Test Program and Procedure Sample Clauses

Test Program and Procedure. During the Integrated Tests, Buyer shall arrange dispatch, and Seller shall, as appropriate, synchronize and steadily synchronise, load and operate the Capacity as required by this Agreement and Grid Code, and in accordance with the agreed program and within the constraints of the technical limits, until full load is reached. Seller shall then run the Unit at full load or as required by Seller. If not already achieved in earlier testing, all the systems and auxiliaries will be brought into their normally energized or pressurized state by the end of these tests. The Integrated Tests shall comprise the following: Fire protection system, all start-up tests; Electrical systems; Heating, ventilation and air-conditioning systems: Control and instrumentation systems, including remote terminal units, microprocessors and functional groups forming part of the DCS; Lubrication systems; Service air systems; Instrument air systems; Cooling systems; Final protection settings, in accordance with agreed design, including those for load shedding protection schemes; Software function and stability tests; Turbine generator protection and tripping settings; Emergency power systems; Motor roll of the hydro turbine; Ignition checks; Excitation checks; Over speed tests; Manual synchronizing; Ramp up and ramp down tests (specifically, during the Integrated Tests, Seller shall confirm the ramp up and ramp down behaviour of the applicable Unit, and any other requirements as prescribed in the Grid Code; Partial and full load rejection tests to demonstrate the ability to run through to full speed no-load, provided that Buyer, System Operator and Seller agree that such test will not jeopardise the safe operation of the grid system at that time; Standby equipment changeover tests; Automatic governor control tests including verification of the droop characteristics of the G's and Block's, and confirmation that the Unit operation is safe and stable within the technical limits; Automatic voltage regulation tests; Confirmation of the methods and equations/Correction Curves to be used for adjusting the recorded data and/or test results to the design conditions and/or Guaranteed Conditions; and other tests mutually agreed prior to the commencement of the Integrated Tests.
AutoNDA by SimpleDocs
Test Program and Procedure. The duration of the Reliability Test for each unit is fifteen (15) consecutive Days during which time such Unit (as the case may be) and its auxiliaries shall, except as permitted hereunder, be operated continuously according to the test and load program agreed between Buyer and Seller. Buyer shall arrange dispatch and System Operator shall dispatch the Unit in accordance with this program and the requirements of this Agreement. The Unit may be subjected to varying load as may be required to conduct or complete other tests. In the event of interruption (zero load and/or effective disco1mection at the Delivery Point), beyond the tolerance permitted in this Clause 14) c) (ii), in generation of the demanded load, due to failure within Seller's responsibilities, the Reliability Test shall be restarted from the beginning. Two (2) such episodes of interruption, not exceeding twenty-four (24) hours in aggregate, shall be permitted. If, for reasons beyond Seller's responsibilities (including any Force Majeure Event), a fault develops during the Unit Reliability Test that necessitates the interruption of the Unit Reliability Test or limits it, then the Unit Reliability Test shall be suspended for the duration of the fault. If the Unit Reliability Test is so suspended, then the Unit Reliability Test shall not be prolonged by the amount of time so lost, and shall be deemed not to have been so interrupted. If the Unit Reliability Test is so suspended for more than three (3) consecutive Days, then Seller and Buyer shall seek to agree as to when and how the Reliability Test shall be demonstrated. The Unit Reliability Test shall also include the following specific tests: at least one (1) cold start; at least one (1) hot start of each Unit; weekly change over of standby equipment; and other tests mutually agreed prior to the commencement of the units Reliability Test; provided that, if, in any previously successful Reliability Test, unit has demonstrated such capability as is the object of such tests (i) though (iv), then Seller may, but shall not be obliged to, waive such test.
Test Program and Procedure a) The Capacity Test for the Plant shall be performed on the basis of the operation of the Plant for six (6) continuous hours without any interruption at full load. During the Capacity Test of the Plant, SO shall dispatch the Plant as requested by Xxxxxx and required by the terms of this Agreement. The Capacity Test shall be performed and monitored by Seller and witnessed by Xxxxx and the Engineer.

