REVIEW OF THE FRAMEWORK PRICES. 5.1 Subject to paragraphs 4.1.1 and 4.1.2 above, the Framework Prices will remain fixed for one
(1) Year from the Commencement Date.
5.2 The Supplier may request a variation in the Framework Prices in accordance with the remaining provisions of this paragraph 5 subject always to:
5.2.1 the Supplier's request being submitted in writing at least three (3) Months before the effective date for the proposed variation ("Adjustment Date");
5.2.2 the cap on any increase in the Framework Prices, whereby any increase in the Framework Prices will be limited to the recommendations announced by the relevant independent pay review body and/or annual percentage change in RPIX Index for that given period at the relevant Adjustment Date; and
5.2.3 the agreement of the Authority.
5.3 The earliest Adjustment Date for any increase in the Framework Prices in accordance with this paragraph 5 will be the first (1) Working Day following the first (1st) anniversary of the Commencement Date. Thereafter any subsequent increase to any of the Framework Prices in accordance with this paragraph 5 shall not occur before the anniversary of the previous Adjustment Date.
5.4 To make a request for a variation of some or all of the Framework Prices in accordance with this paragraph 5, the Supplier shall provide the Authority with:
5.4.1 a list of the Framework Prices it wishes to review;
5.4.2 for each of the Framework Prices under review, written evidence of the justification for the requested increase including:
a) a breakdown of the profit and cost components that comprise the relevant Framework Price;
b) details of the movement in the different identified cost components of the relevant Framework Price;
c) reasons for the movement in the different identified cost components of the relevant Framework Price; and
d) evidence that the Supplier has attempted to mitigate against the increase in the relevant cost components.
REVIEW OF THE FRAMEWORK PRICES. 5.1 Subject to paragraphs 4.1.1 and 4.1.2, the Framework Prices will remain fixed for one (1) Year from the Commencement Date.
5.2 The Supplier may request a variation in the Framework Prices in accordance with the remaining provisions of this paragraph 5Error! Reference source not found. subject always to:
5.2.1 the Supplier's request being submitted in writing at least three (3) Months before the effective date for the proposed variation ("Adjustment Date");
5.2.2 the cap on any increase in the Framework Prices, whereby any increase in the Framework Prices will be limited to the recommendations announced by the relevant independent pay review body and/or annual percentage change in RPIX Index for that given period at the relevant Adjustment Date; and
5.2.3 the agreement of the Authority.
5.3 The earliest Adjustment Date for any increase in the Framework Prices in accordance with this paragraph 5 will be the first (1) Working Day following the first (1st) anniversary of the Commencement Date. Thereafter any subsequent increase to any of the Framework Prices in accordance with this paragraph 5 Error! Reference source not found.shall not occur before the anniversary of the previous Adjustment Date.
REVIEW OF THE FRAMEWORK PRICES. LOTS 1 – 10
REVIEW OF THE FRAMEWORK PRICES. Subject to paragraphs 3.1.1 and 3.1.2, the Framework Prices will remain fixed for the first two (2) Contract Years.
REVIEW OF THE FRAMEWORK PRICES. LOTS 11 AND 12
5.1 Subject to Paragraphs 3.1.1, the Framework Prices for Services listed at Annex B shall not be increased for two (2) Years from the Commencement Date.
5.2 Following the second anniversary of the Commencement Date, the Framework Prices shall be reviewed annually by the Parties and increased or decreased by the agreement of the Parties and in reference to the relevant rates for such Services as listed in the ICT labour index found at this site (or any substantially successor site should this site no longer be made available): xxxx://xxx.xxx.xxx.xx/ons/rel/lms/labour-market-statistics/december- 2011/index-of-data-tables.html#tab-Earnings-tables
5.3 The Framework Prices for Services offered under Lots 11 and 12 shall be increased by no more than the annual rate of increase for the applicable review period.
REVIEW OF THE FRAMEWORK PRICES. 3.1 The Contractor can request a variation in the Framework Prices in accordance with the remaining provisions of this Paragraph 3 (Review of the Framework Prices) subject always to:
3.1.1 the Contractor's request being submitted at least three (3) Months before the effective date for the proposed variation (the "Adjustment Date");
3.1.2 the cap on any increase in the Framework Prices in accordance with Paragraph 1.3 above; and
3.1.3 the agreement of the Authority.
