Lease Commencement Date Delays Sample Clauses

Lease Commencement Date Delays. Each Lease Commencement Date shall occur as provided in Section 3.1 of this Lease, provided that the six (6) month period referenced in clause (i) of Section 3.2.1 of the Summary, and clause (ii)(a) of Sections 3.2.2 and 3.2.3 of the Summary shall be extended by one (1) day for each day of “Lease Commencement Date Delay,” but only to the extent such Lease Commencement Date Delay causes the Substantial Completion of the Improvements within the applicable Phase to occur after the applicable date referenced in clause (ii) of Section 3.2.1 of the Summary and clause (ii)(b) of Sections 3.2.2 and 3.2.3 of the Summary. As used herein, the term “Lease Commencement Date Delay” shall mean only a “Force Majeure Delay” or a “Landlord Caused Delay,” as those terms are defined below in this Section 5.1 of this Work Letter which relates to the construction of Improvements within the applicable Phase. As used herein, the term “Force Majeure Delay” shall mean only an actual delay resulting from strikes, fire, wind, damage or destruction to the Buildings or Project, explosion, casualty, flood, hurricane, tornado, the elements, acts of God or the public enemy, sabotage, war, terrorist acts, invasion, insurrection, rebellion, civil unrest, riots, or earthquakes. As used in this Work Letter, “Landlord Caused Delay” shall mean actual delays to the extent resulting from the following acts or omissions of Landlord or Landlord’s agents, employees or contractors: (i) the failure of Landlord to timely approve or disapprove any Construction Drawings pertaining to the applicable Phase; or (ii) interference (when judged in accordance with industry custom and practice) by Landlord, its agents or Landlord Parties (except as otherwise allowed under this Work Letter) with the Substantial Completion of the Improvements within the applicable Phase and which objectively preclude or delay the construction of improvements in the applicable Building by any person, which interference relates to access by Tenant, or Tenant’s Agents to the applicable Building; or (iii) delays due to the acts or failures to act of Landlord or Landlord Parties with respect to payment of the Improvement Allowance (except as otherwise allowed under this Work Letter) but Tenant shall have a right to suspend its design and construction of its Improvements if Landlord fails to reimburse Tenant all or any part of the Improvement Allowance when due, provided that Landlord’s failure to reimburse Tenant all or any part of the...
AutoNDA by SimpleDocs
Lease Commencement Date Delays. The Commencement Date shall occur as provided in Section 1.5 of this Lease, provided that the Commencement Date shall be extended by the number of days of actual delay of the Substantial Completion of the Tenant Improvements and/or Tenant’s move into the Premises to the extent caused by a “Commencement Date Delay,” as that term is defined, below. As used herein, the term “Commencement Date Delay” shall mean only a “Force Majeure Delay” or a “Landlord Delay,” as those terms are defined below in this
Lease Commencement Date Delays. 4.01 Tenant shall notify Landlord when Substantial Completion has been achieved. In the event Tenant fails to complete the Leasehold Improvements on or before the Lease Commencement Date, Tenant shall be responsible for Rent and all other obligations set forth in the Lease from the Lease Commencement Date regardless of the degree of completion of the Leasehold Improvements on such date, and no such delay in completion of the Leasehold Improvements shall relieve Tenant of any of its obligations under the Lease.
Lease Commencement Date Delays. The Lease Commencement Date shall occur as provided in Section 2.1 of this Lease and Section 3.2 of the Summary, provided that the Outside Lease Commencement Date shall be extended by the number of days of actual delay of the Substantial Completion of the Tenant Improvements in the Premises to the extent caused by a "Commencement Date Delay," as that term is defined, below, but only to the extent such Commencement Date Delay causes the Substantial Completion of the Tenant Improvements to occur after August 1, 2017. As used herein, the term "Commencement Date Delay" shall mean only a "Force Majeure Delay", "Landlord Caused Delay," or "Permit Delay", as those terms are defined below in this Section 5.1 of this Tenant Work Letter.
