Examples of Substantial Completion Guaranteed Date in a sentence
The CPM Schedule shall represent Contractor's best judgment as to how it shall complete the Work in compliance with the Schedule Milestones including the Phase Substantial Completion Guaranteed Dates, the PV Power Plant Substantial Completion Guaranteed Date, and the Final Completion Guaranteed Date.
If the Project fails to achieve the Substantial Completion Date on or prior to close of business on the Substantial Completion Guaranteed Date, then Developer shall pay to PacifiCorp liquidated damages for each day until the Project achieves the Substantial Completion Date, in an amount equal to [ ($ )] per day for the first thirty-one (31) days following the Substantial Completion Guaranteed Date and [ (collectively, the “Delay Liquidated Damages”).
Contractor shall cause Substantial Completion to occur on or before the Substantial Completion Guaranteed Date (as such dates may be extended pursuant to this Contract, including Articles XXIII, XVII, XXII, Section 25.01, Section 36.01 or any other provision hereof).
Subject to Contractor’s obligation to pay Delay Liquidated Damages to the extent set forth herein, Contractor shall have the period (the “Performance Testing Period”) through and including the ninetieth (90th) day following the Substantial Completion Guaranteed Date during which Contractor shall run, and, if necessary, re-run each of the Performance Tests necessary to demonstrate compliance with Performance Guarantees.
A student and faculty centered information processing and dissemination can enhance speedy decision making, provide easy access and ensure transparency and accountability of various actions taken.
Contractor shall cause Substantial Completion of each Unit to occur on or before the applicable Substantial Completion Guaranteed Date.
If Retainage is not released upon Substantial Completion of a Unit due to Contractor being in default under the terms of this Agreement, Owner shall release such fifty percent (50%) Retainage related to the first Unit within ten (10) days after Contractor reasonably demonstrates that such default has been cured; provided that Contractor is on schedule to achieve Substantial Completion by the Substantial Completion Guaranteed Date for the remaining Unit.
The frequency of such meetings shall be established and modified, from time to time, by mutual agreement of the Parties; provided, however, such meetings shall occur no less frequently than monthly; provided, further, if the Milestone Summary Schedule indicates that Substantial Completion is scheduled to occur thirty (30) days or more after the Substantial Completion Guaranteed Date, Owner shall be entitled to require that meetings occur as frequently as weekly.
Without limiting the foregoing, Contractor shall, subject to the terms and conditions of this Agreement, including Section 15.1, perform the Work so as to achieve Substantial Completion of each Unit by such Unit’s Substantial Completion Guaranteed Date.
If an event described in Section 16.1(g) occurs, the Project Schedule (and the Substantial Completion Guaranteed Date referenced therein for Unix 0 xx Unit 2, as applicable) shall be equitably extended as necessary for the repair of such welds and as set forth in a Change In Work Form accepted by Owner; provided that Contractor uses all reasonable efforts to mitigate the duration of any delay in achieving the Substantial Completion Guaranteed Date.