Project Delays Sample Clauses

Project Delays. Consultant will make all reasonable efforts to comply with the Project Schedule as stated in the Attachment Two to the Schedule(s), Schedule of Completion. In the event the Project Schedule will be delayed, Consultant will notify Valley Water Project Manager as soon as possible, providing the reason why, the length of the delay, and a description of the actions being taken to address the delay. In the event Consultant is delayed in performance of its services by circumstances beyond its control, Valley Water may, at its discretion, grant a reasonable adjustment in the Project Schedule.
AutoNDA by SimpleDocs
Project Delays. If the Engineer is required to perform additional Engineering Services due to delays by the imposition of causes not within the Engineer’s control, such as by the re-advertisement of bids or by the delinquency or insolvency of contractors, such services associated with these delays shall be considered additional services, and the Engineer shall be compensated by the Owner for such extra services and expense in accordance with Article 8 hereof. Owner and Engineer shall execute a Supplemental Agreement setting forth such terms.
Project Delays. Contractor shall notify SBAC, in writing, within five (5) days of when Contractor knew or reasonably should have known of the impact of an occurrence of an event that may result in a delay of the performance of the Services. Thereafter, Contractor and SBAC shall immediately enter into discussions to arrive at a mutually satisfactory revision to the time of completion of the Services and/or compensation for the Services.
Project Delays. In the event Sponsor delays, suspends or places a hold on the Study for any reason, Sponsor shall promptly provide Worldwide with written notice of such delay, hold or suspension, and Sponsor and Worldwide will, [***] of such notice, [***] to this Agreement and each Party will complete its respective duties and obligations as described in any resulting Change Order. During the period following Worldwide’s receipt of Sponsor’s notice of delay, hold or suspension, if Sponsor desires Worldwide to continue the assignment of certain Worldwide Study personnel to the Study, [***] to Worldwide hereunder, Sponsor agrees that it shall [***] associated with such continued assignment at [***], such [***] to be agreed upon by the Parties prior to commencement of the delay, as evidenced by a Change Order. Said personnel fees shall be [***] and shall be due and payable by Sponsor within [***] days of Sponsor’s receipt of Worldwide’s invoice. If Sponsor does not wish to retain certain Worldwide Study personnel for the duration of the delay or on hold period, Worldwide shall have the right to reallocate any and all such staff after [***] day period. If the delay or on-hold period continues for [***] either Party may, by provision of written notice, terminate this Agreement without penalty.
Project Delays. Physician will inform Company as early as possible of any anticipated delays in meeting the timeframes and of the actions being taken to assure completion of the Services and Inventions within a time period acceptable to Company.
Project Delays. The Consultant will make all reasonable efforts to comply with the Project Schedule as stated in the Attachment Two to the Schedule(s), Schedule of Completion. In the event the Project Schedule will be delayed, Consultant will notify the District Project Manager as soon as possible, providing the reason why, the length of the delay, and a description of the actions being taken to address the delay. In the event Consultant is delayed in performance of its services by circumstances beyond its control, District may in its discretion grant a reasonable adjustment in the Project Schedule.
Project Delays. The Client recognizes and agrees that various factors both within and without the control of Visarton LLC can operate to delay our work, and the overall completion of the project. The Client agrees that it shall not be entitled to any claim for damages on account of hindrances or delays from any cause whatsoever including, but not limited to: the production of digital images or animations; post-production; beginning or completion of construction; or, performance of any phase of the work pursuant to this Agreement.
AutoNDA by SimpleDocs
Project Delays. 2.5.1 Each Party shall through the JPT, notify the other promptly in the event of an actual or predicted material Project Delay, due to circumstances outside either Party’s control. A “
Project Delays. Each Party shall promptly communicate to the other Party any and all difficulties that might materially affect the timely completion of any milestone set forth in the relevant SOW and where possible estimate the probable or actual impact to the aforesaid milestone resulting from such difficulties, and any actions which might favorably resolve such difficulties. To the extent the completion of any activity defined in an SOW and required to be performed by either Party is delayed by such Party, there shall be an extension equal to such delay in the target completion dates of all subsequent dependent activities set forth in the SOW. SOW Change Orders. The Parties recognize that the design and development efforts described in a SOW might need to be revised over time. Absent written approval from the Parties, no change(s) that would substantially impact costs, functionality, scope of work, or milestone schedules (collectively "Major Modifications") shall be made to any SOW. Major Modifications to any SOW shall be reflected in a new version of the SOW, which will be appended to this Agreement. All proposed Major Modifications will be fully described in a Project change summary for consideration by both Parties, including any changes affecting the anticipated costs of the Project. All Major Modifications will be negotiated and agreed upon in writing prior to implementation. Third party licenses. With respect to Deliverables to be delivered by a Party under a Project (the "Delivering Party"), the Delivering Party shall use reasonable commercial efforts to obtain under fair and reasonable terms and conditions satisfactory to the other Party, any third party license and support agreement for tools and software that are identified in the SOW as necessary for efficient completion of a Project. Support and Maintenance of the 8x8 Based Product For a period of six (6) months after the Completion of a relevant Project 8x8 will provide ST the support and maintenance for the 8x8 Based Product as described in Exhibit 1 of the License Agreement. At the latest within thirty (30) days after the end of this six (6) months period and upon payment of the Fees ST shall have the right to extend the support and maintenance for another twelve (12) months period, thereafter such support and maintenance will be automatically extended on a year-to-year basis upon payment by ST of the Fees before the end of the current year.
Project Delays. Each Party shall promptly communicate to the other Party any and all difficulties that might materially affect the timely completion of any milestone set forth in the relevant SOW and where possible estimate the probable or actual impact to the aforesaid milestone resulting from such difficulties, and any actions which might favorably resolve such difficulties. To the extent the completion of any activity defined in an SOW and required to be performed by either Party is delayed by such Party, there shall be an extension equal to such delay in the target completion dates of all subsequent dependent activities set forth in the SOW; provided, however, that each Party shall use commercially reasonable efforts to meet Project milestones.