Progress Reports and Reviews Sample Clauses

Progress Reports and Reviews. (a) The Borrower shall prepare, under terms of reference satisfactory to the Association, and furnish to the Association, semi-annually beginning on or about the date six (6) months after the Effective Date, a report integrating the results of the monitoring and evaluation activities performed pursuant to Paragraph 1 of this Section, on the progress achieved in the carrying out of the Project during the period preceding the date of said report and setting out the measures recommended to ensure the efficient carrying out of the Project and the achievement of the objectives thereof during the period following such date.
AutoNDA by SimpleDocs
Progress Reports and Reviews. (a) DLC shall prepare, in conjunction with the Recipient, under terms of reference satisfactory to the Association, and furnish to the Association, annually beginning on or about the date twenty four (24) months after the Effective Date, a report integrating the results of the monitoring and evaluation activities performed pursuant to paragraph 1 of this Section, on the progress achieved in the carrying out of Part B of the Project during the period preceding the date of said report, and a draft work program and related budget, including the measures recommended to ensure the efficient carrying out of Part B of the Project and the achievement of the objectives thereof during the twelve months’ period following such date.
Progress Reports and Reviews. (a) Madarail shall prepare, in conjunction with the Borrower, under terms of reference satisfactory to the Association, and furnish to the Association, on or about April 30 of each year, a report integrating the results of the monitoring and evaluation activities performed pursuant to paragraph 1 of this Section, on the progress achieved in the carrying out of the Project during the period preceding the date of said report and setting out the measures recommended to ensure the efficient carrying out of the Project and the achievement of the objective thereof during the period following such date; and
Progress Reports and Reviews. (a) The Recipient shall prepare, under terms of reference satisfactory to the Association, and furnish to the Association, on a annual basis until the completion of the Project, for the first time fifteen months following the Effectiveness Date, or at such other date as the Recipient and the Association shall agree upon, a report integrating the results of the monitoring and evaluation activities performed pursuant to paragraph 1 of this Section, on the progress achieved in the carrying out of the Project during the period preceding the date of said report and setting out the measures recommended to ensure the efficient carrying out of the Project and the achievement of the objectives thereof during the period following such date.

Related to Progress Reports and Reviews

  • Progress Reports The Recipient shall submit to the OPWC, at the OPWC's request, summary reports detailing the progress of the Project pursuant to this Agreement and any additional reports containing such information as the OPWC may reasonably require.

  • Progress Reports and Invoices The goals of this subtask are to: (1) periodically verify that satisfactory and continued progress is made towards achieving the project objectives of this Agreement; and (2) ensure that invoices contain all required information and are submitted in the appropriate format. The Recipient shall: • Submit a monthly Progress Report to the CAM. Each progress report must: o Summarize progress made on all Agreement activities as specified in the scope of work for the preceding month, including accomplishments, problems, milestones, products, schedule, fiscal status, and an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. See the Progress Report Format Attachment for the recommended specifications. • Submit a monthly or quarterly Invoice that follows the instructions in the “Payment of Funds” section of the terms and conditions, including a financial report on Match Fund and in-state expenditures. Products: • Progress Reports • Invoices

  • Progress Report 10.1 If required, you shall submit progress reports in connection with the Service (“Report”) on at least a monthly basis, or as we may require. The Report shall include a summary of the activities and accomplishments during the previous reporting period.

  • Progress Reporting 5. The IP will submit to UNICEF narrative progress reports against the planned activities contained in the Programme Document, using the PDPR. Unless otherwise agreed between the Parties in writing, these reports will be submitted at the end of every Quarter. The final report will be submitted no later than thirty (30) calendar days after the end the Programme and will be provided together with the FACE form.

  • Progress Reports and Information When required, the Contractor shall submit to the Owner such schedule of quantities and costs, payrolls, bills, vouchers, correct copies of all subcontracts, statements, reports, correct copies of all agreements, correspondence, and written transactions with the surety on the performance bond that have any relevance to the Work, estimates, records, and other data as the Owner may request that concerns the Work performed or to be performed under this Contract. When requested by the Owner, the Contractor shall give the Owner access to its records relating to the foregoing. (See also Article 1.2.3, Audits.) The above reports shall include, but are not limited to, (a) written notice of dates by which specified Work will have been completed, (b) written notice of dates by which Non-Compliant Work will be made good, (c) written notice that Non-Compliant Work has been made good, (d) written notice as to the date or dates by which Work that has not been performed with equal steps and at the same rate required by the Overall Project Schedule shall have been brought into conformity with the Overall Project Schedule, (e) date by which any undisputed claim of a Subcontractor, Supplier, or laborer shall have been paid, (f) written advice regarding the nature and amount of any disputed claim of a Subcontractor, Supplier, or laborer, and (g) information regarding Work performed under Change Orders.

  • Project Reports 1. The Borrower shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 5.08 of the General Conditions and on the basis of the indicators agreed with the Bank. Each Project Report shall cover the period of one calendar semester, and shall be furnished to the Bank not later than one month after the end of the period covered by such report.

  • Quarterly Progress Reports The goal of this task is to periodically verify that satisfactory and continued progress is made towards achieving the objectives of this Agreement on time and within budget. The objectives of this task are to summarize activities performed during the reporting period, to identify activities planned for the next reporting period, to identify issues that may affect performance and expenditures, and to form the basis for determining whether invoices are consistent with work performed. The Recipient shall: • Prepare a Quarterly Progress Report which summarizes all Agreement activities conducted by the Recipient for the reporting period, including an assessment of the ability to complete the Agreement within the current budget and any anticipated cost overruns. Progress reports are due to the CAM the 10th day of each January, April, July, and October. The Quarterly Progress Report template can be found on the ECAMS Resources webpage available at xxxxx://xxx.xxxxxx.xx.xxx/media/4691. Product: • Quarterly Progress Reports

  • Evaluation Reports Where a formal evaluation of an employee's performance is carried out, the employee shall be provided with a copy to read and review. Provision shall be made on the evaluation form for an employee to sign it. The form shall provide for the employee's signature in two (2) places, one indicating that the employee has read and accepts the evaluation, and the other indicating that the employee disagrees with the evaluation. The employee shall sign in one of the places provided within seven (7) calendar days. No employee may initiate a grievance regarding the contents of an evaluation report unless the signature indicates disagreement with the evaluation. The employee shall receive a copy of the evaluation report at the time of signing. An evaluation report shall not be changed after an employee has signed it, without the knowledge of the employee, and any such changes shall be subject to the grievance procedure.

  • Monthly Progress Reports During the Construction Period, the Concessionaire shall, no later than 7 (seven) days after the close of each month, furnish to the Authority and the Independent Engineer a monthly report on progress of the Construction Works and shall promptly give such other relevant information as may be required by the Independent Engineer.

  • Project Reports; Completion Report 1. The Recipient shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 2.06 of the Standard Conditions and on the basis of indicators agreed with the World Bank. Each Project Report shall cover the period of one (1) calendar semester, and shall be furnished to the World Bank not later than one (1) month after the end of the period covered by such report.