Lease Commencement Date Delays. The Lease Commencement Date shall occur as provided in Section 3.2 of the Summary, provided that the Lease Commencement Date and the Allowance Deadline shall each be extended by the number of days of delay of the Substantial Completion EXHIBIT B-11- [Reddit, Inc.] 000 XXXXXX XXXXXX Xxxxx Xxxxx
Lease Commencement Date Delays. The Lease Commencement Date with respect to each Phase of the Premises shall be extended by the number of days of delay of the Substantial Completion of the Improvements (as defined below) to the extent solely caused by a "Completion Delay," as that term is defined below, but only to the extent such Completion Delay causes the Substantial Completion of the Improvements to occur (a) with respect to the Phase I Premises, after the later of (A) the date that is ninety (90) days following the Phase I Premises Delivery Date, or (B) the date of Substantial Completion of the Phase I Premises Improvements set forth on Tenant’s construction schedule for the applicable portion of the Phase I Premises, (b) with respect to the Phase II Premises, the later of (1) the date that is one hundred fifty (150) days following the Phase II Premises Delivery Date, or (2) the date of Substantial Completion of the Phase II Premises EXHIBIT B-19-
Lease Commencement Date Delays. The Lease Commencement Date shall occur as provided in Section 2.1 of this Lease and Section 5.2 of the Summary, provided that the Lease Commencement Date shall be extended (A) by the number of days of delay of the Substantial Completion of the Tenant Improvements in the Premises to the extent caused by a "Commencement Date Delay," as that term is defined below, but only to the extent that such Commencement Date Delay causes the Substantial Completion of the Tenant Improvements to occur after the end of the Construction Period and (B) until Landlord shall substantially complete the Base Building and has received a temporary or permanent certificate of occupancy for the Building, subject to Tenant Delays. As used herein, the term "COMMENCEMENT DATE DELAY" shall mean only a "Force Majeure Delay" or a "Landlord Caused Delay," as those terms are EXHIBIT D -13-
AutoNDA by SimpleDocs
Lease Commencement Date Delays. The Lease Commencement Date shall occur as provided in Article 2 of this Lease, provided that the Lease Commencement Date shall be delayed by the number of days of delay of the "substantial completion of the Tenant Improvements," as that term is defined below in this Section 5, in the Premises which is caused solely by a "Lease Commencement Date Delay," which shall mean only an actual delay resulting from the acts or omissions of Landlord including, but not limited to (i) failure of Landlord to timely approve or disapprove any Construction Drawings; (ii) unreasonable and material interference by Landlord, its agents or contractors with the completion of the Tenant Improvements and which objectively preclude construction of tenant improvements in the Building by any person, which interference relates to access by Tenant, its agents and contractors to the Building or any Building facilities (including loading docks and freight elevators) or service (including temporary power and parking areas as provided herein) during normal construction hours, or the use thereof during normal construction hours; and (iii) delays due to the acts or failures to act of Landlord, its agents or contractors with respect to payment of the Tenant Improvement Allowance and/or any cessation of work upon the Tenant Improvements as a result thereof.
Lease Commencement Date Delays. The Lease Commencement Date shall occur as provided in Section 7.2 of the Summary, provided that the date described in the Section 7.2(ii) component of the definition of Lease Commencement Date shall be delayed by the number of days of delay of the "substantial completion of the Tenant Improvements," as that term is defined below in this Section 5, in the Premises which is caused solely by a "Lease Commencement Date Delay." As used herein, the term "LEASE COMMENCEMENT DATE DELAY" shall mean only an actual delay resulting from fire, earthquake, explosion, flood, hurricane, the elements, acts of God or the public enemy, war, invasion, insurrection, rebellion, riots, industry-wide labor strikes or lockouts (which objectively preclude Tenant from obtaining from any source union labor or substitute materials necessary for completing the Tenant Improvements), or governmental acts (which do not specifically relate to the construction of the Tenant Improvements and which objectively preclude construction of tenant improvements in the Building by any person).
Lease Commencement Date Delays. The Lease Commencement Date shall occur as provided in SECTION 2.1 of this Lease and SECTION 3.2 of the Summary, provided that the Lease Commencement Date and the Rent Commencement Date shall be extended by the number of days of delay of the Substantial Completion of the Tenant Improvements in the Premises to EXHIBIT B -12-
Time is Money Join Law Insider Premium to draft better contracts faster.