Substantial Completion and Final Completion Sample Clauses

Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than (DATE) (“Scheduled Substantial Completion Date”) unless otherwise stated in the GMP Exhibit.
AutoNDA by SimpleDocs
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than [*] calendar days after the Date of Commencement.
Substantial Completion and Final Completion. Upon request of the Contractor, CM will, in conjunction with the District Representative, Project Inspector and the Architect determine that Substantial Completion and Final Completion have been achieved. Upon determining that Substantial Completion/Final Completion has been achieved, the CM shall issue Certificates of Substantial Completion and Final Completion, as applicable.
Substantial Completion and Final Completion. A. Substantial Completion of the entire Work shall be achieved within TBD calendar days after the start of Phase 2.
Substantial Completion and Final Completion. The Contractor shall achieve Substantial Completion (as defined in the General Conditions) of the Work, as further provided in Paragraph 8.6 of the General Conditions and other applicable provisions of the Contract Documents, no later than the permitted calendar days set forth in Exhibit SCH, and after the Airport Authority’s issuance of any Notice To Proceed (the “Substantial Completion Date”), subject to adjustments in the Construction Duration, if any, approved by the Airport Authority in accordance with the Contract Documents. In addition, the Contractor shall perform the Work in accordance with all schedule requirements set forth in Exhibit SCH, including without limitation any specified milestone dates or dates for Substantial Completion or Final Completion of phases or portions of the Work, and any special requirements for achieving Substantial Completion set forth therein. As used in the Contract Documents, the terms “Substantial Completion” and “Substantial Completion Date” shall be deemed to refer to Substantial Completion of, or the Substantial Completion Date for, the entire Work and any phase or portion of the Work for which a Substantial Completion date is stated above or in Exhibit SCH, severally or collectively as the context may require. The period of time from the effective date of the Notice to Proceed given to the Contractor in accordance with the Contract Documents to the Substantial Completion Date, for the entire Work or a designated phase or portion thereof, as applicable, together with any valid extensions thereof approved by the Airport Authority in accordance with the Contract Documents, is referred to in the Contract Documents as the “Construction Duration.” If more than one Notice to Proceed is given to the Contractor, the Construction Duration shall commence with the first Notice to Proceed issued, unless otherwise specified in such notice. The Contractor shall achieve Final Completion of the Work, as defined in Paragraph 8.7 of the General Conditions and other provisions of the Contract Documents, no later than ninety (90) days after Substantial Completion of the Work.
Substantial Completion and Final Completion. The CONSULTANT, based upon one or more inspections of the Project, shall determine and recommend in writing to the CITY the date of Substantial Completion of the Project and the date of Final Completion of the Project. The CONSULTANT shall insure all contractual requirements for substantial completion are met prior to issuing the recommendation to the CITY. When appropriate, the CONSULTANT shall issue a recommendation for Approval for final Payment. The CONSULTANT shall also receive, review for adequacy, compile in an organized, bound, and neat format, and forward to the CITY any and all written warranties, guarantees, bonds, certificates of inspection, tests, required approvals, operation manuals, maintenance manuals, and any other related documents required by the Contract for Construction prior to issuing a recommendation for substantial completion;
Substantial Completion and Final Completion. 2.29.1. (i) Substantial Completion is expected to occur not later than the Date Certain, (ii) Final Completion is expected to occur not later than the date that is six (6) months after the Date Certain, and each of the foregoing representations is based on factual evidence and reasonable assumptions at the time such representation is given and (iii) the Vitol S&O Agreement Start US-DOCS\150507763.9 Bakersfield Refinery – Senior Credit Agreement |US-DOCS\150507763.15|| Date is reasonably expected to occur not later than the Start Date Deadline (as defined in the Vitol S&O Agreement).
AutoNDA by SimpleDocs
Substantial Completion and Final Completion. 5.2.1 Substantial Completion of the entire Work shall be achieved no later than Four hundred eight five (485) calendar days after December 2, 2001.
Substantial Completion and Final Completion. So long as Xxxxxx Mechanical receives a Notice to Proceed not later than ten (10) days after November 1, 2006, Substantial Completion shall be achieved not later than April 1, 2008. Final Completion of the Work shall be achieved as expeditiously as reasonably practicable, but in no event, will Final Completion of the Work be completed later than June 1, 2008.
Substantial Completion and Final Completion. Substantial Completion and Final Completion are defined in the General Conditions of Contract, Section 6.6.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!