Dates for Substantial Completion and Final Payment Sample Clauses

Dates for Substantial Completion and Final Payment. A. The Work will be substantially completed within 90 calendar days of issuance of Notice to Proceed, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within 30 calendar days of issuance of Certificate of Substantial Completion.
Dates for Substantial Completion and Final Payment. A. The Work will be substantially completed on or before January 15, 2012, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions on or before January 31, 2012.
Dates for Substantial Completion and Final PaymentThe work will be totally complete and ready for final payment on or before August 8, 2020.
Dates for Substantial Completion and Final Payment. A. The Work will be substantially completed on or before November 15, 2023 and completed and ready for final payment in accordance with the timing as indicated in the Contract Documents B. The entity responsible for scheduling of the Work shall make every effort to provide sufficient time prior to the established date of substantial completion to complete the Work. Reasonable extensions of time will be granted should scheduling of the Work not comply with the Substantial Completion date.
Dates for Substantial Completion and Final Payment. A. The Work will be Substantially Completed on or before December 31, 1998, and completed and ready for final payment in accordance with the GENERAL CONDITIONS on or before January 31, 1999. 1. Areas to be Substantially Complete prior to date stated above are as follows: Switchgear Foundation Installation B May 22, 1998
Dates for Substantial Completion and Final Payment. A. Bidder agrees that the Work associated with the “Civil and Site Work Grading Detail Design Package” and “Temporary Access Road” will be substantially complete on or before August 14, 2006 and ready for partial utilization in accordance with paragraph 14.05 of the General Conditions. Bidder further aggress that all work associated with the project will be completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions on or before October 16, 2006. Adopted from EJCDC Standard Form Of Agreement between Owner and Contractor 0500-1
Dates for Substantial Completion and Final PaymentSubstantial completion shall be achieved by November 15, 2017 Substantial completion shall be defined as the time when the work has progressed to where it is sufficiently complete and the remaining work will not interfere with the work area's intended use. Substantial completion requires, at a minimum, completion of all asphalt pavement.
Dates for Substantial Completion and Final Payment. A. Exterior masonry, mechanical enclosure and exterior painting will commence as soon as contract is full executed after the August 18,
Dates for Substantial Completion and Final Payment. A. The Work will be Substantially Completed within 330 calendar days after the date when the Contract Times commence to run as provided in the GENERAL CONDITIONS, and completed and ready for final payment in accordance with the GENERAL CONDITIONS within 30 calendar days after the substantial completion date.
Dates for Substantial Completion and Final Payment. A. If awarded the contract, the work will be completed no later than 90 Calendar Days after construction commences, but no later than August 31, 2022.