Non-Excusable Delays Sample Clauses

Non-Excusable Delays. 9.2.1 If the delivery of an Aircraft is delayed, and such delay does not constitute an Excusable Delay (hereinafter referred to as “Non-Excusable Delays”), by more than [*****] after the Contractual Delivery Date for such Aircraft, Buyer will be entitled to claim from Embraer liquidated damages in the following amounts: [*****] [*****] [*****] [*****] [*****] [*****] Such liquidated damages shall apply for each Day of delay in excess of the above mentioned [*****] up to the date that the Aircraft is available for inspection and acceptance by, and subsequent delivery to Buyer by means of written confirmation of the successful completion of ground and flight tests performed by Embraer, to be provided as per Article 7.1, it being understood that such liquidated damages will not, in any event, exceed [*****] of the Aircraft Basic Price of the delayed Aircraft and that it will only be due and payable by Embraer to Buyer after Buyer pays to Embraer the total Aircraft Purchase Price, in respect of the affected Aircraft. The Parties acknowledge and agree that such liquidated damages are not a penalty, but are a fair and reasonable estimate of Buyer’s potential damages. 9.2.2 Upon the occurrence of any event which constitutes a Non-Excusable Delay in the delivery of an Aircraft, Embraer shall, as soon as practicable, send a written notice to Buyer, within a reasonable period of time, including a description of the delays and an estimate of the effects expected upon the delivery of the Aircraft. [*****] [*****] Confidential material redacted and filed separately with the Securities and Exchange Commission. [*****] 9.2.3 It is agreed between the Parties that if, with respect to a delayed Aircraft, Embraer does not receive a claim for liquidated damages pursuant to Article 9.2.1, from Buyer, within [*****] the Contractual Delivery Date of such Aircraft, Buyer shall be deemed to have fully waived its right to such liquidated damages.
AutoNDA by SimpleDocs
Non-Excusable Delays. THE FOLLOWING IS ADDED: For work performed by Utilities, delays up to 30 percent of the estimated duration specified in 105.07.02 are considered non-excusable. The duration includes both the advance notice and the completion of the work by the Utility. For delays caused by Railroads, delays up to 30 percent of the estimated availability specified in 105.07 are considered non-excusable.
Non-Excusable Delays. 9.2.1 If the delivery of an Aircraft is delayed, and such delay does not constitute an Excusable Delay (hereinafter referred to as “Non-Excusable Delays”), by more than [***] after the Contractual Delivery Date for such Aircraft, Buyer [***] up to the date that the Aircraft is available for inspection and acceptance by, and subsequent delivery to Buyer by means of written confirmation of the successful completion of ground and flight tests performed by Embraer, to be provided as per Article 7.1, [***] Aircraft within such [***] and [***], it being understood that such [***] will not, in any event, [***] and that it will only be due and payable by Embraer to Buyer after Buyer pays to Embraer the total Aircraft Purchase Price, in respect of the affected Aircraft, and as otherwise provided for in Article 20.2(ii). Such payment shall be made [***]. 9.2.1.1 In the event Embraer issues a written Non-Excusable Delay notice to Buyer within at least [***] prior to the Contractual Delivery Date of the affected Aircraft, Embraer shall have a [***], and Buyer [***] up to the date that the affected Aircraft is available for inspection and acceptance by, and subsequent delivery to Buyer by means of written confirmation of the successful completion of ground and flight tests performed by Embraer, to be provided as per Article 7.1 [***] within such [***] and [***], it being understood that such [***] will not, in any event, [***] of such Aircraft and that it will only be due and payable by Embraer to Buyer after Buyer pays to Embraer the total Aircraft Purchase Price, in respect of the affected Aircraft, and as otherwise provide for in Article 20.2(ii). Such payment shall be made within [***] of payment of the total relevant Aircraft Purchase Price. [***]
Non-Excusable Delays. If the Orbital ATK Group fails to timely deliver all or any portion of an order in any circumstance other than would constitute an Excusable Delay (such delay, a “Non-Excusable Delay”), then the Orbital ATK Group shall pay reasonable costs associated with expedited delivery of such Ammunition Products once they become available. In addition, if the Orbital ATK Group’s delivery is, or would reasonably be expected to be, delayed by more than 30 days, then the Vista Outdoor Group may send a notice of default to LLC, demanding that the Orbital ATK Group either cure or provide a plan to cure. If the Orbital ATK Group neither cures nor provides a plan to cure that is reasonably acceptable to the Vista Outdoor Group within 45 days of the original Ammunition Product delivery date, then the Vista Outdoor Group may, upon written notice to the Orbital ATK Group, “cover” and procure such unfulfilled order for Ammunition Products from alternative suppliers (or manufacture such Ammunition Products itself) (and the applicable Binding FY Order or Additional Order shall automatically be deemed modified to remove any Ammunition Products that the Vista Outdoor Group has notified that it will cover, effective upon receipt by the Orbital ATK Group of the applicable notification), and the Orbital ATK Group shall reimburse the Vista Outdoor Group for the reasonable difference between the price of such Ammunition Products under this Agreement and the “cover” price, which may include reasonable expedited shipping and freight costs.
