Examples of Project Status Schedule Update in a sentence
Wassmer made a motion to put Bogazianos’ name forward as GSCP’s Chair nomination for next AY; Topping seconded; the body voted unanimously to do so.
Note any other changes made to the schedule including modifications to the calendars or constraints.d. If the current Project Status Schedule Update is revised subsequent to submittal of a time impact analysis but prior to its acceptance, DB Contractor shall promptly indicate, in writing, to TxDOT the need for any modification to its time impact analysis.DB Contractor shall submit the following with each TIA Submittal:a.
The Project Status Schedule Update shall accurately reflect the current status of the Project including all activities completed as of the Commercial Closing Date of the current PBS, recovery schedules, schedule revisions due to Relief Events, approved change orders, Development Entity’s detailed schedule for completing the Work and all information and reporting required for the Project Baseline Schedule.
The Project Status Schedule Update shall accurately reflect updated progress as of the Commercial Closing Date of the updated PBS, forecast finish for in-progress schedule activities and reforecast early dates and late dates for remaining schedule activities and shall indicate the overall physically complete percent of the D&C Work.
Development Entity shall submit the Monthly Progress Report, including the corresponding Project Status Schedule Update as required by Section 2.1.1.2, no later than the 15th day of each month following the Commercial Closing Date.
The date for use in calculating the Project Status Schedule Update shall be the first day of the following month.
The Project Status Schedule Update shall be submitted monthly, if applicable, until Final Acceptance of the Work.
No changes in activity durations, calendar assignments, logic ties, or constraints will be allowed in the Project Status Schedule Update without prior written acceptance of GDOT.
Matt reported that he had discussed this with the mayor and recommend we table this until the next council meeting.
Developer shall repeat the submittal process until receiving TxDOT approval of the submittal.2.1.1.3 Project Status Schedule Updates2.1.1.3.1 Project Status Schedule Update RequirementsDeveloper shall provide schedule updates that comply with all PBS requirements.