Monitoring and Supervision during Implementation Sample Clauses

Monitoring and Supervision during Implementation. During the Implementation Period, the Concessionaire shall furnish to the Project Steering Committee monthly reports on actual progress of the Construction Works and furnish any other relevant information as may reasonably be required by the Project Steering Committee. For the purposes of determining that Construction Works are being undertaken in accordance with Specifications and Standards and Good Industry Practice and for quality assurance, the Concessionaire shall carry out such Tests at such time and frequency and in such manner as may be required by the Project Steering Committee or as may be necessary in accordance with Good Industry Practice. The Concessionaire shall with due diligence carry out all such Tests in accordance with the instructions and under the supervision of the Project Steering Committee. The Concessionaire shall promptly carry out such remedial measures as may be necessary to cure the defects or deficiencies, if any, indicated in such Test results. If the Project Steering Committee reasonably determines that the rate of progress of the construction of the Project is such that the achievement of COD is not feasible on or before the Scheduled Project Completion Date, it shall so notify the Concessionaire. Thereupon, the Concessionaire shall within 15 (fifteen) days thereof notify the Project Steering Committee about the steps it proposes to take to expedite progress and the period within which it shall achieve COD. The Project Steering Committee may, by written notice, require the Concessionaire to suspend forthwith the whole or any part of the Construction Works if in the reasonable opinion of the Project Steering Committee such work is being carried on in a manner which threatens the safety of the Construction Works or the users of the Project or does not adhere to Specifications and Standards. The Concessionaire shall upon, instructions of the Project Steering Committee pursuant to sub-clause (d) above suspend the Construction Works or any part thereof as the case may be, for such time and in such manner as may be specified by Project Steering Committee and the costs if any incurred by DUSIB during such suspension to properly protect and secure the Construction Works or such part thereof as is necessary in the opinion of the Project Steering Committee (“Preservation Costs”), shall be borne by the Concessionaire. If the Project Steering Committee issues any instructions requiring suspension of Construction Works for any reason ot...
AutoNDA by SimpleDocs
Monitoring and Supervision during Implementation a) The Concessionaire shall submit to the DTIDCL Engineer, a programme supported with BAR Chart for construction of the Bus Shelters at the 1397 Project Sites (Consisting of 4 distinct zones i.e. Xxxx-0, Xxxx-0, Xxxx-0 & Zone-4) in a phased manner so as to cause least inconvenience to the public. Most of the construction and improvement work shall be carried out during night hours/restricted hours (leaving peak traffic time) keeping in view the safety of pedestrian/traffic. The Concessionaire shall give to the DTIDCL Engineer, its complete programme for different stages of execution, planning, designing, fabrication, and erection etc. of the Project. b) During the Implementation Period, the Concessioanire shall furnish to DTIDCL monthly reports on actual progress of the Construction Works and furnish any other relevant information as may reasonably be required by DTIDCL. c) For the purposes of determining that the work is being undertaken in accordance with Specifications and Standards and Good Industry Practice and for quality assurance, the Concessionaire shall carry out such Tests at such time and frequency and in such manner as may be required by the DTIDCL Engineer or as may be necessary in accordance with
Monitoring and Supervision during Implementation. (a) The Concessionaire shall submit to the Engineer-in-Charge, a programme supported with Bar Chart for construction of the Bus Shelters in a phased manner so as to cause least inconvenience to the public. Most of the construction work shall be carried out during night hours/ restricted hours (leaving peak traffic time) keeping in view the safety of pedestrian/traffic. The Concessionaire shall give to the Engineer-in-Charge, its complete programme for different stages of execution, planning, fabrication, and erection etc. of the Project. During the Implementation Period, the Concessionaire shall furnish to ITEL monthly reports on actual progress of the Construction Works and furnish any other relevant information as may reasonably be required by ITEL.

Related to Monitoring and Supervision during Implementation

  • Monitoring and Review The Provider agrees to allow access to the Department for purposes of monitoring and review. This access includes but is not limited to client records, fiscal records, staffing records, policy and procedural manuals, facilities, staff, and children in care of the Department. The Department will conduct quality reviews, which may include site-based quality review visits.

  • Program Monitoring and Evaluation The Recipient shall prepare, or cause to be prepared, and furnish to the Association not later than six months after the Closing Date, a report of such scope and in such detail as the Association shall reasonably request, on the execution of the Program, the performance by the Recipient and the Association of their respective obligations under the Legal Agreements and the accomplishment of the purposes of the Financing.”