Non-Excusable Delays. Confidential 1. If the delivery of an Aircraft or Spares is delayed, not as a result of an Excusable Delay [*] 2. [*] 3. [*] 4. [*] 5. [*] ---------- * Confidential
Non-Excusable Delays. If a delay does not meet the definition of an Excusable Delay Event (a “NON-EXCUSABLE DELAY”), then CONSULTANT shall not, without the DISTRICT’s prior written consent (which may be withheld), be entitled to an extension of the delivery date for the WORK then due. If the CONSULTANT does not obtain the DISTRICT’s consent to a NON-EXCUSABLE DELAY, then it shall be responsible for any additional costs it incurs in its efforts to meet the delivery deadline. Notwithstanding that the DISTRICT may consent to an extension of the delivery date due to a NON- EXCUSABLE DELAY, the CONSULTANT will be required to pay any actual damages incurred by the DISTRICT as a result of such delay, by either offset against the amount due by the DISTRICT to the CONSULTANT or by submission by the DISTRICT of an invoice indicating the amount of the damages.
Non-Excusable Delays. 9.2.1 If an Aircraft is not made available for inspection for more than ** Business Days after Scheduled Inspection Date without an Excusable Delay, Buyer will be entitled to claim from Embraer liquidated damages equal to **, for each Day of delay in excess of the above mentioned ** Business Days, up to the date that the Aircraft is available for inspection and acceptance by, and subsequent delivery as per Article 7 hereof, ** . 9.2.2 Upon the occurrence of any event which constitutes causes of non Excusable Delays in delivery of an Aircraft, Embraer shall send a written notice to Buyer, within a reasonable period of time (not to exceed ** Days), including a description of details involved and an estimate of the effects expected upon the delivery of the Aircraft. ** . 9.2.3 It is agreed between the Parties that if, with respect to a delayed Aircraft, Embraer does not receive a claim for liquidated damages as mentioned in Article 9.2.1 above, from Buyer, within ** Days after the Actual Delivery Date of such Aircraft, Buyer shall be deemed to have fully waived its right to such liquidated damages.
AutoNDA by SimpleDocs
Non-Excusable Delays. 9.2.1 If the delivery of an Aircraft is delayed by Embraer for any reason other than an Excusable Delay, for more than *, Buyer shall be entitled to *, * Indicates that material has been omitted and confidential treatment has been requested therefor. All such omitted material has been filed separately with the SEC pursuant to Rule 24b-2. * up to *. If the Aircraft is delayed by Embraer for any reasons other than an Excusable Delay for *. 9.2.2 If the delivery of an Aircraft is delayed by Embraer for any reason other than an Excusable Delay *, for more than * then up to *. 9.2.3 It is hereby understood that any and all * by Embraer pursuant to this Purchase Agreement will not, in any event, *. Embraer and Buyer acknowledge that the * as set forth herein and in Items 9.2.1 and 9.2.2 are *. * pursuant to this Article 9.2. shall be * after Buyer pays to Embraer the Aircraft Purchase Price for the Aircraft in question. 9.2.4 Upon the occurrence of any event which *, Embraer shall * send a written notice to Buyer, *. 9.2.5 It is agreed between the Parties that if, with respect to a delayed Aircraft, Embraer does not receive a * as mentioned in Article 9.2.1 above, from Buyer, within * after *, Buyer shall be deemed to have fully waived its right to *.
Non-Excusable Delays. 9.2.1 If an Aircraft is not *** without an Excusable Delay, Buyer will be entitled to claim from Embraer liquidated damages equal to ***, up to the date that the Aircraft is available for inspection and acceptance by, and subsequent delivery as per Article 7 hereof, it being understood that such liquidated damages will not, in any event, *** per Aircraft and that it will only be due and payable by Embraer to Buyer after Buyer pays to Embraer the total Aircraft Purchase Price. 9.2.2 Upon the occurrence of any event which constitutes causes of non Excusable Delays in delivery of an Aircraft, Embraer shall send a written notice to Buyer, within a reasonable period of time (not to exceed *** Days), including a description of details involved and an estimate of the effects expected upon the delivery of the Aircraft. *** 9.2.3 It is agreed between the Parties that if, with respect to a delayed Aircraft, Embraer does not receive a claim for liquidated damages as mentioned in Article 9.2.1 above, from Buyer, within *** after the Actual Delivery Date of such Aircraft, Buyer shall be deemed to have fully waived its right to such liquidated damages.

