency at the end of project construction when all items and conditions of the approved Sediment and Stormwater Management Plan have been satisfied, post construction verification documents demonstrate that the stormwater management systems have been constructed in accordance with the approved Sediment and Stormwater Management Plan, and final stabilization of disturbed areas on the site has been achieved.
Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;
Completion Notice means a notice issued by the Developer in accordance with clause 6.1.
Project Completion Date means the date on which the Completion Certificate is issued;
project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;
Notice to Proceed (NTP) means the authorization issued by the CO to start performance on this Contract.
Construction Completion means physical construction of a cleanup action component is complete.
Completion Schedule means the fulfilment of the Related Services by the Supplier in accordance with the terms and conditions set forth in the Contract;
Construction Completion Certificate means a certificate of the I-Bank to the effect that the construction of the Project is complete.
Improvement completion assurance means a surety bond, letter of credit,
Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.
Notice of assessment means a written notice by the division, based on a citation, that the employer must pay the amount of wages, penalties, or fines assessed.
Construction Work means any work in connection with⎯
Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;
Notice to Proceed means notice issued by the OPWC pursuant to Section IV of this Agreement. "OPWC" means the Ohio Public Works Commission created pursuant to Revised Code Section 164.02.
Phase 1 means the phase of the ATP comprised of: (1) improvements to the State Street Substation; (2) construction of the Proposed Line; (3) the rebuilding of NYSEG’s existing Lines 971 and 000 xxxxx xx Xxxxxxxx Xxxx xx the NYSEG ROW to allow for construction of the Proposed Line as intended; (4) improvements to the Elbridge Substation to accept the Proposed Line; and (5) National Grid’s conveyance to NYSEG of the NYSEG Acquired ROW and such other land interests as contemplated by the Purchase and Sale Agreement.
Construction project means the same as that term is defined in Section 38-1a-102.
Mechanical Completion means that (a) all components and systems of the Project have been properly constructed, installed and functionally tested according to EPC Contract requirements in a safe and prudent manner that does not void any equipment or system warranties or violate any permits, approvals or Laws; (b) the Project is ready for testing and commissioning, as applicable; (c) Seller has provided written acceptance to the EPC Contractor of mechanical completion as that term is specifically defined in the EPC Contract.
Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.
Construction Schedule means a construction schedule indicating the planned start and completion dates of the major activities of the Work as set out in Appendix [ ], a future Appendix;
Phase I Report means, with respect to any Facility, a report that (i) conforms to the ASTM Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process, E 1527, (ii) was conducted no more than six months prior to the date such report is required to be delivered hereunder, by one or more environmental consulting firms reasonably satisfactory to Administrative Agent, (iii) includes an assessment of asbestos-containing materials at such Facility, (iv) is accompanied by (a) an estimate of the reasonable worst-case cost of investigating and remediating any Hazardous Materials Activity identified in the Phase I Report as giving rise to an actual or potential material violation of any Environmental Law or as presenting a material risk of giving rise to a material Environmental Claim, and (b) a current compliance audit setting forth an assessment of Holdings’, its Subsidiaries’ and such Facility’s current and past compliance with Environmental Laws and an estimate of the cost of rectifying any non-compliance with current Environmental Laws identified therein and the cost of compliance with reasonably anticipated future Environmental Laws identified therein.
Phase I means the first part of the tuition incentive assistance program defined as the academic period of 80 semester or 120 term credits, or less, leading to an associate degree or certificate.
Full Notice to Proceed means that all material third party contractors have been given the notice to proceed with construction by the Capacity Market Seller or its agent, with a guaranteed completion date backed by liquidated damages.
Project Deliverables means the Project deliverables set out in Schedule 2. Project Material means all the material including but not limited to documents, computer software, and data stored by any means which is created by the Fellow in the course of undertaking the Project.
Project Commissioning means the Project will be considered as commissioned if all equipment as per rated project capacity has been installed and energy has flown into grid, in line with the Commissioning procedures defined in the RfS/PPA.