T ime for Completion. Consultant shall complete its obligations within 9 months of contract execution. If, through no fault of Consultant, such time or dates are changed, or the orderly and continuous progress of Consultant’s services is impaired, or Consultant’s services are delayed or suspended, then the time for completion of Consultant’s services, and the rates and amounts of Consultant’s compensation, shall be adjusted equitably. If City authorizes changes in the scope, extent, or character of Consultant’s services, then the time for completion of Consultant’s services, and the rates and amounts of Consultant’s compensation, shall be adjusted equitably. City shall make decisions and carry out its other responsibilities in a timely manner so as not to delay the Consultant’s performance of its services. If Consultant fails, through its own fault, to complete the performance required in this Agreement within the time set forth, as duly adjusted, then City shall be entitled to the recovery of direct damages, if any, resulting from such failure.
AutoNDA by SimpleDocs
T ime for Completion. The Developer shall complete the construction of the Facilities within calendar days after the work has commenced thereon, unless an extension is requested and ultimately approved by MATSF. If the Developer discontinues work on the Facilities for 90 calendar days or longer for any reason whatsoever, MATSF shall have the right to require an inspection of the Facilities at the expense of the Developer and to require performance of additional work necessary to make the Facilities acceptable to MATSF before permission will be given by MATSF to the Developer to resume work on the Facilities.

Related to T ime for Completion

  • Time for Completion The Contractor shall deliver the material and/or services called for in the specifications/proposal and within the delivery time specified and in accordance with the terms of the contract. Work shall be completed within 30 days from the Notice to Proceed issued by the City of Sparks Purchasing Division. The Contractor shall not alter or vary any terms or conditions contained or incorporated herein, including but not limited to, the quantity, price, delivery date or date designated as After Receipt of Order (ARO) or date for commencement or completion of services as mutually agreed upon, unless such alteration or variation is consented to in writing by a duly authorized representative of the City. The City reserves the right to cancel resultant Contract upon ten days written notice in the event the type and quality of the product or work performance is unsatisfactory or in default, subject to Contractor’s right to cure as outlined in termination clause. This is a non-exclusive Contract and the City reserves the right to acquire the material and/or services at its discretion, from other sources during the term of this Contract.

  • Date for Completion 4.1 Completion must take place in Canberra on the Date for Completion or as otherwise determined by the Contract and if not specified or determined, within a reasonable time.

  • Time for Commencement and Completion The term (Initial Term) of this Agreement will begin on the Effective Date and expire on ______________________, 20___. University will have the option to renew this Agreement for _______ (___) additional ______ (____) year terms (each a Renewal Term). The Initial Term and each Renewal Term are collectively referred to as the Term.

  • Extension of time for completion (i) Without prejudice to any other provision of this Agreement for and in respect of extension of time, the Contractor shall be entitled to extension of time in the Project Completion Schedule (the “Time Extension”) to the extent that completion of any Project Milestone is or will be delayed by any of the following, namely:

  • Time for Compliance Consultant shall not commence work under this Agreement until it has provided evidence satisfactory to the City that it has secured all insurance required under this section. In addition, Consultant shall not allow any subconsultant to commence work on any subcontract until it has provided evidence satisfactory to the City that the subconsultant has secured all insurance required under this section. Failure to provide and maintain all required insurance shall be grounds for the City to terminate this Agreement for cause.

  • INSTRUCTIONS FOR COMPLETING FORM A AND B Form A and Form B should be completed for Contracts for consulting services in accordance with Section XI.18.C of the Office of the State Comptroller’s Guide to Financial Operations (xxxx://xxx.xxx.xxxxx.xx.xx/agencies/guide/MyWebHelp/), “Consultant Disclosure Legislation,” and the following:

  • TIME OF COMPLETION The Owner shall issue a Notice to Proceed identifying the date for commencement of the Work. The commencement date shall be 10 or more days after the date the notice is issued. The Contractor shall achieve substantial completion of the Work within _____________________ (____) calendar days after the commencement date, as such completion date may be extended by approved Change Orders. The time set forth for completion of the Work is an essential element of the Contract.

  • Commencement and Completion of Work Upon the Effective Date of the Contract, bidder agrees to commence all Preconstruction Activities. Upon issuance of a Proceed Order, bidder agrees to commence physical activities on the Site with adequate forces and equipment and to complete to Material Completion all work in 90 consecutive calendar days beginning the day after the date of the Proceed Order. Bid Bond. Enclosed herewith is a Bid Bond (NO OTHER FORM ACCEPTABLE) in the amount of Dollars ($ ) (being not less than five percent of the Bid). Bidder agrees that the above stated amount is the proper measure of liquidated damages that the Owner will sustain by bidder’s failure to execute the Contract or to furnish the Performance and Payment Bonds should bidder’s bid be accepted. Obligation of Bid Bond. If this bid is accepted within thirty-five days after the date set for the opening of bids and bidder fails to execute the Contract within ten days after Notice of Successful Bid, or if bidder fails to furnish both Performance and Payment Bonds, the obligation of the Bid Bond will remain in full force and effect and the money payable thereon shall be paid into the funds of the Owner as liquidated damages for such failure; otherwise, the obligations of the Bid Bond will be null and void. Bidder Certification Certification under Oath. Under oath I certify that I am a principal or other representative of the bidder, and that I am authorized by it to execute the foregoing bid on its behalf; and further, that I am a principal person of the bidder with management responsibility for the construction for the bidder, and as such I am personally knowledgeable of all its pertinent matters. I further certify that this bid is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a bid for the same services, materials, labor, supplies, or equipment and is in all respects fair and without collusion or fraud. Bidder and its principals understand that collusive bidding is a violation of state and federal law and can result in fines, prison sentences, and civil damage awards. Bidder agrees to abide by all conditions of this bid. BY: Authorized Signature (BLUE INK) Printed Name Title Sworn to and subscribed before me this Day of , 20 . Notary Public My commission expires:

  • Certification of Completion Certification of completion of the program will be contingent upon Resident successfully completing the core requirements of the Program, returning all property of the Medical Center such as books, equipment, etc., and having settled any other professional or financial obligations to the Medical Center. The certificate will be issued in accordance with the provisions of the ASHP Regulations on Accreditation of Pharmacy Residencies and signed by the RPD and the Chief Executive Officer of the organization. A certificate will not be issued to anyone who does not complete the program’s requirements. Core requirements to successfully complete the program include: • Possess a valid pharmacist license from the Pennsylvania State Board of Pharmacy by October 31st of the residency year. • Successful completion of core learning experiences and required longitudinal learning experiences as defined in the learning experience descriptions • Completion of all R1 goals/objectives with a status of achieved by the end of the residency. Completion of 100% of the remaining goals/objectives for the program with at least 50% of the objectives having a status as achieved. All objectives must have a minimum status of satisfactory progress. • All evaluations must be completed in accordance with ASHP Accreditation Standard as outlined in the Resident Agreement • Completion of pharmacokinetic certification by October 31 of residency year • Completion of inpatient anticoagulation certification by October 31 of residency year. • Completion of major project, which includes meeting all project deadlines and submission of written manuscript of completed project to the RAC. • Assigned projects (MUE, drug review, class review, and management project) have been completed • Presentation of at least one major CME program. • Completion of minimum staffing requirements as described in section 2.7 • Adherence to the organization’s attendance standards and as described in this document under Exhibit A.

  • TIME OF COMMENCEMENT AND COMPLETION 2.1 The Contractor shall commence the Work upon the date established in the Notice to Proceed.