Examples of Final Completion Deadline in a sentence
In the event that Department approves adjustments to the Contract Times, Department will issue a Work Order setting forth the date changes and the application, if any, of any incentive or liquidated damage with respect to any revised Substantial Completion Deadline or Final Completion Deadline.
Design-Builder understands that if the Substantial Completion Deadline or the Final Completion Deadline, or both, is not attained, Department will suffer damages that are difficult to determine and accurately specify.
In addition, the Substantial Completion Deadline and the Final Completion Deadline shall each be extended by the number of days between the NTP Delay Date and the date of issuance of the NTP if the conditions described in this Section 5.1.3.1 occur.
If the DB Contractor fails to achieve the Final Completion Deadline, the DB Contractor agrees to pay the District Liquidated Damages in the following amount: $1000 per Day or portion of a Day for the DB Contractor’s failure to achieve Final Completion by the Final Completion Deadline if not the fault of the District, and the DB Contractor agrees and acknowledges that such amount is an accurate estimate of the actual damages the District would incur in the event of such a delay.
The DB Contractor shall diligently and expeditiously prosecute the Work and shall achieve Final Completion of the entire Work by the Final Completion Deadline (such deadline being subject to adjustments in the Contract Time as provided in this Agreement).