3.2 The earliest Adjustment Date for any increase in any of the Framework Prices in accordance with this Paragraph 3 (Review of the Framework Prices) will be the first (1st) Working Day following the first (1st) anniversary of the Commencement Date. Review will occur on an annual basis thereafter and any subsequent increase to any of the Framework Prices in accordance with this Paragraph 3 (Review of the Framework Prices).
3.3 To make a request for a variation of some or all of the Framework Prices in accordance with this Paragraph 3 (Review of the Framework Prices), the Contractor shall provide the Authority with a list of the Framework Prices it wishes to review.
3.4 The Authority will:
3.4.1 refer in its review to the "CPI Index" (which shall mean the "Consumer Prices Index (CPI)" as published by the Office of National Statistics ; and
3.4.2 apply the following definition to the phrase the "annual percentage change in the CPI Index" which for the purposes of this Schedule 2 (Price Schedule) shall mean the percentage increase in the most recently published CPI Index which has been confirmed by the Office for National Statistics at the time of the request for variation.
3.5 Where the published CPI Index figure at the relevant Adjustment Date is stated to be a provisional figure or is subsequently amended, that figure shall apply unless the Authority and the Contractor shall agree otherwise.
REVIEW OF THE FRAMEWORK PRICES. Subject to paragraphs 2.1.1 and 2.1.2, the Framework Prices will remain fixed for six
REVIEW OF THE FRAMEWORK PRICES. 6.1 Subject to paragraphs 5.1.1 and 5.1.2, the Framework Prices will remain fixed for two (2) Years from the Commencement Date.
6.2 The Supplier may request a variation in the Framework Prices in accordance with the remaining provisions of this paragraph 6 subject always to:
6.2.1 the Supplier's request being submitted to the Authority in writing at least three (3) Months before the intended effective date for the proposed variation (the "Indexation Adjustment Date"); and
6.2.2 the written agreement of the Authority.
6.3 The earliest Indexation Adjustment Date for any increase in the Framework Prices in accordance with this paragraph 6 will be the first (1st) Working Day following the second (2nd) anniversary of the Commencement Date. Thereafter any subsequent increase to any of the Framework Prices in accordance with this paragraph 6 shall not occur before the anniversary of the previous Indexation Adjustment Date.
6.4 To make a request for a variation of some or all of the Framework Prices in accordance with this paragraph 6, the Supplier shall provide the Authority with:
6.4.1 a list of the Framework Prices it wishes to review;
6.4.2 for each of the Framework Prices under review, written evidence of the justification for the requested increase including:
6.4.2.1 a breakdown of the profit and cost components that comprise the relevant Framework Price;
6.4.2.2 details of the movement in the different identified cost components of the relevant Framework Price;
6.4.2.3 reasons for the movement in the different identified cost components of the relevant Framework Price; and
6.4.2.4 evidence that the Supplier has attempted to mitigate against the increase in the relevant cost components.
REVIEW OF THE FRAMEWORK PRICES. Subject to paragraphs 12.1.1 and 12.1.2, the Framework Prices will remain fixed for the Initial Period. The Supplier may request a variation in the Framework Prices in accordance with the remaining provisions of this paragraph 13 subject always to: the Supplier's request being submitted in writing at least three (3) Months before the effective date for the proposed variation ("Adjustment Date"); the cap on any increase in the Framework Prices; and the agreement of the Authority. The earliest Adjustment Date for any increase in the Framework Prices in accordance with this paragraph 13 will be the first (1) Working Day following the Initial Period. Thereafter any subsequent increase to any of the Framework Prices in accordance with this paragraph 13 shall not occur before the anniversary of the previous Adjustment Date. To make a request for a variation of some or all of the Framework Prices in accordance with this paragraph 13, the Supplier shall provide the Authority with:
REVIEW OF THE FRAMEWORK PRICES. Subject to paragraphs 4.1.1 and 4.1.2 above, the Framework Prices will remain fixed for one