No Breach or Liability. No delay or failure of a Party to perform any of its obligations, other than payment obligations, under this Agreement due to causes beyond its reasonable control shall constitute a breach of this Agreement or render that Party liable for that delay or failure. Causes beyond a Party's reasonable control include:
(i) events or circumstances that the Party, using its Reasonable Efforts, is unable to prevent or overcome;
(ii) as to Sabre, causes also beyond the reasonable control of the Person to whom or which Sabre has Subcontracted the affected Service or Task in accordance with this Agreement; and
(iii) labor disputes, strikes, or other similar disturbances; acts of God; utilities or communications failures; acts of the public enemy; and riots, insurrections, sabotage, or vandalism.
No Breach or Liability. Each Party shall be excused from performing its respective obligations under this Agreement and shall not be liable in damages or otherwise if and to the extent that it is unable to so perform or is prevented from performing by a Force Majeure Event, provided that the non-performing Party shall:
14.2.1 Give the other Party notice thereof, followed by written notice if the first notice is not written, both notices to be given as promptly as possible after the non-performing Party becomes aware of such Force Majeure Event, describing the particulars of such Force Majeure Event;
14.2.2 Use its reasonable best efforts to remedy its inability to perform as soon as practicable; provided, however, that this Section 14.2.2 shall not require the settlement of any strike, walkout, lockout or other labor dispute on terms which, in the sole judgment of the Party involved in the dispute, are contrary to its interest; provided further, that the settlement of strikes, lockouts or other labor disputes shall be entirely within the discretion of the Party having the difficulty; and
14.2.3 Resume performance of its obligations under this Agreement and give the other Party written notice to that effect, as soon as reasonably practicable following cessation of the Force Majeure Event.
No Breach or Liability. Either Party shall be excused from performance of its obligations hereunder, other than payment obligations that accrued prior to the declaration of the Force Majeure Event, and shall not be construed to be in default in respect of such obligations to the extent that, and for so long as, failure to perform such obligations is due to a Force Majeure Event.
No Breach or Liability. Either Party shall be excused from performance and shall not be construed to be in default in respect of any obligation hereunder for so long as failure to perform such obligation shall be due to a Force Majeure Event.
No Breach or Liability. A Party shall be excused from performing its obligations under this Agreement and shall not be liable in damages or otherwise if and to the extent that it is unable to so perform or are prevented from performing by a Force Majeure Event, provided that such Party shall:
(i) give the other Party notice thereof, followed by written notice if the first notice is not written, as promptly as possible after such Party becomes aware of such Force Majeure Event, describing the particulars of such Force Majeure Event;
(ii) use its reasonable best efforts to remedy its inability to perform as soon as practicable; provided, however, that this Section 12.2 shall not require the settlement of any strike, walkout, lockout or other labor dispute on terms which, in the sole judgment of the Party involved in the dispute, are contrary to its interest; provided further, that the settlement of strikes, lockouts or other labor disputes shall be entirely within the discretion of the Party having the difficulty; and
(iii) when it is able to resume performance of its obligations under this Agreement, give the other Party written notice to that effect.
No Breach or Liability. If a Force Majeure Event occurs, subject to compliance with Section 18.4, the affected Party will be excused from performance of its obligations hereunder, other than payment obligations that accrued prior to the declaration of the Force Majeure Event, and will not be construed to be in default in respect of such obligations to the extent that, and for so long as, failure to perform is due to a Force Majeure Event.
No Breach or Liability. Seller shall be excused from performance and shall not be construed to be in default in respect of any obligation hereunder for so long as failure to perform such obligation shall be due to a Force Majeure Event.
No Breach or Liability. Each Party shall be excused from performing its respective obligations under this Agreement and shall not be liable in damages or otherwise if and to the extent that it is unable to so perform or is prevented from performing by a Force Majeure Event, provided that the non-performing Party shall:
No Breach or Liability. If a Force Majeure Event occurs, subject to compliance with Section 19.4 and Section 19.5, the affected Party will be excused from performance of its obligations hereunder, other than payment obligations that accrued prior to the declaration of the Force Majeure Event, and will not be construed to be in default in respect of such obligations to the extent that, and for so long as, failure to perform is due to a Force Majeure Event. However, the suspension of performance due to a Force Majeure Event shall be of no greater scope and of no longer duration than is required by such Force Majeure Event. Notwithstanding anything herein to the contrary, no Force Majeure Event shall extend this Agreement beyond its stated Term.
No Breach or Liability. 14 15.2 Notice of Excusable Delay or Failure..................................14 15.3 Efforts to Overcome...................................................14 15.4 Extended Delay or Failure.............................................14