Baseline Project Schedule definition

Baseline Project Schedule means the time-scaled and cost-loaded Critical Path Method (CPM) network, updated in accordance with the Contract and depicting the Price Items and subordinate activities and their respective prices (distributed over time), durations, sequences, and interrelationships and represent the Contractor’s Work plans; the Contractor’s Work Breakdown Structure (WBS) for the Work including the design, permitting and construction activities and completing the Project; and the Contract Price distributed over the period of the Contract.

Examples of Baseline Project Schedule in a sentence

  • The Baseline Project Schedule will remain unaltered as a tool to measure progress outlined and anticipated during the Initial Schedule Meetings and from the agreed-upon Baseline Project Schedule.

  • If the Contractor fails substantially to perform in a timely manner in accordance with the Contract Documents and, through the fault of the Contractor or Subcontractor(s) of any tier, fails to meet the Baseline Project Schedule, the Contractor shall take such steps as may be necessary to immediately improve its progress by increasing the number of workers, shifts, overtime operations, or days of work, or by other means and methods, all without additional cost to the Port.

  • The Baseline Project Schedule includes a tentative schedule of events and dates.

  • The Contractor shall furnish sufficient forces and shall work such hours, including extra shifts, overtime operations, and weekend and holiday work as may be necessary to ensure completion of the Work within the Contract Time and the approved Baseline Project Schedule.

  • This may include major milestones or phases required by the Contract Documents to be utilized by the Contractors and Project Team in developing the Baseline Project Schedule.

  • OGS Scheduling will maintain the agreed-upon Baseline Project Schedule as the assigned project baseline schedule.

  • A Baseline Project Schedule (BPS) within sixty (60) days after receiving the NTP.

  • Revised Project Work Plan developed from recovery options presented by the Contractor to the Director’s Representative when Project Update Reporting indicates the Work is 15 or more work days behind the current Substantial Completion dates of the agreed-to Baseline Project Schedule.

  • The goal of the meeting is for CDCR to accept the proposed Contract Schedule as the Baseline Project Schedule for the project.

  • OGS Scheduling will maintain the Baseline Agreement Recovery Project Schedule as the assigned Baseline Project Schedule.

Related to Baseline Project Schedule

  • Project Schedule means a document that, with respect to each Phase of the Project, identifies, coordinates and integrates the anticipated design and construction schedules, the Contracting Authority’s and Owner's responsibilities, government authority reviews and other activities as are necessary for the timely completion of the Work.

  • Baseline Schedule means the initial time schedule prepared by Contractor for Owner’s information and acceptance that conveys Contractor’s and Subcontractors’ activities (including coordination and review activities required in the Contract Documents to be performed by A/E and ODR), durations, and sequence of work related to the entire Project to the extent required by the Contract Documents. The schedule clearly demonstrates the critical path of activities, durations and necessary predecessor conditions that drive the end date of the schedule. The Baseline Schedule shall not exceed the time limit current under the Contract Documents.

  • Development Schedule shall have the meaning set forth in Section 1.1.

  • Project Completion Schedule means the progressive Project Milestones set forth in Schedule-J for completion of the Project Highway on or before the Scheduled Completion Date;

  • The Project Plan means the document to be developed by the Supplier and approved by the Purchaser, pursuant to GCC Clause 19, based on the requirements of the Contract and the Preliminary Project Plan included in the Supplier’s bid. The “Agreed and Finalized Project Plan” is the version of the Project Plan approved by the Purchaser, in accordance with GCC Clause 19.2. Should the Project Plan conflict with the Contract in any way, the relevant provisions of the Contract, including any amendments, shall prevail.

  • Milestone Schedule means Seller’s milestone schedule, the form of which is attached to this Agreement as Exhibit Q.

  • Project Scope means the description or activity of work to be accomplished on the Project.

  • BASE budget means the minimum general fund budget of a district, which includes 80% of the basic

  • Approved Project Budget means the most recent statement, approved by the FTA, of the costs of the Project, the maximum amount of Federal assistance for which the TJPA is currently eligible, the specific tasks (including specified contingencies) covered, and the estimated cost of each task.

  • Project Plan means the document to be developed by the Contractor and approved by WTL, based on the requirements of the Contract and the Preliminary Project Plan included in the Contractor’s bid. For the sake of clarity, the Agreed and Finalized Project Plan” refers to the version of the Project Plan submitted by the contractor after receiving the letter of Award and the same approved by WTL. The project plan may be changed/ modified during the course of the project. Should the Project Plan conflict with the provisions of the Contract in any way, the relevant provisions of the Contract, including any amendments, shall prevail.

  • Project Budget means the budget and project description included in the grant application. The Project Budget must succinctly describe all major elements of project work, the estimated cost of each and clearly allocate requested grant funding and match contributions to each.

  • Contract Schedule means a schedule to this Contract;

  • Construction Budget means the cost of acquisition, installation, testing, constructing and developing any Property as determined by the Construction Agent in its reasonable, good faith judgment.

  • Project Milestones means the Project milestones set out in Schedule 3;

  • Work Schedule means the approved order and timeline for how the requirements of this contract, including Work on individual Units or groups of Units, will be fulfilled by the Contractor.

  • Project area budget means a multiyear projection of annual or cumulative

  • Project Plans mean the plans for the Project that are attached to this Agreement as Exhibit “B.”

  • Product Schedule means a product schedule documenting the specific terms and conditions applying to a Product as may be amended, updated or replaced from time to time (and includes any Electronic Platform Schedules);

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.

  • Project Milestone means the project milestone set forth in Schedule-J;

  • The Contract Price/Project Cost means the price payable to the Vendor under the Contract for the full and proper performance of its contractual obligations.

  • Construction Schedule means a construction schedule indicating the planned start and completion dates of the major activities of the Work as set out in Appendix [ ], a future Appendix;

  • Original Project Cost means the capital expenditure incurred by the Generating Company or the Transmission Licensee, as the case may be, within the original scope of the project up to the cut-off date as admitted by the Commission;

  • Total Contract Price/Project Cost/TCO means the price payable to Service Provider over the entire period of Contract for the full and proper performance of its contractual obligations.

  • Development Budget means the cost categories listed on Pages 8 - 11 in Form 3 that are directly related to the proposed Project as submitted in the Application. Indirect or off-site costs not directly related to the development of the project are not valid or eligible costs.

  • Project Completion Date means the date on which the Completion Certificate is issued;