Multiple Completion Times Sample Clauses

Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, Construction Manager shall organize and perform its services as appropriate to each stage. Each stage of the Project may have a unique schedule for completion and a specific Construction Cost Limitation, at Owner’s discretion. Attend and participate in Owner’s “Partnering” Program for all phases of the Project. Construction Manager shall identify to the Owner the employees and other personnel that it will assign to the Project and provide the Monthly Salary Rate for each of them. Construction Manager shall also identify any consultants that will be performing services for the Project. After execution of this Agreement by the Owner, Construction Manager shall not add, remove or replace the persons or entities assigned to the Project except with the Owner’s written consent, which consent shall not be unreasonably withheld. Construction Manager shall not assign to the Project or contract with any person or entity to which Owner has a reasonable objection. Construction Manager shall promptly update and resubmit Exhibit F, CM’s Personnel and Monthly Salary Rates form, indicating the list of persons by name and title and consultants if they change during the course of the Project. Construction Manager’s employees and other personnel that it assigns to the project shall be identified on the Schedule of Values by name and title. The Owner’s Policy on the Utilization of Historically Underutilized Businesses (“Policy”) is described in an attached exhibit. Construction Manager, as a provision of the Agreement, must comply with the requirements of the Policy and adhere to the HUB Subcontracting Plans submitted for Pre-Construction Phase and Construction Phase Services. No changes to the HUB Subcontracting Plans can be made by the Construction Manager without the written approval of Owner in accordance with the Policy.
AutoNDA by SimpleDocs
Multiple Completion Times. Cooperate fully if Owner decides to “Fast Track” and establish Multiple Completion Times. If the Owner elects these approaches, CM shall organize and perform its services to be most appropriate and efficient for each stage of Project development. In these circumstances, each stage of the Project may have a unique schedule for completion and a separate specific Construction Cost Limitation as negotiated between the two parties.
Multiple Completion Times. Cooperate fully if Owner decides to “Fast Track” and establish “Multiple Completion Times”. If the Owner elects these approaches, Contractor shall organize and perform its services to be most appropriate and efficient for each stage of Project development. In these circumstances, each stage of the Project may have a unique schedule for completion and a separate specific cost as agreed to in writing by the Contractor and Owner.
Multiple Completion Times. CMR agrees to timely deliver the services described in this Agreement whether the Project is to be completed as a single package or in multiple combinations of packages. CMR will cooperate fully if TFC decides to “Fast Track” and establish multiple completion dates. If TFC elects these approaches, CMR shall organize and perform its services to be most appropriate and efficient for each stage of Project development. In these circumstances, each stage of the Project may have a unique schedule for completion and specific cost limitations agreed to in writing by the CMR and TFC.
Multiple Completion Times. DB agrees to timely deliver the services described in this Agreement whether the Project is to be completed as a single package or in multiple combinations of packages. DB will cooperate fully if TFC decides to “Fast Track” and establish multiple completion dates. If TFC elects these approaches, DB shall organize and perform its services to be most appropriate and efficient for each stage of Project development. In these circumstances, each stage of the Project may have a unique schedule for completion and specific cost limitations agreed to in writing by the DB and TFC.
Multiple Completion Times. If the Owner elects to “fast-track” or develop the Project in multiple stages, the Design/Build Contractor shall cooperate fully with the Owner and organize and perform its services to be most appropriate and efficient for each stage. Each stage of the Project may have a unique schedule for completion and a specific CCL, at Owner’s discretion.