DRB Meeting Protocol Sample Clauses

DRB Meeting Protocol. 5.2.1 The DRB Chair convenes the first DRB meeting, and the RE, the Contractor and DRB members execute the DRB Third-Party Agreement. The DRB formulates its own rules of operation, consistent with recommended DRBF operation guidelines.
AutoNDA by SimpleDocs

Related to DRB Meeting Protocol

  • Meeting Agenda 6.1 The Co-chairpersons will prepare an agenda and forward a copy of the agenda to all Joint Committee members at least one week in advance of the meeting (sample attached).

  • Meeting of Committee In the event of either party wishing to call a meeting of the Committee, the meeting shall be held at a time and place fixed by mutual agreement, however, such meeting to be held not later than 14 days after request has been received unless varied by mutual agreement.

  • Scoping Meeting 4.2.1 A scoping meeting will be held within ten (10) Business Days after the Interconnection Request is deemed complete, or as otherwise mutually agreed to by the Parties. The Utility and the Interconnection Customer will bring to the meeting personnel, including system engineers and other resources as may be reasonably required to accomplish the purpose of the meeting. The scoping meeting may be omitted by mutual agreement in writing.

  • PRE-BID MEETING 3.1. The contracting Agency/Department will hold a pre-bid meeting at LOCATION on DAY, DATE and TIME

  • Monthly Meetings The Chief Xxxxxxx or Xxxxxxx designated by the Union and the university’s chief human resources officer or designee shall schedule monthly meetings to review pending grievances and contractual issues and to make good faith efforts to resolve such grievances and issues. The Chief Xxxxxxx or Xxxxxxx designated by the Union and the university’s chief human resources officer or designee shall mutually agree on the participation of other Union and Employer representatives at these meetings on a case-by-case basis. Such meetings shall take place during regular working hours. Bargaining unit employees authorized to attend these meetings shall be considered to be on work time.

  • Meeting Frequency SICM shall be held monthly unless otherwise agreed upon by all Parties. Meeting dates shall be determined by NCDEQ after consultation with the Parties. The meeting shall consist of updates and other pertinent information provided by each Party.

  • Final Meeting The goal of this subtask is to complete the closeout of this Agreement. The Recipient shall: • Meet with Energy Commission staff to present project findings, conclusions, and recommendations. The final meeting must be completed during the closeout of this Agreement. This meeting will be attended by the Recipient and CAM, at a minimum. The meeting may occur in person or by electronic conferencing (e.g., WebEx), with approval of the CAM. The technical and administrative aspects of Agreement closeout will be discussed at the meeting, which may be divided into two separate meetings at the CAM’s discretion. o The technical portion of the meeting will involve the presentation of findings, conclusions, and recommended next steps (if any) for the Agreement. The CAM will determine the appropriate meeting participants. o The administrative portion of the meeting will involve a discussion with the CAM and the CAO of the following Agreement closeout items:  Disposition of any state-owned equipment.  Need to file a Uniform Commercial Code Financing Statement (Form UCC-1) regarding the Energy Commission’s interest in patented technology.  The Energy Commission’s request for specific “generated” data (not already provided in Agreement products).  Need to document the Recipient’s disclosure of “subject inventions” developed under the Agreement.  “Surviving” Agreement provisions such as repayment provisions and confidential products.  Final invoicing and release of retention. • Prepare a Final Meeting Agreement Summary that documents any agreement made between the Recipient and Commission staff during the meeting.

  • Safety Meetings (iii) Accident investigation.

  • Progress Meetings The Engineer shall from time to time during the progress of the work confer with the State. The Engineer shall prepare and present such information as may be pertinent and necessary or as may be requested by the State in order to evaluate features of the work.

  • Project Kick-off Meeting The Contractor shall hold a project kick-off meeting within thirty days from the contract execution date. The Contractor shall coordinate with NYSERDA's Project Manager to arrange the meeting at a mutually convenient time and place. The Contractor is encouraged to invite representatives of sub-contractors and equipment vendors. The purpose of this meeting shall be to finalize the strategies for accomplishing the objectives of this work. In a timely manner, the Contractor shall submit to NYSERDA’s Project Manager a brief report summarizing the issues discussed and decisions made, if any, during this meeting. Deliverable: A brief report regarding the project kickoff meeting.