NEPA Documents definition
Examples of NEPA Documents in a sentence
If supplements to the NEPA Documents or additional NEPA Documents are needed following the Agreement Date, the Department will prepare the necessary documentation using data and other information provided by the Developer, and the Department will pay the Developer’s Allocable Costs associated with the preparation of such data and other information.
The Concessionaire shall be responsible for compliance with the terms and conditions of the NEPA Documents, at the Concessionaire’s sole cost and expense.
For a period of 8 years after approval of the final construction voucher DOT&PF shall maintain Final NEPA Documents (Draft ▇▇▇▇, Final ▇▇▇▇, Supplemental ▇▇▇▇, RODs, EAs, FONSIs, CE documentation and determinations), Supporting Materials (documentation supporting the Sec.
At any time after a determination by the applicable federal Governmental Authorities that the Project does not require Additional NEPA Documents, Bizzack may request in writing that the Department pay to it the outstanding Additional Preliminary Work Retainage, and the Department will pay all undisputed amounts within 30 days of receipt of such written request.
Buyer agrees to accept the Assets subject to the terms of the NEPA documents as they exist now and in the future, and agrees that the NEPA Documents and their effect on operations will not be the basis for an Environmental Defect, Title Defect or other claim by Buyer.
Both parties acknowledge that the amount of time for the applicable federal Governmental Authorities to make a determination whether the Project requires Additional NEPA Documents following any NEPA reevaluation is beyond either party’s complete control.
The Department will not be financially responsible for any delays to the Project because of the applicable federal Governmental Authorities’ failure to make a timely determination whether the Project requires Additional NEPA Documents.
If supplements to the NEPA Documents or additional NEPA Documents are needed following the Agreement Date, the Department will prepare the necessary documentation using data and other information provided by the Developer.
The purpose of Amendment No. 2 is to allow Bizzack to undertake the Additional Preliminary Work before the date of notice from the applicable federal Governmental Authorities regarding whether the Project requires Additional NEPA Documents following the ongoing NEPA reevaluation for the Project (the “NEPA Reevaluation Outcome Date”).
For a period of 8 years after approval of the final construction voucher ADOT shall maintain Final NEPA Documents (Draft ▇▇▇▇, Final ▇▇▇▇, Supplemental ▇▇▇▇, RODs, EAs, FONSIs, CE documentation and determinations), supporting materials documentation supporting the Sec.