Substantial Completion and Final Completion Sample Clauses

Substantial Completion and Final Completion. Upon request of the Contractor, CM will, in conjunction with the District Representative, Project Inspector and the Architect determine that Substantial Completion and Final Completion have been achieved. Upon determining that Substantial Completion/Final Completion has been achieved, the CM shall issue Certificates of Substantial Completion and Final Completion, as applicable.
AutoNDA by SimpleDocs
Substantial Completion and Final Completion. A. Substantial Completion of the entire Work shall be achieved within TBD calendar days after the start of Phase 2. B. Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 1.2.L of the General Conditions. C. All of the dates set forth in this Article 11 (collectively the “Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions.
Substantial Completion and Final Completion. The Contractor shall achieve Substantial Completion (as defined in the General Conditions) of the Work, as further provided in Paragraph 8.6 of the General Conditions and other applicable provisions of the Contract Documents, no later than the permitted calendar days set forth in Exhibit SCH, and after the Airport Authority’s issuance of any Notice To Proceed (the “Substantial Completion Date”), subject to adjustments in the Construction Duration, if any, approved by the Airport Authority in accordance with the Contract Documents. In addition, the Contractor shall perform the Work in accordance with all schedule requirements set forth in Exhibit SCH, including without limitation any specified milestone dates or dates for Substantial Completion or Final Completion of phases or portions of the Work, and any special requirements for achieving Substantial Completion set forth therein. As used in the Contract Documents, the terms “Substantial Completion” and “Substantial Completion Date” shall be deemed to refer to Substantial Completion of, or the Substantial Completion Date for, the entire Work and any phase or portion of the Work for which a Substantial Completion date is stated above or in Exhibit SCH, severally or collectively as the context may require. The period of time from the effective date of the Notice to Proceed given to the Contractor in accordance with the Contract Documents to the Substantial Completion Date, for the entire Work or a designated phase or portion thereof, as applicable, together with any valid extensions thereof approved by the Airport Authority in accordance with the Contract Documents, is referred to in the Contract Documents as the “Construction Duration.” If more than one Notice to Proceed is given to the Contractor, the Construction Duration shall commence with the first Notice to Proceed issued, unless otherwise specified in such notice. The Contractor shall achieve Final Completion of the Work, as defined in Paragraph 8.7 of the General Conditions and other provisions of the Contract Documents, no later than ninety (90) days after Substantial Completion of the Work.
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than (DATE) (“Scheduled Substantial Completion Date”) unless otherwise stated in the GMP Exhibit. 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work (“Scheduled Interim Milestone Dates”) shall be achieved as follows unless otherwise stated in the GMP Exhibit: 5.2.3 For a minimum of ninety (90) calendar days after Substantial Completion or until Final Completion is achieved, whichever is later, provide adequate qualified on-site staff that is authorized to act on behalf of the Design-Builder to coordinate and insure that any outstanding work items, Punch Lists, testing and commissioning are completed, at no additional cost to the Owner. 5.2.4 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable and within 45 Working days of Substantial Completion, unless otherwise agreed by the PMT. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 6.5 of the General Conditions. 5.2.5 All of the dates set forth in this Article 5 (collectively the “Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions.
Substantial Completion and Final Completion. The CONSULTANT, based upon one or more inspections of the Project, shall determine and recommend in writing to the CITY the date of Substantial Completion of the Project and the date of Final Completion of the Project. The CONSULTANT shall insure all contractual requirements for substantial completion are met prior to issuing the recommendation to the CITY. When appropriate, the CONSULTANT shall issue a recommendation for Approval for final Payment. The CONSULTANT shall also receive, review for adequacy, compile in an organized, bound, and neat format, and forward to the CITY any and all written warranties, guarantees, bonds, certificates of inspection, tests, required approvals, operation manuals, maintenance manuals, and any other related documents required by the Contract for Construction prior to issuing a recommendation for substantial completion;
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than (DATE) (“Scheduled Substantial Completion Date”) unless otherwise stated in the GMP Exhibit. 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work (“Scheduled Interim Milestone Dates”) shall be achieved as follows unless otherwise stated in the GMP Exhibit: 5.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable and within 45 Working days of Substantial Completion, unless otherwise agreed by the PMT. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 6.5 of the General Conditions. 5.2.4 All of the dates set forth in this Article 5 (collectively the “Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions.
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than four hundred eighty-five (485) calendar days after the Date of Commencement. However, any delays caused by the modification of Owner’s construction air emission permit as referenced in Section 11, are hereby specifically excluded from the 485 calendar days specified in this section. 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work shall be achieved as described in Exhibit F. The Scheduled Substantial Completion date will likewise be extended a corresponding amount of days for each day Owner exceeds the deliverable timeframes referred to in Exhibit F. 5.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable, but not later than sixty (60) days following issuance of the Certificate of Substantial Completion. 5.2.4 All of the dates set forth in this Article 5 (“Contract Time(s)”) shall be subject to adjustment in accordance with the General Conditions of Contract. Specifically, if delays in the Contract Time occur because of delay in the delivery of materials or equipment that is beyond the control of Design-Builder, the Contract Time will be adjusted, without penalty to Design-Builder, pursuant to Sections 8.2.1 and 8.2.2 of the General Conditions of Contract.
AutoNDA by SimpleDocs
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than Month, Day, Year (“Scheduled Substantial Completion Date”). 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work (“Scheduled Interim Milestone Dates”) shall be achieved as follows: 5.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in the Interim General Conditions and Supplemental Conditions. 5.2.4 All of the dates set forth in this Article 5 (collectively the “Contract Time(s)”) shall be subject to adjustment in accordance with the Interim General Conditions and the Supplemental Conditions.
Substantial Completion and Final Completion. 2.29.1. (i) Substantial Completion is expected to occur not later than the Date Certain, (ii) Final Completion is expected to occur not later than the date that is six (6) months after the Date Certain, and each of the foregoing representations is based on factual evidence and reasonable assumptions at the time such representation is given and (iii) the Vitol S&O Agreement Start US-DOCS\150507763.9 Bakersfield Refinery – Senior Credit Agreement |US-DOCS\150507763.15|| Date is reasonably expected to occur not later than the Start Date Deadline (as defined in the Vitol S&O Agreement). 2.29.2. On each Funding Date that occurs after the Thirteenth Amendment Effective Date and after giving effect to the funding of the Tranche D Loans, but, in each case, prior to the Final Completion Date, the sum of (i) the amounts on deposit in the Collateral Accounts, plus (ii) Project Revenues reasonably anticipated to be received by the Project Company prior to Final Completion (up to a cap, in the case of this clause (ii) of the Cash Flow Utilization Cap, if applicable) plus (iii) the proceeds of any Permitted Working Capital Facility plus (iv) the amount of any unfunded Commitments is expected to be sufficient to cause the Project to achieve Substantial Completion and Final Completion.
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than Four hundred eight five (485) calendar days after December 2, 2001. 5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work shall be achieved as follows: N/A 5.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable. 5.2.4 All of the dates set forth in this Article 5 ("Contract Time(s)") shall be subject to adjustment in accordance with the General Conditions of Contract.