LINE ITEM ADJUSTMENTS. Upon written request by the Recipient, the Division may adjust the line items of the Summary Project Cost Table at the time of Division’s Final Budget Approval. Upon written request by the Recipient, the Division may also adjust the line items of the Summary Project Cost Table as well as the detailed budget at the time of Recipient’s submittal of its final claim. Any line item adjustments to the Summary Project Cost Table that are due to a change in scope of work will require an Agreement amendment. The sum of adjusted line items in both the Summary Project Cost Table and the detailed budget must not exceed the Project Funding Amount. The Division may also propose budget adjustments. Under no circumstances may the sum of line items in the budget approved through the Final Budget Approval process exceed the Project Funding Amount. Any increase in the Project Funding Amount will require an Agreement amendment.
LINE ITEM ADJUSTMENTS. 1. The Recipient may submit a request for an adjustment between line items of the budget in writing to the Project Manager for the Division’s review and approval. Such adjustment may not increase or decrease the total Project Funding Amount. The Recipient shall submit a copy of the Agreement budget reflecting the requested changes and shall note proposed changes by striking out the original amount(s) followed with proposed change(s) in bold and underlined. Budget adjustments deleting a budget line item or adding a new budget line item shall require a formal amendment. The Division may also propose budget adjustments.
2. The Division may adjust the funding amounts of the line items of the budget as follows, in accordance with any applicable rules. Under no circumstances may the sum of line items in the approved budget exceed the Project Funding Amount set forth on the Cover Page of this Agreement.
(a) The Division may adjust the budget for existing line items, other than the Contingency and Conditional Costs line items, by shifting funds from one line item to another. The sum of all line item adjustments approved by the Division for this Agreement must not exceed fifteen percent (15%) of the total Project Funding Amount. If the Division modifies the budget (i) at the time of the Division’s Final Budget Approval(s), (ii) by amending the Agreement, or (iii) following the Recipient’s submittal of its final Reimbursement Request, then any adjustments that were made prior to such modification of the budget shall not be counted in the calculation of the 15% limit.
(b) At the time of the Division’s Final Budget Approval(s) and/or any amendments to the Agreement, the Division may adjust the amounts allocated to the line items of the budget at its discretion. Any adjustments at these times are not subject to the 15% limit in paragraph a.
(c) Following the Recipient’s submittal of its final Reimbursement Request, the Division may adjust the amounts allocated to the line items of the budget at its discretion. Any adjustments at this time are not subject to the 15% limit in paragraph a.
3. No line item adjustment is authorized until the Division provides written approval for the adjustment to the Recipient. Any line item adjustments to the budget that are due to a change in scope of work will require an Agreement amendment.
LINE ITEM ADJUSTMENTS. (a) Subject to the prior review and approval of the Project Manager and Technical Lead, adjustments between existing line items may be used to defray allowable direct costs up to fifteen percent (15%) of the total Project Funding Amount, including any amendment(s) thereto. Line Item adjustments approved by the Project Manager and Technical Lead must be de minimis, less than fifteen percent (15%) of the total Project Funding Amount, and may not include any changes to the Scope of Work. Line item adjustments in excess of fifteen percent (15%) or line item adjustments that result in a change to the scope of work will require an Agreement amendment. If the detailed budget includes an amount for the Recipient’s personnel costs, that amount is based on the hours, classifications, and rates submitted by the Recipient in its application. Any changes to the hours, classifications, and rates must be approved, in advance and in writing, by the Project Manager and Technical Lead.
(b) The Recipient may submit a request for an adjustment in writing to the Project Manager and Technical Lead. Such adjustments may not increase or decrease the total funding amount. The Recipient shall submit a copy of the original Agreement budget reflecting the requested changes and shall note proposed changes by striking out the original amount(s) followed with proposed change(s) in bold and underlined. Budget adjustments deleting a budget line item or adding a new budget line item shall require a formal amendment. The Division may also propose budget adjustments.
(c) The sum of adjusted line items shall not exceed the total budget amount.
LINE ITEM ADJUSTMENTS. Adjustments may be made between line items, as approved by the Project Manager, [non-DAC] at the time of Recipient’s submittal of its final Reimbursement Request. The sum of adjusted line items must not exceed the Project Funding Amount.
LINE ITEM ADJUSTMENTS. Adjustments may be made between line items, as approved by the Project Manager, at the time of Recipient’s submittal of its final Reimbursement Request. The sum of adjusted line items must not exceed the Project Funding Amount.
LINE ITEM ADJUSTMENTS. Subject to prior written notice under Paragraph 12, the Department of Health Services Division Director, or designee, may approve Line Item Budget Adjustment Requests and Budget Revision Request to “Exhibit B2” so long as the total contract maximum set forth in Section 2 (Payment) neither increases nor decreases and there is no significant change in the Scope of Work. Proposed transfers between budget sections or between line items require an approved Budget Revision Request if the total of the proposed changes are greater than 10% of the total contract amount for each budget year. Proposed budget transfers that total less than 10% of the total contract amount each budget year require an approved Line Item Budget Adjustment Request.
LINE ITEM ADJUSTMENTS. Upon written request by the Recipient, the Division may adjust the summary budget line items at time of Division’s Final Budget Approval. Upon written request by the Recipient, the Division may also adjust the line items of the summary budget as well as the detailed budget at the time of Recipient’s submittal of its final claim. Any summary budget line item adjustments that are due to a change in scope of work will require an Agreement amendment. The sum of adjusted line items in both the Summary budget and the detailed budget must not exceed the total budget amount. The Division may also propose budget adjustments.
LINE ITEM ADJUSTMENTS. Upon written request by the Recipient, the Division may adjust the line items of the budget at the time of Division’s Final Budget Approval(s). Upon written request by the Recipient, the Division may also adjust the line items of the budget at the time of Recipient’s submittal of its final claim. Any line item adjustments to the budget that are due to a change in scope of work will require an Agreement amendment. The sum of adjusted line items in the budget must not exceed the Project Funding Amount. The Division may also propose budget adjustments. Under no circumstances may the sum of line items in the budget approved through the Final Budget Approval process exceed the Project Funding Amount. Any increase in the Project Funding Amount will require an Agreement amendment.