Cost Estimate The cost estimate shall set out the estimated costs for the proposed Change Order in such a way that a fair evaluation can be made. It shall include a breakdown for labor, materials, equipment and markups for overhead and profit, unless TxDOT agrees otherwise. If the work is to be performed by Subcontractors and if the work is sufficiently defined to obtain Subcontractor quotes, DB Contractor shall obtain quotes (with breakdowns showing cost of labor, materials, equipment and markups for overhead and profit) on the Subcontractor’s stationery and shall include such quotes as back-up for DB Contractor’s estimate. No markup shall be allowed in excess of the amounts allowed under Section 10.6. DB Contractor shall identify all conditions with respect to prices or other aspects of the cost estimate, such as pricing contingent on firm orders being made by a certain date or the occurrence or non-occurrence of an event.
ESTIMATED / SPECIFIC QUANTITY CONTRACTS Estimated quantity contracts, also referred to as indefinite delivery / indefinite quantity contracts, are expressly agreed and understood to be made for only the quantities, if any, actually ordered during the Contract term. No guarantee of any quantity is implied or given. With respect to any specific quantity stated in the contract, the Commissioner reserves the right after award to order up to 20% more or less (rounded to the next highest whole number) than the specific quantities called for in the Contract. Notwithstanding the foregoing, the Commissioner may purchase greater or lesser percentages of Contract quantities should the Commissioner and Contractor so agree. Such agreement may include an equitable price adjustment.
Cost Estimates If this Agreement pertains to the design of a public works project, CONSULTANT shall submit estimates of probable construction costs at each phase of design submittal. If the total estimated construction cost at any submittal exceeds ten percent (10%) of CITY’s stated construction budget, CONSULTANT shall make recommendations to CITY for aligning the PROJECT design with the budget, incorporate CITY approved recommendations, and revise the design to meet the Project budget, at no additional cost to CITY.
Estimated Cost Estimated costs by construction phases for Specified Roads listed in A7 are stated by segments in the Schedule of Items. Such estimated costs are subject to adjustment under B3.3, B5.2, B5.21, B5.212, B5.25, and B5.26. Appropriately adjusted costs shall be made a part of a revised Schedule of Items and shown as adjustments to Timber Sale Account. The revised Schedule of Items shall supersede any prior Schedule of Items when it is dated and signed by Contracting Officer and a copy is furnished to Purchaser.
Initial Cost Subject to reimbursement as hereinafter provided, the cost of organizing the Trust and the sale of the Units shall be borne by the Depositor, provided, however, that the liability on the part of the Depositor under this Section 3.01 shall not include any fees or other expenses incurred in connection with the administration of the Trust subsequent to the deposit referred to in Section 2.01. At the earlier of six (6) months after the Initial Date of Deposit or the conclusion of the initial offering period (as certified by the Depositor to the Trustee), the Trustee shall withdraw from the account(s) specified in the Prospectus or, if no account is therein specified, from the Capital Account, and pay to the Depositor the Depositor’s reimbursable expenses of organizing the Trust in an amount certified to the Trustee by the Depositor. In no event shall the amount paid by the Trustee to the Depositor for the Depositor’s reimbursable expenses of organizing the Trust exceed the estimated per Unit amount of organization costs set forth in the Prospectus for the Trust multiplied by the number of Units of the Trust outstanding at the earlier of six (6) months after the Initial Date of Deposit or the conclusion of the initial offering period; nor shall the Depositor be entitled to or request reimbursement for expenses of organizing the Trust incurred after the earlier of six (6) months after the Initial Date of Deposit or the conclusion of the initial offering period. If the cash balance of the Capital Account is insufficient to make such withdrawal, the Trustee shall, as directed by the Depositor, sell Securities identified by the Supervisor, or distribute to the Depositor Securities having a value, as determined under Section 5.01 as of the date of distribution, sufficient for such reimbursement provided that such distribution is permissible under applicable laws and regulations. Securities sold or distributed to the Depositor to reimburse the Depositor pursuant to this Section shall be sold or distributed by the Trustee, to the extent practicable, in the Percentage Ratio then existing (unless the Trust is a RIC, in which case sales or distributions by the Trustee shall be made in accordance with the instructions of the Supervisor or its designees). The reimbursement provided for in this Section shall be for the account of Unitholders of record at the earlier of six (6) months after the Initial Date of Deposit or the conclusion of the initial offering period. Any assets deposited with the Trustee in respect of the expenses reimbursable under this Section 3.01 shall be held and administered as assets of the Trust for all purposes hereunder. Any cash which the Depositor has identified as to be used for reimbursement of expenses pursuant to this Section 3.01 shall be held by the