Available Capacity Forecasting Sample Clauses

Available Capacity Forecasting. Seller shall provide the Available Capacity forecasts described below. [The following bracketed language applies to As-Available solar or wind Projects only] [Seller’s availability forecasts below shall include Project availability and updated status of [The following bracketed language applies to solar Projects only] [photovoltaic panels, inverters, transformers, and any other equipment that may impact availability] or [The following bracketed language applies to wind Projects only] [transformers, wind turbine unit status, and any other equipment that may impact availability].] [The following bracketed language applies to As-Available Product only] [To avoid Forecasting Penalties set forth in Section 4.6(c)(iii),] Seller shall use commercially reasonable efforts to forecast the Available Capacity of the Project accurately and to transmit such information in a format reasonably acceptable to Buyer. Buyer and Seller shall agree upon reasonable changes to the requirements and procedures set forth below from time-to-time, as necessary to comply with CAISO Tariff changes, accommodate changes to their respective generation technology and organizational structure and address changes in the operating and Scheduling procedures of Buyer, Third-Party SC (if applicable) and the CAISO, including automated forecast and outage submissions.
AutoNDA by SimpleDocs
Available Capacity Forecasting. Seller shall provide the Available Capacity forecasts described below. Seller’s availability forecasts below shall include Project availability and updated status of photovoltaic panels, inverters, transformers, and any other equipment that may impact availability. To avoid Forecasting Penalties set forth in Section 4.5(c)(iii), Seller shall use commercially reasonable efforts to forecast the Available Capacity of the Project accurately and to transmit such information in a format reasonably acceptable to Buyer. Buyer and Seller shall agree upon reasonable changes to the requirements and procedures set forth below from time-to-time, as necessary to comply with CAISO Tariff changes, accommodate changes to their respective generation technology and organizational structure and address changes in the operating and Scheduling procedures of Buyer, Third-Party SC (if applicable) and the CAISO, including automated forecast and outage submissions.
Available Capacity Forecasting. Seller shall provide the Available Capacity forecasts described below. Seller’s availability forecasts below shall include Project availability and updated status of photovoltaic panels, inverters, transformers, and any other equipment that may impact availability. To avoid Forecasting Penalties set forth in Section 4.5(c)(ii), Seller shall use commercially reasonable efforts to forecast the Available Capacity of the Project accurately and to transmit such information in a format reasonably acceptable to Buyer. Buyer and Seller shall agree upon reasonable changes to the requirements and procedures set forth below from time-to-time, as necessary to comply with CAISO Tariff changes, accommodate changes to their respective generation technology and organizational structure and address changes in the operating and Scheduling procedures of Buyer, Third-Party SC (if applicable) and the CAISO, including but not limited to automated forecast and outage submissions. Annual Forecast of Available Capacity. No later than (I) the earlier of September 1 of the first Contract Year or forty-five (45) days before the first day of the first Contract Year of the Delivery Term, if applicable, and (II) September 1 of each calendar year for every subsequent Contract Year during the Delivery Term, Seller shall provide to Buyer and Third-Party SC (if applicable) a non-binding forecast of the hourly Available Capacity for an average day in each month of the following calendar year in a form reasonably acceptable to Buyer. Monthly Forecast of Available Capacity. Ten (10) Business Days before the beginning of each month during the Delivery Term, Seller shall provide to Buyer and Third-Party SC (if applicable) a non-binding forecast of the hourly Available Capacity for each day of the following month in a form reasonably acceptable to Buyer. Daily Forecast of Available Capacity. During each month of the Delivery Term, Seller or Seller’s agent shall provide a binding day ahead forecast of Available Capacity (the “Day-Ahead Availability Notice”) to Buyer or Third-Party SC (as applicable) via Buyer’s internet site, as provided in Appendix VIII, for each day no later than fourteen (14) hours before the beginning of thePreschedule Day” (as defined by the WECC) for such day. The current industry standard Preschedule Day timetable in the WECC is as follows:
Available Capacity Forecasting. Seller shall provide the Available Capacity forecasts described below. [The following bracketed language applies to As-Available Product only] Seller shall use commercially reasonable efforts to forecast the Available Capacity of the Project accurately and to transmit such information in a format reasonably acceptable to Buyer. Buyer and Seller shall agree upon reasonable changes to the requirements and procedures set forth below from time-to-time, as necessary to comply with CAISO Tariff changes, accommodate changes to their respective generation technology and organizational structure and address changes in the operating and Scheduling procedures of Buyer and the CAISO, including but not limited to automated forecast and outage submissions.
Available Capacity Forecasting. Seller shall provide the Available Capacity forecasts described below. To avoid Forecasting Penalties set forth in Section 4.6(c)(iii),Seller shall use commercially reasonable efforts to forecast the Available Capacity of the Project accurately and to transmit such information in a format reasonably acceptable to Buyer. Buyer and Seller shall agree upon reasonable changes to the requirements and procedures set forth below from time-to-time, as necessary to comply with CAISO Tariff changes, accommodate changes to their respective generation technology and organizational structure and address changes in the operating and Scheduling procedures of Buyer, Third-Party SC (if applicable) and the CAISO, including automated forecast and outage submissions.
Available Capacity Forecasting. Seller shall provide the Available Capacity forecasts described below. Seller’s availability forecasts below shall include Project availability and updated status of transformers, wind turbine unit status, and any other equipment that may impact availability. Seller shall use commercially reasonable efforts to forecast the Available Capacity of the Project accurately and to transmit such information in a format reasonably acceptable to Buyer. Buyer and Seller shall agree upon reasonable changes to the requirements and procedures set forth below from time-to-time, as necessary to comply with CAISO Tariff changes, accommodate changes to their respective generation technology and organizational structure and address changes in the operating and Scheduling procedures of Seller, Buyer, Third-Party SC (if applicable) and the CAISO, including but not limited to automated forecast and outage submissions.

