Review of Applications Sample Clauses

Review of Applications. A. Within 10 days after receipt of each application for payment, the Engineer will either indicate in writing a recommendation for payment and present the application for payment to Owner or return the application for payment to Contractor indicating in writing Engineer’s reasons for refusing to recommend payment. The Contractor will make the necessary corrections and resubmit the application for payment. B. Engineer will recommend reductions in payment (set-offs) which, in the opinion of the Engineer, are necessary to protect Owner from loss because the Work is defective and requires correction or replacement. C. The Owner is entitled to impose set-offs against payment based on any claims that have been made against Owner on account of Contractor’s conduct in the performance of the Work, incurred costs, losses, or damages on account of Contractor’s conduct in the performance of the Work, or liquidated damages that have accrued as a result of Contractor’s failure to complete the Work.
Review of Applications. 1. Engineer will, within 10 days after receipt of each Application for Payment, including each resubmittal, either indicate in writing a recommendation of payment and present the Application to Owner, or return the Application to Contractor indicating in writing Engineer’s reasons for refusing to recommend payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. Engineer’s recommendation of any payment requested in an Application for Payment will constitute a representation by Engineer to Owner, based on Engineer’s observations of the executed Work as an experienced and qualified design professional, and on Engineer’s review of the Application for Payment and the accompanying data and schedules, that to the best of Engineer’s knowledge, information and belief: a. the Work has progressed to the point indicated; b. the quality of the Work is generally in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning whole prior to or upon Substantial Completion, the results of any subsequent tests called for in the Contract Documents, a final determination of quantities and classifications for Unit Price Work under Paragraph 13.03, and any other qualifications stated in the recommendation); and c. the conditions precedent to Contractor’s being entitled to such payment appear to have been fulfilled in so far as it is Engineer’s responsibility to observe the Work. 3. By recommending any such payment Engineer will not thereby be deemed to have represented that: a. inspections made to check the quality or the quantity of the Work as it has been performed have been exhaustive, extended to every aspect of the Work in progress, or involved detailed inspections of the Work beyond the responsibilities specifically assigned to Engineer in the Contract; or b. there may not be other matters or issues between the parties that might entitle Contractor to be paid additionally by Owner or entitle Owner to withhold payment to Contractor. 4. Neither Engineer’s review of Contractor’s Work for the purposes of recommending payments nor Engineer’s recommendation of any payment, including final payment, will impose responsibility on Engineer: a. to supervise, direct, or control the Work; b. for the means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto; c. for Contractor’s failure to comply with Laws and Regulations applicable to ...
Review of Applications. Contractor shall review with Customer any application Contractor makes to any government department, agency, or entity for any approval, permit, license, or agreement, as may be required for performance of the Work, prior to submission of such application. Contractor shall provide Customer a minimum of three (3) Business Days to review such application prior to submission to such governmental entity, and Contractor shall in good faith consider any comments and proposed revisions made by Customer for incorporation into such application. Customer shall reasonably cooperate with Contractor in Contractor's efforts to procure all such approvals, permits, licenses, and agreements.
Review of Applications. 1. ENGINEER will, within 10 days after receipt of each Application for Payment, either indicate in writing a recommendation of payment and present the Application to OWNER or return the Application to CONTRACTOR indicating in writing ENGINEER’s reasons for refusing to recommend payment. In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application. 2. ENGINEER’s recommendation of any payment requested in an Application for Payment will constitute a representation by ENGINEER to OWNER, based on ENGINEER’s observations on the Site of the executed Work as an experienced and qualified design professional and on ENGINEER's review of the Application for Payment and the accompanying data and schedules, that to the best of ENGINEER’s knowledge, information and belief:
Review of Applications. (a) Contractor shall review with Customer any application relating to import or export that Contractor makes to any government department, agency, or entity for any approval, permit, license, or agreement, as may be required for performance of the Work, prior to submission of such application. Contractor shall provide Customer a minimum of [**Redacted**] to review such application prior to submission to such governmental entity, and Contractor shall in good faith consider and accommodate any comments and proposed revisions made by Customer for incorporation into such application. (b) Customer shall reasonably cooperate with Contractor in Contractor’s efforts to procure all such approvals, permits, licenses, and agreements.
Review of Applications. The TNRCC shall be responsible for the administrative review of all wastewater and storm water discharge permit applications within the TNRCC's jurisdiction. TNRCC will make completeness determinations and inform permittees of their application status, and that application information will be coded into PCS.
Review of Applications. 1. City will, after receipt of each Application for Payment, either indicate in writing a recommendation of payment or return the Application to Contractor indicating reasons for refusing payment. In the latter case, Contractor may make the necessary corrections and resubmit the Application. 2. City’s processing of any payment requested in an Application for Payment will be based on City’s observations of the executed Work, and on City’s review of the Application for Payment and the accompanying data and schedules, that to the best of City’s knowledge:
Review of Applications. Upon receipt of the Classification/Reclassification application, the committee shall complete a review of the application and render a decision in writing to the employee.
Review of Applications. Review of applications will occur in three rounds before being invited to participate in Finals during 43North Week. 43North Week will run from October24, 2021 to October 29, 2021. Applicants must fill out, complete and submit a written application, including uploaded business documentation, via the 43North website. In the first round, 43North working in collaboration with its panels of judges (the “Committee”) will select promising applications from the pool of applicants by July 19 at Noon EST, 2021. Such selections shall be made in the sole and absolute discretion of 43North working with the Committee. 43North shall be entitled to begin conducting background checks during the first round on applicants who are identified as semifinalists and may request the consent of applicants for these checks.
Review of Applications. Owner’s Representative will, within 10 calendar days after receipt of each Application for Payment, either indicate in writing a recommendation of payment and present the Application to OWNER or return the Application to CONTRACTOR indicating in writing Owner’s Representative’s reasons for refusing to recommend payment. In the latter case, CONTRACTOR may make the necessary corrections and resubmit the Application.