  • Project Implementation Manual The Recipient, through the PCU, shall: (i) take all action required to carry out Parts 1.1, 1.3, 1.4, 2, 3.1(b), 3.2, 3.3 and 4 (ii) of the Project in accordance with the provisions and requirements set forth or referred to in the Project Implementation Manual; (ii) submit recommendations to the Association for its consideration for changes and updates of the Project Implementation Manual as they may become necessary or advisable during Project implementation in order to achieve the objective of Parts 1.1, 1.3, 1.4, 2, 3.1(b), 3.2, 3.3 and 4(ii) of the Project; and (iii) not assign, amend, abrogate or waive the Project Implementation Manual or any of its provisions without the Association’s prior agreement. Notwithstanding the foregoing, if any of the provisions of the Project Implementation Manual is inconsistent with the provisions of this Agreement, the provisions of this Agreement shall prevail and govern.

  • Evaluation, Testing, and Monitoring 1. The System Agency may review, test, evaluate and monitor Grantee’s Products and services, as well as associated documentation and technical support for compliance with the Accessibility Standards. Review, testing, evaluation and monitoring may be conducted before and after the award of a contract. Testing and monitoring may include user acceptance testing. Neither the review, testing (including acceptance testing), evaluation or monitoring of any Product or service, nor the absence of review, testing, evaluation or monitoring, will result in a waiver of the State’s right to contest the Grantee’s assertion of compliance with the Accessibility Standards. 2. Grantee agrees to cooperate fully and provide the System Agency and its representatives timely access to Products, records, and other items and information needed to conduct such review, evaluation, testing, and monitoring.

  • CONTRACTOR SUPERVISION Contractor shall provide competent supervision of personnel employed on the job Site, use of equipment, and quality of workmanship.

  • Implementation and Review The Parties shall consult annually, or as otherwise agreed, to review the implementation of this Chapter and consider other matters of mutual interest affecting trade in services. (10) 10 Such consultations will be addressed under Article 170 (Free Trade Commission) of Chapter 14 (Administration of the Agreement).

  • Construction Phase Services 3.1.1 – Basic Construction Services

  • SITE SUPERVISION 1.9.1 Contractor shall provide adequate supervision of his employees to ensure complete and satisfactory performance of all work in accordance with the terms of the contract. Contractor shall have a responsible supervisor on the job at all times when the work of the contract is being carried out. 1.9.2 Contractor's site supervisor shall be responsible for communication with the State's representatives and shall meet with the Project Manager at the site on a weekly basis to discuss project status, including any problems, ideas, or concerns related to the project work. 1.9.3 Contractor and its employees shall be subject to all applicable State and Federal statutes and regulations for the conduct of personnel. 1.9.4 The Contractor shall provide adequate supervision of his/her subcontractors and their employees at all times.

  • SUPERVISION AND CONSTRUCTION PROCEDURES 4.3.1 The Contractor shall supervise and direct the Work, using his / her best skill and attention. The Contractor shall be solely responsible for all construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract. All aspects of the Project shall be subject to the inspection and approval of the State. Contractor guarantees to repair, replace, re-execute or otherwise correct any defect in workmanship, materials, or the like that fails to conform to the requirements of this Contract or that appears during the progress of the Work or within one year of final acceptance by the State. 4.3.2 The Contractor shall be responsible to the State for the acts and omissions of his / her employees, Subcontractors and their agents and employees, and other persons performing any of the Work under a contract with the Contractor. 4.3.3 The Contractor shall not be relieved from his / her obligations to perform the Work in accordance with the Contract Documents either by the activities or duties of the Architect in his / her administration of the Contract, or by inspections, tests or approvals required or performed under Paragraph 7.7 by persons other than the Contractor. 4.3.4 The Contractor shall acquaint himself (herself / itself) with the limits of the property or right- of-way of the State and shall not trespass on other property. The Contractor shall adequately protect the project, adjacent property and the public, and shall be responsible for any damage or injury due to the Contractor’s act or neglect, and shall save the State harmless in respect thereto. 4.3.5 All work shall be done in such a manner as not to interfere with the State’s operating functions. Contractor and his employees shall familiarize themselves and comply with all rules and regulations applicable to the project. 4.3.6 The Contractor shall keep the premises free from liens arising out of or from the Project. Contractor shall obtain and submit waivers of liens with a request for a progress or final payment.

  • Commercial Operation Date Testing and Modifications Prior to the Commercial Operation Date, the Connecting Transmission Owner shall test the Connecting Transmission Owner’s Attachment Facilities and System Upgrade Facilities and System Deliverability Upgrades and Developer shall test the Large Generating Facility and the Developer Attachment Facilities to ensure their safe and reliable operation. Similar testing may be required after initial operation. Developer and Connecting Transmission Owner shall each make any modifications to its facilities that are found to be necessary as a result of such testing. Developer shall bear the cost of all such testing and modifications. Developer shall generate test energy at the Large Generating Facility only if it has arranged for the injection of such test energy in accordance with NYISO procedures.