Related to Available Capacity Forecasting

  • TRUNK FORECASTING 57.1. CLEC shall provide forecasts for traffic utilization over trunk groups. Orders for trunks that exceed forecasted quantities for forecasted locations will be accommodated as facilities and/or equipment are available. Sprint shall make all reasonable efforts and cooperate in good faith to develop alternative solutions to accommodate orders when facilities are not available. Company forecast information must be provided by CLEC to Sprint twice a year. The initial trunk forecast meeting should take place soon after the first implementation meeting. A forecast should be provided at or prior to the first implementation meeting. The semi-annual forecasts shall project trunk gain/loss on a monthly basis for the forecast period, and shall include: 57.1.1. Semi-annual forecasted trunk quantities (which include baseline data that reflect actual Tandem and end office Local Interconnection and meet point trunks and Tandem-subtending Local Interconnection end office equivalent trunk requirements) for no more than two years (current plus one year); 57.1.2. The use of Common Language Location Identifier (CLLI-MSG), which are described in Telcordia documents BR 000-000-000 and BR 000-000-000; 57.1.3. Description of major network projects that affect the other Party will be provided in the semi-annual forecasts. Major network projects include but are not limited to trunking or network rearrangements, shifts in anticipated traffic patterns, or other activities by CLEC that are reflected by a significant increase or decrease in trunking demand for the following forecasting period. 57.1.4. Parties shall meet to review and reconcile the forecasts if forecasts vary significantly.

  • Forecasting Manager and Sprint PCS will work cooperatively to generate mutually acceptable forecasts of important business metrics including traffic volumes, handset sales, subscribers and Collected Revenues for the Sprint PCS Products and Services. The forecasts are for planning purposes only and do not constitute Manager's obligation to meet the quantities forecast.

  • Interconnection Customer Provided Services The services provided by Interconnection Customer under this LGIA are set forth in Article 9.6 and Article 13.5. 1. Interconnection Customer shall be paid for such services in accordance with Article 11.6.

  • Under-Frequency and Over Frequency Conditions The New York State Transmission System is designed to automatically activate a load- shed program as required by the NPCC in the event of an under-frequency system disturbance. Developer shall implement under-frequency and over-frequency relay set points for the Large Generating Facility as required by the NPCC to ensure “ride through” capability of the New York State Transmission System. Large Generating Facility response to frequency deviations of predetermined magnitudes, both under-frequency and over-frequency deviations, shall be studied and coordinated with the NYISO and Connecting Transmission Owner in accordance with Good Utility Practice. The term “ride through” as used herein shall mean the ability of a Generating Facility to stay connected to and synchronized with the New York State Transmission System during system disturbances within a range of under-frequency and over-frequency conditions, in accordance with Good Utility Practice and with NPCC Regional Reliability Reference Directory # 12, or its successor.

  • Forecast Customer shall provide Flextronics, on a monthly basis, a rolling [***] forecast indicating Customer’s monthly Product requirements. The first [***] of the forecast will constitute Customer’s written purchase order for all Work to be completed within the first [***] period. Such purchase orders will be issued in accordance with Section 3.2 below.

