Examples of Project Substation in a sentence
Contractor shall be responsible for performing all Work necessary to interconnect the WTGs, the Project Substation and other components of the Work, as set forth in the Scope of Work and Technical Specifications, and in compliance with the Interconnection Agreement.
The Project Substation circuit breakers, disconnect switches, PTs, CTs, and surge arresters will be connected by a combination of strain buses and rigid buses mounted on porcelain insulators, supported on steel structures.
The Project Substation will be connected to the Xxxxxxx Substation, described below, by overhead 230 kV buswork and a 230 kV disconnect switch.
Install an additional SONET optical multiplex and channel equipment at Windhub Substation and at the CPC West Project Substation 4B for this redundant fiber optical cable.
In addition to the wind turbines, the project will also include the following qualified investment inPawnee ISD: • Access roads to the turbines • Underground electrical collection cables and fiber network • Permanent meteorological towers • Overhead transmission line connecting the project substation to the Point of Interconnection • Aircraft Detection Lighting System • Operations and Maintenance Building • Project Substation The location of each of these improvements is shown on the map in Tab 11.
Seller shall cause the Project Meters to be installed on the high voltage side of the Project Substation step-up transformer.
Interconnection Customer: Task Dates Initial Back-feed through Project Substation Date May 1, 2022 Project Commercial Operation Date for 274MWac December 15, 2022 The Interconnection Customer shall complete all Customer Interconnection Facilities and Transmission Owner Interconnection Facilities to be built by Interconnection Customer pursuant to Option to Build set forth in Schedules D, G and I of this CSA by May 1, 2022.
The schedule of work for the Interconnection Customer is: Task Dates Initial Back-feed through Project Substation Date 09/01/2022 Project Commercial Operation Date 12/31/2022 SCHEDULE K APPLICABLE TECHNICAL REQUIREMENTS AND STANDARDS “EKPC Facility Connection Requirements” rev.
The Project Owner’s Meters are installed on the low voltage side of the Project Substation transformer immediately prior to the Project Delivery Point.
The Project Substation will include circuit breaker current transformers and bus- connected voltage transformers for metering and relaying.