Related to Test Program and Procedure

  • Test procedure The engine speed shall be gradually increased from idle to the target engine speed, not exceeding the tolerance band of ±3 per cent of the target engine speed, and held constant. Then the throttle control shall be rapidly released and the engine speed shall be returned to idle. The sound pressure level shall be measured during a period of operation consisting of a maintaining constant engine speed of 1 second and throughout the entire deceleration period. The maximum sound level meter reading during this period of operation, mathematically rounded to the first decimal place, is taken as the test value.

  • Ordering Guidelines and Processes 1.14.1 For information regarding Ordering Guidelines and Processes for various Network Elements, Combinations and Other Services, TWTC should refer to the “Guides” section of the AT&T Interconnection Web site. TWTC will be notified of any material changes to such “Guides”.

  • Contractor Requirements and Procedures For Business Participation Opportunities For NYS Certified Minority- and Women-Owned Business Enterprises and Equal Employment Opportunities for Minority Group Members and Women

  • Development Plan document specifying the work program, schedule, and relevant investments required for the Development and the Production of a Discovery or set of Discoveries of Oil and Gas in the Contract Area, including its abandonment.

  • TIMELINESS OF BILLING SUBMISSION The parties agree that timeliness of billing is of the essence to this Contract and recognize that the City is on a fiscal year. All xxxxxxxx for dates of service prior to July 1 must be submitted to the City no later that the first Friday in August of the same year.

  • Testing Procedure A. For alcohol testing, the member shall be first given a breath test, at the collection site, followed by a confirmatory urine test only where the breath test reveals an initial positive alcohol level of .04 grams per 210 l. of breath. If the initial breath test results are below this level, testing shall be discontinued; if confirmatory urine tests results are below a level equivalent to .04 grams per 210 l. of breath, the confirmatory test shall be considered negative.

  • Project Plan Development of Project Plan Upon the Authorized User’s request, the Contractor must develop a Project Plan. This Project Plan may include Implementation personnel, installation timeframes, escalation procedures and an acceptance plan as appropriate for the Services requested. Specific requirements of the plan will be defined in the RFQ. In response to the RFQ, the Contractor must agree to furnish all labor and supervision necessary to successfully perform Services procured from this Lot. Project Plan Document The Contractor will provide to the Authorized User, a Project Plan that may contain the following items: • Name of the Project Manager, Contact Phone Numbers and E-Mail Address; • Names of the Project Team Members, Contact Phone Numbers and E-Mail Address; • A list of Implementation milestones based on the Authorized User’s desired installation date; • A list of responsibilities of the Authorized User during system Implementation; • A list of designated Contractor Authorized Personnel; • Escalation procedures including management personnel contact numbers; • Full and complete documentation of all Implementation work; • Samples of knowledge transfer documentation; and • When applicable, a list of all materials and supplies required to complete the Implementation described in the RFQ. Materials and Supplies Required to Complete Implementation In the event that there are items required to complete an Implementation, the Contractor may request the items be added to its Contract if the items meet the scope of the Contract. Negotiation of Final Project Plan If the Authorized User chooses to require a full Project Plan, the State further reserves the right for Authorized Users to negotiate the final Project Plan with the apparent RFQ awardee. Such negotiation must not substantively change the scope of the RFQ plan, but can alter timeframes or other incidental factors of the final Project Plan. The Authorized User will provide the Contractor a minimum of five (5) business days’ notice of the final negotiation date. The Authorized User reserves the right to move to the next responsible and responsive bidder if Contractor negotiations are unsuccessful.

  • Contractor Requirements and Procedures For Business Participation Opportunities For New York State Certified Minority- and

  • ORDERING PROCEDURE Orders placed against this contract may be in the form of an agency issued purchase order on an as-required basis. Or an agency may also use the Arkansas State Purchasing Card (P- Card) to purchase furniture.

  • Violence Policies and Procedures The Employer agrees to have in place explicit policies and procedures to deal with violence. The policy will address the prevention of violence, the management of violent situations, provision of legal counsel and support to employees who have faced violence. The policies and procedures shall be part of the employee's health and safety policy and written copies shall be provided to each employee. Prior to implementing any changes to these policies, the employer agrees to consult with the Association.