Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).
Work Orders If the Contract is for indefinite quantities of Services, as specified in the Signature Document, all Work will be performed in accordance with properly executed Work Orders.
Stop Work Orders A. The JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Services for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the parties may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Services covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Services covered by the Stop Work Order as provided for in this Agreement. B. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of Services. The JBE shall make an equitable adjustment in the delivery schedule, the Contract Amount, or both, and the Agreement shall be modified, in writing, accordingly, if: i. The Stop Work Order results in an increase in the time required for, or in Contractor’s cost properly allocable to the performance of any part of this Agreement; and ii. Contractor requests an equitable adjustment within thirty (30) days after the end of the period of stoppage; however, if the JBE decides the facts justify the action, the JBE may receive and act upon a proposal submitted at any time before final payment under this Agreement. C. The JBE shall not be liable to Contractor for loss of profits because of a Stop Work Order issued under this provision.
Work Order (s) means a detailed scope of work for a Service required by Transnet, including timeframes, Deliverable, Fees and costs for the supply of the Service to Transnet, which may be appended to this Agreement from time to time.
Task Orders A. Some tasks and Services will be assigned to the Consultant through issuance of Task Orders. After the tasks and Services are identified and communicated to the Consultant by Valley Water Project Manager, Consultant will prepare a proposed Task Order (see Standard Consultant Agreement, Appendix Three Task Order Template). The proposed Task must identify the following: 1) Description of the services, including deliverables; 2) The total Not-to-Exceed Fees for Consultant to complete the services, including estimated number of hours per assigned staff to complete the services; 3) Proposed staff that will be assigned to complete the services, including resumes if not previously provided to Valley Water’s Project Manager; 4) Estimated cost of each other direct cost and reimbursable expense, including any applicable fees; 5) Schedule for completing the services; and 6) Copies of applicable state and federal permits required to complete the services, unless previously provided to Valley Water. B. Consultant agrees that the Not-to-Exceed Fees specified in a proposed Task Order will be the product of a good faith effort in exercising its professional judgment. After an agreement has been reached on the negotiable items, the finalized Task Order will be signed by both Valley Water’s authorized representative referenced in the Standard Consultant Agreement, Appendix One Additional Legal Terms (Appendix One), and Consultant’s authorized representative. C. Consultant must not commence performance of work or services on a Task Order until it has been approved by Valley Water’s authorized representative and Notice to Proceed has been issued by Valley Water Project Manager. No payment will be made for any services performed prior to approval or after the period of performance of the Task Order. The period of performance for Task Orders will be in accordance with dates specified in the Task Order. No Task Order will be written which extends beyond the expiration date of this Agreement. The total amount payable by Valley Water for an individual Task Order will not exceed the amount agreed to in the Task Order.
Change Orders and Contract Amendments 33.1 The Procuring Entity may at any time order the Supplier through notice in accordance GCC Clause 8, to make changes within the general scope of the Contract in any one or more of the following: a) drawings, designs, or specifications, where Goods to be furnished under the Contract are to be specifically manufactured for the Procuring Entity; b) the method of shipment or packing; c) the place of delivery; and d) the Related Services to be provided by the Supplier. 33.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Supplier's performance of any provisions under the Contract, an equitable adjustment shall be made in the Contract Price or in the Delivery/Completion Schedule, or both, and the Contract shall accordingly be amended. Any claims by the Supplier for adjustment under this Clause must be asserted within twenty-eight (28) days from the date of the Supplier's receipt of the Procuring Entity's change order. 33.3 Prices to be charged by the Supplier for any Related Services that might be needed but which were not included in the Contract shall be agreed upon in advance by the parties and shall not exceed the prevailing rates charged to other parties by the Supplier for similar services.
CHANGE ORDERS AND AMENDMENTS A. Any alterations, additions, or deletions to the terms of this Agreement, which are required by changes in federal or state law or by regulations, are automatically incorporated without written amendment hereto, and shall become effective on the date designated by such law or by regulation. B. To ensure the legal and effective performance of this Agreement, both parties agree that any amendment that affects the performance under this Agreement must be mutually agreed upon and that all such amendments must be in writing. After a period of no less than 30 days subsequent to written notice, unless sooner implementation is required by law, such amendments shall have the effect of qualifying the terms of this Agreement and shall be binding upon the parties as if written herein. C. Customers have the right to issue a change order to any purchase orders issued to the Contractor for the purposes of clarification or inclusion of additional specifications, qualifications, conditions, etc. The change order must be in writing and agreed upon by Contractor and the Customer agency prior to issuance of any Change Order. A copy of the Change Order must be provided by the Contractor to, and acknowledged by, H-GAC.
Stop Work Order (a) NYSERDA may at any time, by written Order to the Contractor, require the Contractor to stop all or any part of the Work called for by this Agreement for a period of up to ninety (90) days after the Stop Work Order is delivered to the Contractor, and for any further period to which the parties may agree. Any such order shall be specifically identified as a Stop Work Order issued pursuant to this Section. Upon receipt of such an Order, the Contractor shall forthwith comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Order during the period of work stoppage consistent with public health and safety. Within a period of ninety (90) days after a Stop Work Order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, NYSERDA shall either: (i) by written notice to the Contractor, cancel the Stop Work Order, which shall be effective as provided in such cancellation notice, or if not specified therein, upon receipt by the Contractor, or (ii) terminate the Work covered by such order as provided in the Termination Section of this Agreement. (b) If a Stop Work Order issued under this Section is cancelled or the period of the Order or any extension thereof expires, the Contractor shall resume Work. An equitable adjustment shall be made in the delivery schedule, the estimated cost, the fee, if any, or a combination thereof, and in any other provisions of the Agreement that may be affected, and the Agreement shall be modified in writing accordingly, if: (i) the Stop Work Order results in an increase in the time required for, or in the Contractor’s cost properly allocable to, the performance of any part of this Agreement, and (ii) the Contractor asserts a claim for such adjustments within 30 days after the end of the period of Work stoppage; provided that, if NYSERDA decides the facts justify such action, NYSERDA may receive and act upon any such claim asserted at any time prior to final payment under this Agreement. (c) If a Stop Work Order is not cancelled and the Work covered by such Order is terminated, the reasonable costs resulting from the Stop Work Order shall be allowed by equitable adjustment or otherwise. (d) Notwithstanding the provisions of this Section 12.01, the maximum amount payable by NYSERDA to the Contractor pursuant to this Section 12.01 shall not be increased or deemed to be increased except by specific written amendment hereto.
Scope of Works (a) Users with an appropriate licence type may be able to create and access Scope of Works. (b) The parties acknowledge and agree that: (i) any wording contained in a Scope of Works is established by the Customer, is customisable and within the Customer's absolute control; (ii) Users make decisions within ProcurePro on how to draft Scope of Works and ProcurePro is not responsible for those decisions; (iii) the Supplier is not liable for the Customer's use or reliance upon any Scope of Works; and (iv) the Supplier is not responsible for controlling the use, copying, modification or export of a Scope of Works by any User to which the Customer allows access to that Scope of Works.
PURCHASE ORDERS AND INVOICING All invoices shall at a minimum, include the items listed below and any additional information identified in the Authorized User RFQ and resulting Authorized User Agreement: Contract Number; Contractor/Reseller Name; NYS Vendor ID; Manufacturer Part Number (SKU); Product Name; Product Description; Quantity; NYS Net Price for each Product; Specific designation of special price(s) which may be better than the NYS Net Contract Price; and Invoice Total.