Date of commencement of the project means the date of the agreement.
Cost of the Project means and embraces the cost of construction; the cost of all
Scope of the Project shall have the meaning set forth in Clause 2.1;
Redevelopment project means a specific construction project
Project means the goods or Services described in the Signature Document or a Work Order of this Contract.
The Project means supply, installation, testing and commissioning, integration of computer hardware and services with support under Warranty and annual maintenance contract, if required for the contract period.
The Project Site, where applicable, means the place or places named in the SCC.
Tenant Improvements Defined in Exhibit B, if any.
Tenant Improvement Work means the construction of the Tenant Improvements, together with any related work (including demolition) that is necessary to construct the Tenant Improvements.
Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.
Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:
Construction Commencement Date means the date set out in the Addendum, if applicable, by which you must commence construction of the Hotel. For the Hotel to be considered under construction, youmust have begun to pour concrete foundations for the Hotel or otherwise satisfied any site-specific criteria for “under construction” set out in the Addendum.
Pilot project means an innovative environmental project that covers one or more designated facilities, designed and implemented in the form of an EMSA. (See Section 52.3 of the Act.)
Construction Completion means physical construction of a cleanup action component is complete.
Construction Phase means that Phase of the Project which shall commence after the Authority provides the Trade Contractor with written Notice to Proceed with the Construction Phase.
Renovation means altering a facility or one or more facility components in any way, including the stripping or removal of RACM from a facility component. Operations in which load-supporting structural members are wrecked or taken out are demolitions.
Construction project means the same as that term is defined in Section 38-1a-102.
Expansion Project has the meaning set forth in Section IV.3.a of this Agreement.
Project Commencement Date means the commencement date notified to the Minister pursuant to clause 4(1);
Tenant Work All work installed or furnished to the Premises by Tenant in connection with Tenant’s initial occupancy pursuant to Rider 2 and the Workletter.
Landlord Work means the work, if any, that Landlord is obligated to perform in the Premises pursuant to a separate agreement (the “Work Letter”), if any, attached to this Lease as Exhibit C.
Ongoing Project means a multi-year project undertaken by a Company in fulfilment of its CSR obligation having timelines not exceeding three years excluding the financial year in which it was commenced, and shall include such project that was initially not approved as a multi-year project but whose duration has been extended beyond one year by the board based on reasonable justification;
Redevelopment Project Area means an area designated by the municipality, which is not less in the aggregate than 1 1/2 acres and in respect to which the municipality has made a finding that there exist conditions which cause the area to be classified as an industrial park conservation area or a blighted area or a conservation area, or a combination of both blighted areas and conservation areas.
Capital Improvement Project means the acquisition, construction, reconstruction, improvement, planning and equipping of roads and bridges, appurtenances to roads and bridges to enhance the safety of animal-drawn vehicles, pedestrians, and bicycles, wastewater treatment facilities, water supply systems, solid waste disposal facilities, and storm water and sanitary collection, storage and treatment facilities including real property, interests in real property, facilities, and equipment related or incidental to those facilities.
Construction Work means any work in connection with⎯
Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;