Trustee, without interest, and reserved for such purposes and, accordingly, prior to the earlier of six (6) months after the Initial Date of Deposit or the conclusion of the initial offering period, shall not be subject to distribution or, unless the Depositor otherwise directs, used for payment of redemptions in excess of the per Unit amount payable pursuant to the next sentence. If a Unitholder redeems Units prior to the earlier of six months after the Initial Date of Deposit or the conclusion of the initial offering period, the Trustee shall pay the Unitholder, in addition to the Unit Value of the tendered Units (in the computation of which the expenses reimbursable pursuant to this Section shall have been deducted), unless otherwise directed by the Depositor, an amount equal to the estimated per Unit cost of organizing the Trust set forth in the Prospectus, or such lower revision thereof most recently communicated to the Trustee by the Depositor, multiplied by the number of Units tendered for redemption; to the extent the cash on hand in the Trust is insufficient for such payments, the Trustee shall have the power to sell Securities in accordance with Section 6.02. As used herein, the Depositor’s reimbursable expenses of organizing the Trust shall include, but are not limited to, the cost of the initial preparation and typesetting of the registration statement, prospectuses (including preliminary prospectuses), the Indenture, and other documents relating to a Trust Securities and Exchange Commission and state blue sky registration fees, the costs of the initial valuation of the portfolio and audit of a Trust, the costs of a portfolio consultant, if any, one-time licensing fees, if any, the initial fees and expenses of the Trustee, and legal and other out-of-pocket expenses related thereto, but not including the expenses incurred in the printing of prospectuses (including preliminary prospectuses), expenses incurred in the preparation and printing of brochures and other advertising materials and any other selling expenses.”
Total Project Cost With regard to any Real Property acquired prior to or during the development, construction or improvement stages, all hard and soft costs and expenses paid or incurred by or on behalf of the Corporation that are in any way related to the development, construction, improvement or stabilization (including tenant improvements) of such Real Property, including, but not limited to, any debt, whether borrowed or assumed, land and construction costs.
Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.
Statement of Estimated Direct Expenses In addition, Landlord shall give Tenant a yearly expense estimate statement (the “Estimate Statement”) which shall set forth Landlord’s reasonable estimate (the “Estimate”) of what the total amount of Direct Expenses for the then-current Expense Year shall be and the estimated Tenant’s Share of Direct Expenses (the “Estimated Direct Expenses”). The failure of Landlord to timely furnish the Estimate Statement for any Expense Year shall not preclude Landlord from enforcing its rights to collect any Estimated Direct Expenses under this Article 4, nor shall Landlord be prohibited from revising any Estimate Statement or Estimated Direct Expenses theretofore delivered to the extent necessary. Thereafter, Tenant shall pay, with its next installment of Base Rent due that is at least thirty (30) days thereafter, a fraction of the Estimated Direct Expenses for the then-current Expense Year (reduced by any amounts paid pursuant to the last sentence of this Section 4.4.2). Such fraction shall have as its numerator the number of months which have elapsed in such current Expense Year, including the month of such payment, and twelve (12) as its denominator. Until a new Estimate Statement is furnished (which Landlord shall have the right to deliver to Tenant at any time), Tenant shall pay monthly, with the monthly Base Rent installments, an amount equal to one-twelfth (1/12) of the total Estimated Direct Expenses set forth in the previous Estimate Statement delivered by Landlord to Tenant.
Project Cost An updated cost spreadsheet reflecting the current forecasted cost vs. the latest approved budget vs. the baseline budget should be included in this section. One way to track project cost is to show: (1) Baseline Budget, (2) Latest Approved Budget, (3) Current Forecasted Cost Estimate, (4) Expenditures or Commitments to Date, and (5) Variance between Current Forecasted Cost and Latest Approved Budget. Line items should include all significant cost centers, such as prior costs, right-of-way, preliminary engineering, environmental mitigation, general engineering consultant, section design contracts, construction administration, utilities, construction packages, force accounts/task orders, wrap-up insurance, construction contingencies, management contingencies, and other contingencies. The line items can be broken-up in enough detail such that specific areas of cost change can be sufficiently tracked and future improvements made to the overall cost estimating methodology. A Program Total line should be included at the bottom of the spreadsheet. Narratives, tables, and/or graphs should accompany the updated cost spreadsheet, basically detailing the current cost status, reasons for cost deviations, impacts of cost overruns, and efforts to mitigate cost overruns. The following information should be provided:
Price Schedule, Payment Terms and Billing, and Price Adjustments (a) Price Schedule: Price Schedule under this Contract is set forth in Exhibit B.