Suspensions of Work Ordered by the Engineer Sample Clauses

Suspensions of Work Ordered by the Engineer. 1. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the engineer in writing a request for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment. 2. Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted. 3. No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed. 4. No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.
AutoNDA by SimpleDocs
Suspensions of Work Ordered by the Engineer. 1. If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the 2. Upon receipt, the engineer will evaluate the contractor's request. If the engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the engineer's determination whether or not an adjustment of the contract is warranted. 3. No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed. 4. No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.
Suspensions of Work Ordered by the Engineer. (i) If the performance of all or any portion of the work is suspended or delayed by the engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the contractor believes that addi- tional compensation and/or contract time is due as a result of such suspen- sion or delay, the contractor shall sub- mit to the engineer in writing a re- quest for adjustment within 7 calendar days of receipt of the notice to resume work. The request shall set forth the
Suspensions of Work Ordered by the Engineer. This clause provides for the adjustment of the contract terms if the performance of all or a portion of the work is suspended or delayed by the Engineer, in writing, for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry). The contractor is required to submit a request for adjustment, in writing, to the Engineer within 7 calendar days of receipt of the notice to resume work. Recovery of profit on costs resulting from suspensions of work is not allowed. 1. This clause does not preclude the recognition of constructive suspensions or delays resulting from the contracting agency's actions, without written notification. These are delays caused by the owner's instructions that are not in writing. The contractor may receive verbal orders from the engineer, or be delayed by the owners' lengthy review of submittals. Some states recognized constructive delays in their specifications prior to the FHWA regulation. The preamble to the regulation indicates that states may continue to recognize construction delays if this is provided in their standard specifications and contract administration procedures. 2. To qualify for an adjustment, suspensions must be for unreasonable periods and do not include brief, customary suspensions for reasons inherent to highway construction (i.e., material sampling and testing; approval of shop drawings, material sources, etc.; and other reasonable and customary suspensions necessary for the supervision of construction by the contracting agency). In addition, an adjustment under this clause is not allowed if the work is suspended for other reasons or if an adjustment is provided for, or excluded, under other terms or conditions of the contract.

Related to Suspensions of Work Ordered by the Engineer

  • Stop Work Orders A. The JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Services for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the parties may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Services covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Services covered by the Stop Work Order as provided for in this Agreement. B. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of Services. The JBE shall make an equitable adjustment in the delivery schedule, the Contract Amount, or both, and the Agreement shall be modified, in writing, accordingly, if: i. The Stop Work Order results in an increase in the time required for, or in Contractor’s cost properly allocable to the performance of any part of this Agreement; and ii. Contractor requests an equitable adjustment within thirty (30) days after the end of the period of stoppage; however, if the JBE decides the facts justify the action, the JBE may receive and act upon a proposal submitted at any time before final payment under this Agreement. C. The JBE shall not be liable to Contractor for loss of profits because of a Stop Work Order issued under this provision.

  • Statement of Work The Statement of Work to which Grantee is bound is incorporated into and made a part of this Grant Agreement for all purposes and included as Attachment A.

  • Work Orders If the Contract is for indefinite quantities of Services, as specified in the Signature Document, all Work will be performed in accordance with properly executed Work Orders.

  • Stop Work Order (a) NYSERDA may at any time, by written Order to the Contractor, require the Contractor to stop all or any part of the Work called for by this Agreement for a period of up to ninety (90) days after the Stop Work Order is delivered to the Contractor, and for any further period to which the parties may agree. Any such order shall be specifically identified as a Stop Work Order issued pursuant to this Section. Upon receipt of such an Order, the Contractor shall forthwith comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Order during the period of work stoppage consistent with public health and safety. Within a period of ninety (90) days after a Stop Work Order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, NYSERDA shall either: (i) by written notice to the Contractor, cancel the Stop Work Order, which shall be effective as provided in such cancellation notice, or if not specified therein, upon receipt by the Contractor, or (ii) terminate the Work covered by such order as provided in the Termination Section of this Agreement. (b) If a Stop Work Order issued under this Section is cancelled or the period of the Order or any extension thereof expires, the Contractor shall resume Work. An equitable adjustment shall be made in the delivery schedule, the estimated cost, the fee, if any, or a combination thereof, and in any other provisions of the Agreement that may be affected, and the Agreement shall be modified in writing accordingly, if: (i) the Stop Work Order results in an increase in the time required for, or in the Contractor’s cost properly allocable to, the performance of any part of this Agreement, and (ii) the Contractor asserts a claim for such adjustments within 30 days after the end of the period of Work stoppage; provided that, if NYSERDA decides the facts justify such action, NYSERDA may receive and act upon any such claim asserted at any time prior to final payment under this Agreement. (c) If a Stop Work Order is not cancelled and the Work covered by such Order is terminated, the reasonable costs resulting from the Stop Work Order shall be allowed by equitable adjustment or otherwise. (d) Notwithstanding the provisions of this Section 12.01, the maximum amount payable by NYSERDA to the Contractor pursuant to this Section 12.01 shall not be increased or deemed to be increased except by specific written amendment hereto.

  • Work Order (s) means a detailed scope of work for a Service required by Transnet, including timeframes, Deliverable, Fees and costs for the supply of the Service to Transnet, which may be appended to this Agreement from time to time.

  • Obligations of and Services to be Provided by the Manager The Manager undertakes to provide the services hereinafter set forth and to assume the following obligations:

  • Obligations of and Services to be Provided by the Adviser The Adviser undertakes to provide the services hereinafter set forth and to assume the following obligations:

  • Suspension of Work Authorization DocuSign Envelope ID: F977C999-9391-4B1E-8882-3E74EBE07795

  • Suspension of Work The Department may, at its sole discretion, suspend any or all activities under the Contract, at any time, when it is in the best interest of the State of Florida to do so. The Customer may suspend a resulting contract or purchase order, at any time, when in the best interest of the Customer to do so. The Department or Customer will provide the Contractor written notice outlining the particulars of the suspension. After receiving a suspension notice, the Contractor must comply with the notice and will cease the performance of the Contract or purchase order. Suspension of work will not entitle the Contractor to any additional compensation. The Contractor will not resume performance of the Contract or purchase order until so authorized by the Department.

  • Transitional Services Upon cancellation, termination, or expiration of the Contract for any reason, the Contractor shall provide reasonable cooperation, assistance and Services, and shall assist the Department to facilitate the orderly transition of the work under the Contract to the Department and/or to an alternative contractor selected for the transition upon written notice to the Contractor at least thirty (30) business days prior to termination or cancellation, and subject to the terms and conditions set forth in the Contract.