Related to Non-Excusable Delays

  • Excusable Delays Except with respect to defaults of subproviders, the Engineer shall not be in default by reason of any failure in performance of this contract in accordance with its terms (including any failure to progress in the performance of the work) if such failure arises out of causes beyond the control and without the default or negligence of the Engineer. Such causes may include, but are not restricted to, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather.

  • Excusable Delay The parties shall not be obligated to perform and shall not be deemed to be in default hereunder, if the performance of a non-monetary obligation required hereunder is prevented by the occurrence of any of the following, other than as the result of the financial inability of the party obligated to perform: acts of God, strikes, lock-outs, other industrial disturbances, acts of a public enemy, war or war-like action (whether actual, impending or expected and whether de jure or de facto), acts of terrorists, arrest or other restraint of government (civil or military), blockades, insurrections, riots, epidemics, landslides, lightning, earthquakes, fires, hurricanes, storms, floods, washouts, sink holes, civil disturbances, explosions, breakage or accident to equipment or machinery, confiscation or seizure by any government or public authority, nuclear reaction or radiation, radioactive contamination or other causes, whether of the kind herein enumerated or otherwise, that are not reasonably within the control of the party claiming the right to delay performance on account of such occurrence.

  • Force Majeure Delays In any case where either party hereto is required to do any act (other than the payment of money), delays caused by or resulting from Acts of God or Nature, war, civil commotion, fire, flood or other casualty, labor difficulties, shortages of labor or materials or equipment, government regulations, delay by government or regulatory agencies with respect to approval or permit process, unusually severe weather, or other causes beyond such party’s reasonable control the time during which act shall be completed, shall be deemed to be extended by the period of such delay, whether such time be designated by a fixed date, a fixed time or “a reasonable time.”

  • Unavoidable Delays Delays due to acts of God, acts of public agencies, labor disputes, strikes, fires, freight embargoes, inability (despite the exercise of due diligence) to obtain supplies, materials, fuels or permits, or other causes or contingencies (excluding financial inability) beyond the reasonable control of Landlord or Tenant, as applicable. Landlord shall use commercially reasonable efforts to provide Tenant with prompt notice of any Unavoidable Delays.

  • Tenant Delays A "Tenant Delay” shall be defined as any delay in the design, permitting or performance of the Base Building Work to the extent that such delay is actually caused by any act or, where there is a duty to act under this Lease, any failure to act by Tenant or Tenant's contractors, architects, engineers, or anyone else engaged by or on behalf of Tenant in connection with the construction of the Tenant Improvement Work as set forth in this Article III (including, without limitation, any delays resulting from the Approved Tenant Finishes under Section 3.l(C) above) and disclosed to Tenant as hereinafter provided. Notwithstanding the foregoing, in no event shall any delays in the completion of the Base Building Work caused by Tenant’s use of non-union labor constitute a Tenant Delay hereunder. Notwithstanding the foregoing, no event shall be deemed a Tenant Delay unless and until Landlord has given Tenant written notice (the "Tenant Delay Notice") advising Tenant: (x) that a Tenant Delay is occurring and setting forth Landlord's good faith estimate as to the likely length of such Tenant Delay; (y) of the basis on which Landlord has determined that a Tenant Delay is occurring; and (z) the actions which Landlord believes that Tenant must take to eliminate such Tenant Delay. No event shall be deemed to be a Tenant Delay unless and until Tenant has failed to rectify the situation causing the Tenant Delay within forty-eight (48) hours after Tenant's receipt of the Tenant Delay Notice (which for the purposes of determining receipt may be delivered by hand to Tenant's Construction Representative, with copies to follow to Tenant at the notice address set forth in Section 1.2 of this Lease within five (5) days thereafter); provided, however, that if Tenant shall fail to eliminate the delay within the aforesaid 48-hour period, then the 48-hour cure period shall be included in the period of time charged to Tenant pursuant to such Tenant Delay Notice (it being understood and agreed that if Tenant shall in fact eliminate the Tenant Delay within the 48-hour cure period, no Tenant Delay shall be deemed to have occurred for the purposes of this Article III). In addition, any delay to the extent caused by (i) Landlord Delay or (ii) subject to the limitations of subsection (D) below, Tenant's Force Majeure (as defined in said subsection (D)) shall not constitute Tenant Delay. Tenant covenants that no Tenant Delay shall delay commencement of the Term or the obligation to pay Annual Fixed Rent or Additional Rent. The Delivery Dates and/or the date of substantial completion of the Base Building Work, as applicable, shall be deemed to have occurred as of the date when such Delivery Dates and/or date of substantial completion of the Base Building Work, as applicable, would have occurred but for any Tenant Delays, as determined by Landlord in the exercise of its good faith business judgment (it being understood and agreed that the foregoing shall not be construed so as to relieve Landlord of its obligation to actually complete the Base Building Work, notwithstanding the fact that substantial completion may have been deemed to have occurred prior to actual completion as the result of Tenant Delays).

