Date of Works Completion definition

Date of Works Completion means a Certificate of Completion issued by the Principal Agent appointed by the Grant Recipient or the Developer, when the contractor has completed all the work specified in the works completion list;
Date of Works Completion the date which the Consultant certifies as being the date on which practical completion of the Works was achieved for the purposes of this agreement
Date of Works Completion means the date agreed to complete the work by the contractor and mentioned in the special conditions of the contract.

Examples of Date of Works Completion in a sentence

  • Date of Works Completion: 31 March 2019 Note: The programme must be based on the completion time as specified in the Contract Data.

  • Date of Works Completion: 29 March 2019 Note: The programme must be based on the completion time as specified in the Contract Data.

  • Details of NominationFeature No. : Location : Agreement No. : Contract No. : Date of Works Completion : (dd/mm/yyyy) 3.

  • Date of Works Completion: Note: The programme must be based on the completion time as specified in the Contract Data.

Related to Date of Works Completion

  • Project Start Date means the first Milestone Start Date specified in Schedule B;

  • Contract Start Date means the date specified in your Contract for Signature as the date this Contract starts;

  • Date of Completion with respect to a Project shall mean: (i) the date upon which such Project and all components thereof have been acquired or constructed and are capable of performing the functions for which they were intended, as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; or (ii) the date on which the Issuer determines, upon the recommendation of or in consultation with the Consulting Engineer, that it cannot complete such Project in a sound and economical manner within a reasonable period of time as evidenced by an Engineers’ Certificate filed with the Trustee and the Issuer; provided that in each case such certificate of the Consulting Engineer shall set forth the amount of all Costs of such Project which have theretofore been incurred, but which on the Date of Completion is or will be unpaid or unreimbursed.

  • Project Completion means the date, as determined by the Division after consultation with the Recipient, that operation of the Project is initiated or is capable of being initiated, whichever comes first.

  • Final Completion means the date determined and certified by A/E and Owner on which the Work is fully and satisfactorily complete in accordance with the Contract.

  • Work Site means the site where the Work is being performed.

  • Construction Completion Date means the Completion Date of the Construction as specified in the Statutory Declaration of Completion for the Project;

  • Testson Completion means the tests which are specified in the Contractor agreed by both Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on Completion] before the Works or a Section (as the case may be) are taken over by the Procuring Entity.

  • Project Completion Date means the date on which the Completion Certificate is issued;

  • The Completion Date means the date of completion of the Works as certified by the Employer’s Representative.

  • project completion period means the period of sixty (60) months commencing from and expiring on for the construction and obtaining of Temporary Occupation Permit or Permits for the whole of the Development as provided in clause 3.3;

  • Target Completion Date has the meaning given such term in Section 3.3(b).

  • Scheduled Completion Date shall be the date set forth in Clause 10.3;

  • Work Order means an individually negotiated document that is executed by both Parties and which authorizes a Project, if any, in an indefinite quantity Contract.

  • Construction Completion means physical construction of a cleanup action component is complete.

  • Development Work means any work carried out in relation to the physical construction of a mine;

  • Completion of work means completion of the entire contracted work. Exhaustion of quantity of any particular item mentioned in the bid document shall not imply completion of work or any component thereof.

  • The Work Order means the order placed by the Purchaser on the Supplier signed by the Purchaser including all attachments and appendices thereto and all documents incorporated by reference therein. The Work order shall be deemed as "Contract" appearing in the document.

  • Period of Work means the time during which an employee is at the disposal of the employer;

  • The Work means the work or works to be executed or done under this contract.

  • Final Completion Date means the date on which Final Completion occurs.

  • Continuous Improvement Plan means a plan for improving the provision of the Goods and/or Services and/or reducing the Charges produced by the Supplier pursuant to Framework Schedule 12 (Continuous Improvement and Benchmarking);

  • Substantial Completion means the stage in the progress of the work as determined and certified by the Contracting Officer in writing to the Contractor, on which the work (or a portion designated by the Government) is sufficiently complete and satisfactory. Substantial completion means that the property may be occupied or used for the purpose for which it is intended, and only minor items such as touch-up, adjustments, and minor replacements or installations remain to be completed or corrected which:

  • Practical Completion means the completion of the Project where the building is fit for occupancy and/or purpose.

  • Virtual Completion means the premise is in the opinion of the Employer fit for occupation.

  • Billing Commencement Date means the earlier of: