of AIA Document A201. 2007 or by other provisions of the Contract Documents, and which do not fall within the scope of Section 6.7.3.
of AIA Document A201. 2007 requires release of applicable retainage upon Substantial Completion of Work with consent of surety, if any.)
.2 Add, if final completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional amounts payable in accordance with Section 9.10.3
of AIA Document A201. The provisions of Article 14 of AIA Document A201 do not otherwise apply to this Paragraph 10.2.
of AIA Document A201. If the Owner's accountants report the Cost of the Work as substantiated by the Construction Manager's final accounting to be less than claimed by the Construction Manager, the Construction Manager shall be entitled to proceed in accordance with Article 9 without a further decision of the Architect. Unless agreed to otherwise, a demand for mediation or arbitration of the disputed amount shall be made by the Construction Manager within 60 days after the Construction Manager's receipt of a copy of the Architect's final Certificate for Payment. Failure to make such demand within this 60-day period shall result in the substantiated amount reported by the Owner's accountants becoming binding on the Construction Manager. Pending a final resolution of the disputed amount, the Owner shall pay the Construction Manager the amount certified in the Architect's final Certificate for Payment.
of AIA Document A201. 2007 and the term
of AIA Document A201. The Owner shall be responsible for obtaining the services of a licensed laboratory to verify the presence or absence of the material or substance reported by the Construction Manager and, in the event such material or substance is found to be present, to verify that it has been rendered harmless. Unless otherwise required by the Contract Documents, the Owner shall furnish in writing to the Construction Manager and Architect the names and qualifications of persons or entities who are to perform tests verifying the presence or absence of such material or substance or who are to perform the task of removal or safe containment of such material or substance. The Construction Manager and Architect will promptly reply to the Owner in writing stating whether or not either has reasonable objection to the persons or entities proposed by the Owner if either the Construction Manager or Architect has an objection to a person or entity proposed by the Owner, the Owner shall propose another to whom the Construction Manager and the Architect have no reasonable objection.
of AIA Document A201. In repairing or correcting damaged or nonconforming Work executed by the Construction Manager or the Construction Manager's Subcontractors or suppliers, provided that such damaged or nonconforming Work was not caused by the negligence or failure to fulfill a specific responsibility to the Owner set forth in this Agreement of the Construction Manager or the Construction Manager's foremen, engineers or superintendents, or other supervisory, administrative or managerial personnel of the Construction Manager, or the failure of the Construction Manager's personnel to supervise adequately the Work of the Subcontractors or suppliers, and only to the extent that the cost of repair or correction is not recoverable by the Construction Manager from insurance, Subcontractors or suppliers.
of AIA Document A201. The time periods stated in this Paragraph 7.2 supersede those stated in Subparagraph 9.4.1
of AIA Document A201 containing a record of weather, Subcontractors working on the site, number of workers, Work accomplished, problems encountered and other similar relevant data as the Owner may reasonably require. The Copies of the log shall be available provided each month to the Owner and Architect as a precondition to payment application approval.
2.3.2.7 The Construction Manager shall develop a system of cost control for the Work, including regular monitoring of actual costs for activities in progress and estimates for uncompleted tasks and proposed changes. The Construction Manager shall identify variances between actual and estimated costs and report the variances to the Owner and Architect at regular intervals.
2.3.2.8 Unless otherwise provided in the Contract Documents, the Construction Manager shall obtain and pay for all necessary permits, approvals, licenses, government charges and inspection fees required for the prosecution of the Work by any government or quasi-government entity having jurisdiction over the Project.
2.3.2.9 The Construction Manager shall update and distribute Master Schedules, construction schedules, and Cash Flow reports as appropriate.
2.3.2.10 The Construction Manager shall assist the Owner in obtaining Occupancy Permits by appropriate Governmental organizations during inspections of the Work, including preparing and submitting documentation, coordinating final testing and other activities.
2.3.2.11 If the Construction Manager supplies any construction equipment to be billed against the GMP, the billing rate shall be no higher than that of similar equipment provided by local rental companies. No idle time may be charged to the Work.
of AIA Document A201. Such costs shall be at rates not higher than those customarily paid at the place of the Project except with prior written consent of the Owner. The Cost of the Work shall include only the items set forth in this Article 6.