Rescheduling of Tests Sample Clauses

Rescheduling of Tests. If the Authority’s Engineer certifies to the Authority and the Contractor that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Contractor shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
AutoNDA by SimpleDocs
Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. ENTRY INTO COMMERCIAL SERVICE
Rescheduling of Tests. If the Independent Engineer certifies to the Authority and the Concessionaire that it is unable to certify the completion of the facilities required for rendering Healthcare Services or issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire at its own cost and expense, shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. The provisions of this Article 15 shall apply mutatis mutandis to such re-scheduled Tests.
Rescheduling of Tests. If the Independent Monitor[s] certifies to the Authority and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. If the Independent Engineer certifies to CEB and Seller that it is unable to issue the Completion Certificate, as the case may be, because of events or circumstances on account of which the tests could not be held or had to be suspended, Seller shall be entitled to re-schedule the tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. 13 Change of Scope
Rescheduling of Tests. If the Authority is unable to issue the Completion Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Mine Operator shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable. Provided, however, that the Mine Operator shall be excused for the delay in Tests arising hereunder if such delay is not solely attributable to the Mine Operator.
AutoNDA by SimpleDocs
Rescheduling of Tests. If the Commissioning Committee certifies to Railways and the SPD that it is unable to issue the Completion Certificate because of events or circumstances on account of which the Tests could not be held or had to be suspended, the SPD shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.
Rescheduling of Tests. 13 Change of Scope Drafit Contract Agreement 13.1 Change of Scope
Rescheduling of Tests. 14.6.1 If the Construction Supervisor certifies to the ULB and the Concessionaire that it is unable to issue the Completion Certificate or Provisional Certificate, as the case may be, because of events or circumstances on account of which the Tests could not be held or had to be suspended, the Concessionaire shall be entitled to re-schedule the Tests and hold the same as soon as reasonably practicable.