Estimating Assumptions. Section 1 Estimate 4 site visits. • One site visits for project reconnaissance. • One site visit for wall inspection (Hrs. in Section 2). • One site visit for environmental screens (Hrs. in Section 4) • One site visit for utility coordination.
Estimate 2 meetings during the life of this agreement (not included elsewhere). • Two meetings with the Village to discuss alternatives.
Estimating Assumptions. The following assumptions have been made for estimating purposes: Section 1
Estimating Assumptions. The following assumptions have been made for estimating purposes: Section 1 Estimate 4 meetings during the life of this agreement. Estimate 24 cost and progress reporting periods will occur during the life of this agreement.
Estimating Assumptions. The following assumptions have been made for estimating purposes:
Section 1 Estimate 8 meetings during the life of this agreement. Assume 4 hours per meeting.
Estimating Assumptions. Section 1 Estimate 12 meetings during the life of this agreement (hours in Section 8). • 1 Preconstruction meeting • 10 construction meetings (2 meetings/month for 5-month construction duration) • 1 Final walk through Estimate 6 cost and progress reporting periods will occur during the life of this agreement.
Estimating Assumptions. Section 1 Estimate 4 site visits. • Two site visits for project reconnaissance. • One site visit for environmental screens (Hrs. in Section 4) • One site visit for utility coordination. Estimate 5 meetings during the life of this agreement (not included elsewhere). • One meeting with the Town to discuss bridge alternatives. • Three meetings with the Town for project updates • One meeting with NYSDOT. Estimate 36 cost and progress reporting periods will occur during the life of this agreement.
Section 2 Estimate 0 day of Supplemental Survey and associated mapping updates. Estimate 0 accidents will require analysis. Estimate 0 capacity analysis will be required. Estimate 0 soil borings will be taken.
Section 3 Estimate 2 concepts will be evaluated. Estimate 1 bridge will be rehabilitated.
Estimating Assumptions. The following assumptions have been made for estimating purposes:
Section 1 Estimate 9 additional meetings during the life of this agreement. Estimate 28 additional cost and progress reporting periods will occur during the life of this agreement. Estimate 1 additional subcontractor contact/coordination.
Section 2 Estimate 1 other additional project will be designed concurrently immediately adjacent to the project and require additional coordination.
Section 3 Estimate 1 additional concept will be evaluated. Estimate 1 additional design alternative will be analyzed.
Section 4 Estimate Phase 1A/B Cultural Resources Survey will be required. Section 6 Detailed Design or Final Design Final Design will include but not be limited to: • Development of highway and bridge plans. • Structural rehabilitation design. • Highway & Drainage design. • Preparation of right-of-way plans and acquisition maps. • Development and design for public utilities. • Maintenance and protection of traffic during construction. • Preparation and submission of final Plans, Specifications, and Estimate (PS&E) for the project. Estimate 1 cost estimate(s) plus 1 update will be required. Estimate 1 bridges will be replaced and 0 will be rehabilitated.
Estimating Assumptions. The following assumptions have been made for estimating purposes:
Section 1 Estimate Six (6) meetings during the life of this Agreement, in addition to routine progress meetings held on-site and attended by the Resident Engineer.
Estimating Assumptions. The following assumptions have been made for estimating purposes:
Section 1 Estimate four (4) meetings with the City during the design phase of this project. (excludes Public Information Meeting.) Estimate twelve (12) cost and progress reporting periods will occur during the design tasks of this agreement.
Section 2 Assume that GPS methods and equipment will be used to establish vertical control points. The project will be on State Plane Coordinate System. The vertical datum will be based on USGS elevations (NAVD 88) (benchmark or map spot elevation). Estimate 0 accidents will require analysis.
Estimating Assumptions. The following assumptions have been made for estimating purposes: Section 1 - General:
1. Estimate 8 meetings during the life of this agreement. Six (6) meetings in person and two (2) meetings with NYSDOT.
2. Estimate 12 cost and progress reporting periods will occur during the life of this agreement.
1. Assume that GPS methods and equipment will be used to establish local control points
2. Estimate 0 crashes will require analysis
3. Estimate 0 capacity analyses will be required
4. Estimate 6 soil borings will be taken Section 3 - Preliminary Design
1. Estimate 1 public meeting during life of this agreement
2. Estimate 1 concepts will be evaluated
3. Estimate 1 design alternative(s) will be analyzed in addition to the null alternative
4. Estimate 2 cost estimate(s) plus 2 updates will be required 5. Estimate 0 bridges will be rehabilitated Section 4 - Environmental
1. Estimate 0 permits will be required
1. Estimate 3 properties will require title searches
2. Estimate 3 ROW maps will be required
3. Estimate 3 property acquisitions will be required Section 6 – Detailed Design
1. Estimate 2 cost estimate(s) plus 1 updates will be required
2. Estimate 0 bridges will be replaced and 0 will be rehabilitated
3. Estimate 5 utility companies (electric, gas, telephone, cable television, fiber) and 0 railroad agencies will be affected
1. Estimate 0 USB Drives containing PDF’s of the final contract bid documents will be needed for prospective bidders, materials to be supplied electronically
2. Estimate advertisements will be placed in 1 publications in addition to the NYS Contract Reporter Section 8 – Construction Support – (To be added by supplemental)