Performance tests after Completion Sample Clauses

Performance tests after Completion. The Contractor to demonstrate that the works can operate as guaranteed by the Contractor (in Contractor’s Works Information) or specified by the Employer either here or elsewhere in this Works Information.
AutoNDA by SimpleDocs
Performance tests after Completion. The physical equipment and system performance guarantee shall be demonstrated during the reliability test run for a period of 90 days after the commissioning of the last machine and in agreement with the Project Manager.
Performance tests after Completion a. The Contractor applies formally for each test/test phases to start. The test only starts when the Plant is in a fully operational state. Plant commissioning and optimization are not be allowed during testing.
Performance tests after Completion. CONTRACT 37 ECC3 COVER PAGES
Performance tests after Completion. Cold commissioning open and closing of the valve with actuator installed. Assess the response time of the valve and fail to open functionality
Performance tests after Completion. Not applicable.
Performance tests after Completion. The Contactor shall conduct performance test after installation in the presence of the Project Manager and the Engineer according to the QCP.
AutoNDA by SimpleDocs
Performance tests after Completion. The Contractor tests the works in accordance with the accepted testing procedure.
Performance tests after Completion. The Contractor will perform all tests required to bring the asset to service.
Performance tests after Completion. After Completion of the Works the Contractor applies formally to the Employer to conduct any tests on the Plant. No optimisation and commissioning of the Plant is permitted during any testing periods. The Contractor develops and submits for approval to the Employer a complete testing and inspection procedure for all tests/test phases to be conducted after Completion of the works. The testing and inspection procedure includes all tests and inspections deemed necessary by the Contractor to prove to the Employer’s satisfaction that the Plant performs according to the Employers specification. The testing and inspection procedure includes as a minimum:  Correct switching of the level switches.  Confirmation that the xxxxxx aeration allows the ash to flow freely. In the case of a failure of any of the tests/test phases, the functional tests for the relevant areas of the Plant and all affected areas of the Plant are repeated. The capacity and reliability tests are redone in total on the relevant Plant. During the test period, the Employer’s personnel operates the Plant, under the supervision of the Contractor. The Contractor is not permitted to directly operate the Plant. The Employer reserves the right to carry out further testing on the Plant. On completion of all the tests the Contractor supplies in triplicate, completed test certificates. The Contractor supplies all prescribed statutory documents as are required, certifying that the Plant is in complete working order and that all working parts are evenly lubricated.