  • Unavoidable Delay When construction is impeded as a result of strikes, lockouts, acts of God or other factors beyond the control, and ability to remedy, of the Developer.

  • Tenant Delay Except as otherwise provided in the Lease, Delivery of the Premises shall occur when Landlord’s Work has been Substantially Completed, except to the extent that completion of Landlord’s Work shall have been actually delayed by any one or more of the following causes (“Tenant Delay”): (i) Tenant’s Representative was not available to give or receive any Communication or to take any other action required to be taken by Tenant hereunder within a reasonable period of time (not to exceed 2 business days) after written request from Landlord; (ii) Tenant’s request for changes to the Building Shell, whether or not such changes are actually performed; (iii) The construction of any changes to the Building Shell requested by Tenant and agreed upon by Landlord; (iv) Tenant’s request for Change Requests (as defined in Section 4(a) below) whether or not any such Change Requests are actually performed; (v) Construction of any Change Requests; (vi) Tenant’s request for materials, finishes or installations requiring unusually long lead times (provided Landlord will request that the General Contractor inform Tenant of any long lead time items and identify substitutes for such items as soon as reasonably possible); (vii) Tenant’s delay in reviewing, revising or approving plans and specifications beyond the periods set forth herein; (viii) Tenant’s delay in providing any information that is reasonably required to come from Tenant which is critical to the normal progression of the Project within a reasonable period of time after request. Tenant shall provide such information as soon as reasonably possible, but in no event longer than one week after receipt of any request for such information from Landlord; (ix) Tenant’s delay in making payments to Landlord for Excess TI Costs (as defined in Section 5(d) below) for more than 10 business days after such Excess TI Costs are required to be paid to Landlord; or (x) Any other act or omission by Tenant or any Tenant Party (as defined in the Lease), or persons employed by any of such persons that continues for more than 1 business day after Landlord’s notice thereof to Tenant. If Delivery is delayed for any of the foregoing reasons, then Landlord shall cause the TI Architect to certify the date on which the Tenant Improvements would have been Substantially Completed but for such Tenant Delay and such certified date shall be deemed to be the Commencement Date for purposes of Tenant’s obligation to pay Base Rent, Operating Expenses, Excess TI Costs and TI Rent; however, Tenant will not have any obligation to pay any amounts to third parties pursuant to the Lease (and will not occupy the Premises) until the date upon which the Premises is Delivered to Tenant with the Landlord’s Work Substantially Complete. Upon request, Landlord shall advise Tenant of any materials, finishes or installations which are required as part of any Change Request that will result in unusually long lead times.

  • FORCE MAJEURE CLAUSE Contractor shall be excused from performance hereunder during the time and to the extent that it is prevented from obtaining delivery, or performing by act of God, fire, strike, loss, or shortage of transportation facilities, lock-out, commandeering of materials, product, plant, or facilities by the government, when satisfactory evidence thereof is presented to the District, provided that it is satisfactorily established that the

  • Force Majeure Events a) Neither Party shall be responsible or liable for or deemed in breach hereof because of any delay or failure in the performance of its obligations hereunder (except for obligations to pay money due prior to occurrence of Force Majeure events under this Agreement) or failure to meet milestone dates due to any event or circumstance (a "Force Majeure Event") beyond the reasonable control of the Party experiencing such delay or failure, including the occurrence of any of the following: i) acts of God; ii) typhoons, floods, lightning, cyclone, hurricane, drought, famine, epidemic, plague or other natural calamities; iii) acts of war (whether declared or undeclared), invasion or civil unrest; iv) any requirement, action or omission to act pursuant to any judgment or order of any court or judicial authority in India (provided such requirement, action or omission to act is not due to the breach by the SPG or of any Law or any of their respective obligations under this Agreement); v) inability despite complying with all legal requirements to obtain, renew or maintain required licenses or Legal Approvals; vi) earthquakes, explosions, accidents, landslides; fire; vii) expropriation and/or compulsory acquisition of the Project in whole or in part by Government Instrumentality; viii) chemical or radioactive contamination or ionizing radiation; or ix) damage to or breakdown of transmission facilities of GETCO/ DISCOMs; x) Exceptionally adverse weather condition which are in excess of the statistical measure of the last hundred (100) years.

  • ADDITIONAL SPECIAL CONTRACT CONDITIONS Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following: