The Owner’s. Project Manager shall assist the Owner and the Designer in preparing and sending the Notice to Proceed to the Contractor.
The Owner’s. Project Manager shall assist the Owner in the preparation and execution of the Owner-Contractor Agreement and shall obtain from the Contractor performance and payment bonds, insurance certificates, and all other documents and certificates required for contract execution.
The Owner’s. Project Manager shall assist the Owner in completing the written evaluation of the Designer(s) pursuant to M.G. L. c. 7 § 38E and prepare, sign and provide to the Owner for its signature the written evaluation of the Contractor(s) and Trade Subcontractors pursuant to M.G.L. c. 149 § 44D.
The Owner’s. Project Manager shall shoot and maintain Project progress photographs showing construction progress at a frequency sufficient to document major activities or to document safety incidents, differing site conditions and quality issues. The Owner’s Project Manager shall maintain a descriptive log and captioning of the photographs on CD.
The Owner’s. Project Manager’s review of the construction documents shall also include, but not be limited to, any concerns of the Owner’s Project Manager and/or the Owner relative to access, usable area, parking, utilities, anticipated noise sources during construction and identification of field offices, facilities, supplies and equipment.
The Owner’s. Project Manager shall provide a full-time (40 hours per week minimum) on-site Project Representative, who shall be dedicated exclusively to the Project, either as an employee of the Owner’s Project Manager or as a subconsultant to the Owner’s Project Manager.
8.6.2.1 The Project Representative shall be subject to the approval of the Owner and the Owner reserves the right to require the Owner’s Project Manager to replace the Project Representative at any time during the course of the Project.
8.6.2.2 The Project Representative shall have at least five years experience in on-site supervision of projects similar in size and complexity to the Project.
8.6.2.3 Unless otherwise directed, the Project Representative shall be present at all times when the Contractor is conducting operations at the site starting from issuance by the Owner of a Notice to Proceed to the Contractor and continuing until issuance to the Contractor of a Certificate of Substantial Completion by the Owner and thereafter on an, as needed basis, until issuance to the Contractor of a Certificate of Final Completion by the Owner.
The Owner’s. Project Manager shall coordinate the timely review of the design between the Designer and the Commissioning Consultant. The Owner’s Project Manager shall be responsible for providing the necessary documents to the Commissioning Consultant for its review, distributing review comments made to the Designer, Owner and the Authority and coordinate the timely resolution and incorporation of the Commissioning Consultant’s recommendations. The Owner's Project Manager shall not be responsible for the Commissioning Consultant’s performance, but if the Owner’s Project Manager becomes aware of any performance or lack of performance issues with the Commissioning Consultant, the Owner’s Project Manager shall immediately notify the Owner and the Authority of such issues.
The Owner’s. SIGNED, SEALED, EXECUTED and ) DELIVERED as a DEED by ) IVS BULK OWNING PTE. LTD. ) /s/ Xxxx Xxxxxxx Xxxxxxxx acting by ) such execution being witnessed by: ) SIGNED, SEALED, EXECUTED and ) DELIVERED as a DEED by ) IVS BULK CARRIERS PTE. LTD. ) /s/ Xxxx Xxxxxxx Xxxxxxxx acting by ) such execution being witnessed by: ) SIGNED, SEALED, EXECUTED and ) DELIVERED as a DEED by ) IVS BULK 603 PTE. LTD. ) /s/ Xxxx Xxxxxxx Xxxxxxxx acting by ) such execution being witnessed by: )
The Owner’s. Project Manager shall continue to oversee the activities and responsibilities of the Designer in the further development of the scope, schedule and budget including a general review of the Designer’s detailed scaled plans, elevations and sections of all aspects of the design. The Owner’s Project Manager shall:
a. Review and reconcile the construction cost estimates of the Designer and the CM at Risk. In the event that the Owner has not executed a contract with a CM at Risk by the end of the Design Development Phase, the Owner’s Project Manager shall prepare an independent construction cost estimate for comparison with the Designer’s cost estimate.
b. Work with the Owner, Designer and CM at Risk to update the Project Budget and Schedule.
The Owner’s. Project Manager shall coordinate the timely review of the design between the Designer and the Commissioning Consultant. The Owner’s Project Manager shall be responsible for providing the necessary documents to the Commissioning Consultant for its review, distributing review comments made to the Designer, Owner and the Authority and coordinate the timely resolution and incorporation of the Commissioning Consultant’s recommendations. The Owner's Project Manager shall not be responsible for the Commissioning Consultant’s performance, but if the Owner’s Project Manager becomes aware of any performance or lack of performance issues with the Commissioning Consultant, the Owner’s Project Manager shall immediately notify the Owner and the Authority of such issues. The Owner’s Project Manager shall coordinate the timely review of the construction documents by the Commissioning Consultant to determine that plans and specifications include the recommendations made by the Commissioning Consultant during design development in regard to materials selection, installation and testing criteria in regard to commissioning and start-up and provide adequate information and allow sufficient time for functional and system testing.