  • Minimum Customer Support Requirements for TIPS Sales Vendor shall provide timely and commercially reasonable support for TIPS Sales or as agreed to in the applicable Supplemental Agreement.

  • Local Circuit Switching Capability, including Tandem Switching Capability 4.2.1 Local circuit switching capability is defined as: (A) line-side facilities, which include, but are not limited to, the connection between a loop termination at a main distribution frame and a switch line card; (B) trunk-side facilities, which include, but are not limited to, the connection between trunk termination at a trunk-side cross-connect panel and a switch trunk card; (C) switching provided by remote switching modules; and (D) all features, functions, and capabilities of the switch, which include, but are not limited to: (1) the basic switching function of connecting lines to lines, line to trunks, trunks to lines, and trunks to trunks, as well as the same basic capabilities made available to BellSouth’s customers, such as a telephone number, white page listings, and dial tone; and (2) all other features that the switch is capable of providing, including but not limited to customer calling, customer local area signaling service features, and Centrex, as well as any technically feasible customized routing functions provided by the switch. Any features that are not currently available but are technically feasible through the switch can be requested through the BFR/NBR process. 4.2.2 Notwithstanding BellSouth’s general duty to unbundle local circuit switching, BellSouth shall not be required to unbundle local circuit switching for Louisville Telephone when Louisville Telephone serves an end-user with four (4) or more voice-grade (DS-0) equivalents or lines served by BellSouth in one of the following MSAs: Atlanta, GA; Miami, FL; Orlando, FL; Ft. Lauderdale, FL; Charlotte-Gastonia-Rock Hill, NC; Greensboro-Winston Salem-High Point, NC; Nashville, TN; and New Orleans, LA, and BellSouth has provided non- discriminatory cost based access to the Enhanced Extended Link (EEL) throughout Density Zone 1 as determined by NECA Tariff No. 4 as in effect on January 1, 1999. 4.2.3 In the event that Louisville Telephone orders local circuit switching for an end user with four (4) or more DS0 equivalent lines within Density Zone 1 in an MSA listed above, BellSouth shall charge Louisville Telephone the market based rates in Exhibit B for use of the local circuit switching functionality for the affected facilities.

  • Rolling Forecast (i) On or before the fifteenth (15th) calendar day of each month during the Term (as defined in Section 6.1 herein), Buyer shall provide Seller with an updated eighteen (18) month forecast of the Products to be manufactured and supplied (each a “Forecast”) for the eighteen (18) month period beginning on the first day of the following calendar month. The first two months of each Forecast will restate the balance of the Firm Order period of the prior Forecast, and the first three (3) months of the Forecast shall constitute the new Firm Order period for which Buyer is obligated to purchase and take delivery of the forecasted Product, and the supply required for the last month of such new Firm Order period shall not be more than one (1) full Standard Manufacturing Batch from the quantity specified for such month in the previous Forecast (or Initial Forecast, as the case may be). Except as provided in Section 2.2(a), Purchase Orders setting forth Buyer’s monthly Product requirements will be issued for the last month of each Firm Order period no later than the fifteenth calendar day of the first month of each Firm Order period, and such Purchase Order will be in agreement with the Firm Order period of the Forecast. If a Purchase Order for any month is not submitted by such deadline, Buyer shall be deemed to have submitted a Purchase Order for such month for the amount of Product set forth in Buyer’s Forecast for such month. (ii) The remainder of the Forecast shall set forth Buyer’s best estimate of its Product production and supply requirements for the remainder of the Forecast period. Each portion of such Forecast that is not deemed to be a Firm Order shall not be deemed to create a binding obligation on Buyer to purchase and take delivery of Products nor a binding obligation of Seller to deliver Products, except as otherwise provided in Section 2.2(f). (iii) Forecast and Purchase Orders shall be in full Standard Manufacturing Batches. If a Product has multiple SKUs, then the composite of the forecasted SKU must equate to the Standard Manufacturing Batch. One Purchase Order shall be issued for each full Standard Manufacturing Batch of Product and contain the required information set forth in Section 2.2(e) hereof.

  • Cost Responsibility for Interconnection Facilities and Distribution Upgrades 4.1 Interconnection Facilities 4.2 Distribution Upgrades

  • Contract Capacity The electric power producing capability of the Generating Facility which is committed to Edison.