Examples of Project Baseline Schedule in a sentence
All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.
The Proposal will be deemed non-responsive if the number of days is greater than that shown in the Preliminary Project Baseline Schedule Proposer shall submit a Proposal Price Value using Form O setting forth the Price Value to be used in the determination of the Price Score and Total Proposal Score.
The Parties shall use the Project Baseline Schedule for planning and monitoring the progress of the Design Work and Construction Work.
The Project Baseline Schedule shall include the Baseline Substantial Completion Date set forth in the Preliminary Project Baseline Schedule.
The number of days to achieve Substantial Completion shown on Form P may be less than that represented in the Preliminary Project Baseline Schedule included with the Technical Proposal.
All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates or Completion Deadlines.
Developer shall submit a single hardcopy of the Project Baseline Schedule on full-size (24” x 36”) color plot sheets, along with an electronic version of the schedule in its native format.
The Project Baseline Schedule shall be built through the input of all Trade Contractors and is subject to reasonable change during the course of the Project.
Trade Contractor is also aware that CM will be building a Project Baseline Schedule based on the input of all Trade Contractors so the dates shown on the Outline Schedule are only approximate dates and durations.
All Float contained in the Project Schedule, as shown in the Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.