Commencement; Critical Path Sample Clauses

Commencement; Critical Path. Within five (5) working days after the later to occur of the issuance of all permits necessary to commence the Work and Contractor’s receipt of a Notice to Proceed issued by Owner, Contractor shall commence performance of the Work and thereafter continuously and diligently proceed with the performance of the Work, in accordance with the Construction Schedule, to completion. Contractor shall be responsible for the Construction Schedule and meet all critical path dates, including but not limited to, any milestone dates contained in the Construction Schedule, subject only to extension for Excused Delays in accordance with Section 4.2. Should Contractor fail to meet any of the critical path dates, including but not limited to any milestone dates identified in the Construction Schedule, upon written notice from Owner, Contractor shall cause its employees, Subcontractors and other parties performing the Work, to perform and work at hours and days, in addition to the normal working hours and days, whatever overtime work is necessary to meet the Construction Schedule. No adjustment will be made to the Contract Sum for additional compensation paid to Contractor’s employees and Subcontractors for overtime or shift work due to Contractor’s failure to meet any of the critical path dates, unless such failure is due to an Excused Delay, in which case any additional compensation to Contractor shall be determined by Change Order in accordance with Article 5. If Contractor shall fail to expedite Work upon demand by Owner in accordance with the foregoing sufficient to eliminate the effect of any critical path delays on the Construction Schedule, Contractor shall be deemed in default hereunder, and in such event, without limitation of any other right or remedy of Owner, Owner shall have the right to terminate this Agreement as provided in Section 15.2 and Owner shall also have the right to expedite such Work and charge such costs to Contractor to the extent such costs, together with all other costs of completing the Work, exceed the Contract Sum.
AutoNDA by SimpleDocs

Related to Commencement; Critical Path

  • Pre-Commencement Phase Services The services required to be provided by the Contractor for the Pre- Commencement Phase of the Project in accordance with the Contract Documents.

  • Project Commencement The Grantee shall begin the grant-funded project <<on or before insert date>> <<within 90 days of the original start date of the grant term or grant execution date, whichever is later,>>, unless otherwise approved by System Agency. If project commencement is delayed, the Grantee must submit in writing to the assigned contract manager, the steps taken to initiate the project, the reasons for the delay, and the expected start date. System Agency may require Grantee to take immediate remedial or corrective action in response to any delay.

  • Service Commencement Date The date the Transmission Provider begins to provide service pursuant to the terms of an executed Service Agreement, or the date the Transmission Provider begins to provide service in accordance with Section 15.3 or Section 29.1 under the Tariff.

  • Commencement of Work Engineer shall not commence any field work under this Contract until he/she/it has obtained all required insurance and such insurance has been approved by County. As further set out below, Engineer shall not allow any subcontractor/subconsultant(s) to commence work to be performed in connection with this Contract until all required insurance has been obtained and approved and such approval shall not be unreasonably withheld. Approval of the insurance by County shall not relieve or decrease the liability of Engineer hereunder.

  • Post-Commercial Operation Date Testing and Modifications Each Party shall at its own expense perform routine inspection and testing of its facilities and equipment in accordance with Good Utility Practice as may be necessary to ensure the continued interconnection of the Large Generating Facility with the Participating TO’s Transmission System in a safe and reliable manner. Each Party shall have the right, upon advance written notice, to require reasonable additional testing of the other Party’s facilities, at the requesting Party’s expense, as may be in accordance with Good Utility Practice.

  • Construction Commencement The Connecting Transmission Owner shall commence construction of the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades for which it is responsible as soon as practicable after the following additional conditions are satisfied:

  • Service Commencement 3.1 The Engineer may reuse an existing socket and line routing to fulfil your order; if this occurs your appointment will be cancelled and no engineer will attend site. If you want to force an engineer to attend site, then you are required to tick the box on the order form (up to 2 hours of Time Related Charges may apply in addition to the activation fee):

  • Commencement and Completion of Work Upon the Effective Date of the Contract, bidder agrees to commence all Preconstruction Activities. Upon issuance of a Proceed Order, bidder agrees to commence physical activities on the Site with adequate forces and equipment and to complete to Material Completion all work in 90 consecutive calendar days beginning the day after the date of the Proceed Order. Bid Bond. Enclosed herewith is a Bid Bond (NO OTHER FORM ACCEPTABLE) in the amount of Dollars ($ ) (being not less than five percent of the Bid). Bidder agrees that the above stated amount is the proper measure of liquidated damages that the Owner will sustain by bidder’s failure to execute the Contract or to furnish the Performance and Payment Bonds should bidder’s bid be accepted. Obligation of Bid Bond. If this bid is accepted within thirty-five days after the date set for the opening of bids and bidder fails to execute the Contract within ten days after Notice of Successful Bid, or if bidder fails to furnish both Performance and Payment Bonds, the obligation of the Bid Bond will remain in full force and effect and the money payable thereon shall be paid into the funds of the Owner as liquidated damages for such failure; otherwise, the obligations of the Bid Bond will be null and void. Bidder Certification Certification under Oath. Under oath I certify that I am a principal or other representative of the bidder, and that I am authorized by it to execute the foregoing bid on its behalf; and further, that I am a principal person of the bidder with management responsibility for the construction for the bidder, and as such I am personally knowledgeable of all its pertinent matters. I further certify that this bid is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a bid for the same services, materials, labor, supplies, or equipment and is in all respects fair and without collusion or fraud. Bidder and its principals understand that collusive bidding is a violation of state and federal law and can result in fines, prison sentences, and civil damage awards. Bidder agrees to abide by all conditions of this bid. BY: Authorized Signature (BLUE INK) Printed Name Title Sworn to and subscribed before me this Day of , 20 . Notary Public My commission expires:

  • Commencement and Completion The Work shall commence on _______________, 20__ and shall be complete in accordance with this Agreement without delay on ______________, 20__. The term “day”, used throughout this Agreement, refers to calendar days. Contractor shall not be entitled to any additional compensation for any Permitted Delays. If this Agreement is not signed and returned to the Owner before any work commences, this Agreement will be considered as accepted as presented to the Contractor.

  • PRE-COMMENCEMENT PHASE Part 1 - Pre-commencement Phase Services Part 2 - Construction Documents and Site Plan SECTION 3 – CONSTRUCTION PHASE Part 1 - Construction Phase Services Part 2 - Changes to the Work Part 3 - Time. Part 4 - Correcting the Work, Inspections, Covering and Uncovering Work Part 5 - Subcontractors, Trade Contractors, and Suppliers

Time is Money Join Law Insider Premium to draft better contracts faster.