Project Baseline Schedule definition

Project Baseline Schedule means the logic-based critical path schedule for all Work leading up to and including Final Acceptance for all Project Segments, as described in Section 2 of the Technical Provisions.
Project Baseline Schedule means the approved critical path schedule prepared by the Design-Build Entity for performance of all Work within the Contract Time, as approved by the Owner.
Project Baseline Schedule means the approved critical path schedule prepared by the Design-Builder for performance of all Work.

Examples of Project Baseline Schedule in a sentence

  • All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.

  • The Proposal will be deemed non-responsive if the number of days is greater than that shown in the Preliminary Project Baseline Schedule Proposer shall submit a Proposal Price Value using Form O setting forth the Price Value to be used in the determination of the Price Score and Total Proposal Score.

  • The Parties shall use the Project Baseline Schedule for planning and monitoring the progress of the Design Work and Construction Work.

  • The Project Baseline Schedule shall include the Baseline Substantial Completion Date set forth in the Preliminary Project Baseline Schedule.

  • The number of days to achieve Substantial Completion shown on Form P may be less than that represented in the Preliminary Project Baseline Schedule included with the Technical Proposal.

  • All Float contained in the Project Schedule, as shown in the initial Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates or Completion Deadlines.

  • Developer shall submit a single hardcopy of the Project Baseline Schedule on full-size (24” x 36”) color plot sheets, along with an electronic version of the schedule in its native format.

  • The Project Baseline Schedule shall be built through the input of all Trade Contractors and is subject to reasonable change during the course of the Project.

  • Trade Contractor is also aware that CM will be building a Project Baseline Schedule based on the input of all Trade Contractors so the dates shown on the Outline Schedule are only approximate dates and durations.

  • All Float contained in the Project Schedule, as shown in the Preliminary Project Baseline Schedule or as generated thereafter, shall be considered a Project resource available to either Party or both Parties as needed to absorb delays caused by any event, achieve schedule milestones, interim completion dates and/or Completion Deadlines.


More Definitions of Project Baseline Schedule

Project Baseline Schedule means the logic-based critical path schedule for all D&C Work as described in the Requirements and Provisions for Work, as may be revised and updated in accordance with the Project Documents.
Project Baseline Schedule means the logic-based critical path schedule for all Work from commencement of the Work leading up to and including, without limitation, each Milestone Schedule Deadline, Substantial Completion and Final Acceptance, to be prepared by Design- Build Team consistent with and taking into account the Milestone Schedule, as and to the extent such schedule has been approved by GDOT, all as more particularly described in Section 2.3 of the Technical Provisions, and all revisions to such schedule as provided in the DB Documents. The Project Baseline Schedule shall not mean the Project Status Schedule Updates as set forth in Section 2.3.4 of the Technical Provisions, nor shall such Project Status Schedule Updates constitute revisions or amendments to the Project Baseline Schedule.
Project Baseline Schedule means the schedule meeting the requirements of Appendix A9 (Scheduling Procedures and Reporting Requirements) approved by Company pursuant to Section 4.3.2 (Project Baseline Schedule).
Project Baseline Schedule shall have the meaning set forth in the Project Control Requirements.

Related to Project Baseline Schedule

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Milestone Schedule means Seller’s milestone schedule, the form of which is attached to this Agreement as Exhibit Q.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • The Contract Price/ Project Cost means the price payable to the Vendor under the Contract for the full and proper performance of its contractual obligations.