Suppression Schedule Sample Clauses

Suppression Schedule. The regular work schedule for UAF Local 1324 Unit Members working a suppression schedule shall be approximately fifty-six (56) hours per week on alternating shifts (known as the Xxxxx Schedule). Shift duration shall be 24.25 hours beginning at 0700 hours and ending at 0715 hours the next day. This shall mean a typical work schedule of one on, one off, one on, one off, one on, four off, on a continuous basis. UAF Local 1324 Unit Members’ timesheets will reflect all hours worked by UAF Local 1324 Unit Members within biweekly payroll periods, except for shift trades governed by Article 6.4.5. All hours worked by UAF Local 1324 Unit Members in excess of 106 hours per 14 day work cycle shall be paid at the overtime rate. This schedule is referred to in this Agreement as the "Suppression Schedule."
AutoNDA by SimpleDocs
Suppression Schedule. 1. The regular work schedule for the suppression Members covered by this Agreement shall be a 3 platoon (48/96) tour system; 48 hours on, with 96 hours off duty, will be a tour. The regular work schedule for the Battalion Chief supervising a shift shall be 48.5 hours on, with 95.5 hours off duty between tours. If more than one Battalion Chief is assigned to a shift, additional Battalion Chief(s) shall only be paid for a maximum 48 hours per shift. The City will maintain records of all hours worked by Members within 24-day work cycles, except for standby time, which is governed by Section
Suppression Schedule. The regular work schedule for UAF Local 1324 bargaining unit members working a suppression schedule shall be approximately fifty-six (56) hours per week on alternating shifts (known as forty-eight/ninety-six (48/96). Shift duration shall be twenty-four (24) hours beginning at 0900 hours and ending at 0900 hours the next day. The typical work schedule will be two consecutive twenty-four (24)-hour shifts (forty-eight (48) hours) on and ninety-six (96) hours off on a continuous basis. UAF Local 1324 bargaining unit members’ timesheets will reflect all hours worked by UAF Local 1324 bargaining unit members within biweekly payroll periods, except for shift trades governed by Article 5.5. All hours worked by UAF Local 1324 bargaining unit members in excess of one hundred and six (106) hours per fourteen (14) day work cycle shall be paid at the overtime rate. This schedule is referred to in this Agreement as the "Suppression Schedule."

Related to Suppression Schedule

  • Evaluation Schedule CLIENT REFERENCES The Tenderer shall provide details of his performance on each of the previous projects listed in the “Relevant Experience” returnable schedule. “Client Reference Scorecards” will be completed by each of the respective Clients for the projects listed in the “Relevant Experience” returnable schedule. The following are to be completed by the Client and Principal Agent and is to be supported in each case by a letter of award and the works completion certificate. Both Client and Principal Agent must sign and stamp the documents, failure to obtain both signatures and stamps will result in no allocation of points. PROJECT NAME and SCOPE OF WORK: Principal agent: ................................................................................................................................. Client: .. ..............................................................................................................................................

  • Construction Schedule The progress schedule of construction of the Project as provided by Developer and approved by District.

  • Implementation Schedule TIME IS OF THE ESSENCE with regard to all dates and time periods set forth and/or incorporated herein. Any material modification or deviation from an approved schedule described in this Agreement shall occur only upon approval of the City and RDA, with any such approvals required to be in writing as an amendment to this Agreement, and which approvals shall not be unreasonably withheld. City shall cooperate and act promptly with respect to any and all permits or approvals necessary for completion of the Project. Notwithstanding the above, this Agreement shall not limit the discretion of the City, or any of its duly appointed and authorized governing bodies, boards or entities, in approving or rejecting any aspect of the Project or improvements contemplated on or about the Property.

  • Preliminary Schedule A preliminary schedule of construction indicating the starting and completion dates of the various stages of the Work, including any information and following any form as may be specified in the Specifications. Once approved by District, this shall become the Construction Schedule. This schedule shall include and identify all tasks that are on the Project’s critical path with a specific determination of the start and completion of each critical path task as well as all Contract milestones and each milestone’s completion date(s) as may be required by the District.

  • Recovery Schedule If the initial schedule or any current updates fail to reflect the Work’s actual plan or method of operation, or a contractual milestone date is more than fifteen (15) days behind, Owner may require that a recovery schedule for completion of the remaining Work be submitted. The Recovery Schedule must be submitted within seven (7) calendar days of Owner’s request. The Recovery Schedule shall describe in detail Construction Contractor’s plan to complete the remaining Work by the required Contract milestone date. The Recovery Schedule submitted shall meet the same requirements as the original Construction Schedule. The narrative submitted with the Recovery Schedule should describe in detail all changes that have been made to meet the Contract milestone dates.

  • Construction Schedules 10.1 Within seven (7) days of the University’s issuance of a purchase order, the Contractor shall submit to the Project Coordinator three (3) copies of a Construction Schedule for this Project. The Schedule shall be in bar chart form and shall include all aspects of the work, the interrelationship of the various trades and the critical path of the job. The schedule shall include a timeline for the submission, review and approval of shop drawings for critical path items and delivery and installation dates for those same critical path, or long lead time items, (such as electrical transformers and elevator). The Schedule shall coincide with the Contractor’s approved Schedule of Values. The Schedule shall indicate a completion date in advance of the date established for Substantial Completion. The Schedule shall be acceptable to the Architect/Engineer and the Project Coordinator. It shall be revised and reissued at the beginning of every month for the duration of the project. This monthly update progress Schedule shall include a summary comparison of the original schedule and the latest updated schedule (previous month) showing all activity description and dates. These comparison schedules shall be in the form of a summary bar chart, an activity listing report and actual to target comparisons. The reports may include critical activities, float time, duration of each activity, dates of each activity and the network logic (including successors and predecessors of each activity). Included with the written report and electronic copy of the schedule submission noting the above referenced requirements. Failure to provide the Architect/Engineer, or the Project Coordinator with an acceptable, revised Schedule, within seven (7) days of the receipt of a written request, may result in the withholding of the Contractor’s monthly progress payments until such a Schedule is received.

  • Amortization Schedule We do not provide an initial amortization schedule at the time of project agreement release but maintain a "Loan Summary Spreadsheet" on our website on the Financial Tab under "Loans". Once your loan is put into billing an amortization schedule will be posted to the same website, with a copy mailed to the Chief Financial Officer the month following project closeout.

  • Flexible Work Schedule A flexible work schedule is any schedule that is not a regular, alternate, 9/80, or 4/10 work schedule and where the employee is not scheduled to work more than 40 hours in the "workweek" as defined in Subsections F. and H., below.

  • PROGRESS SCHEDULE The Contractor, within ten (10) working days of receiving notice of the award of the contract, shall prepare and submit for the State's and Architect's information an estimated progress schedule for the Work. The progress schedule shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

  • Master Schedule At the start of the schematic design phase, the Construction Administrator will be given a copy of the updated DAS initial schedule as described in the pre-design phase. The Construction Administrator will then create its master schedule based on the DAS’ initial schedule. Utilizing CPM-based software, the Construction Administrator will assign a duration and relationship to each task, add or delete tasks, identify the logic of interrelationships and milestones, and perform schedule management activities to identify the project's critical path and timeline. The master schedule shall include all tasks from the pre-design phase through design, construction, and project closeout. Items to be identified during subsequent refinements include milestones for departmental occupancy, shop drawing and Construction Administrator reviews, special support services, mobilization and demobilization, long lead item purchases, and float times.

Time is Money Join Law Insider Premium to draft better contracts faster.