Suspension by the Owner for Convenience. 11.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
11.3.2 The Contract Price and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Paragraph 11.
3.1. Adjustment of the Contract Price shall include profit. No adjustment shall be made to the extent:
11.3.2.1 that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or
11.3.2.2 that an equitable adjustment is made or denied under another provision of the Agreement.
Suspension by the Owner for Convenience. § 13.2.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 13.2.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 13.2.
Suspension by the Owner for Convenience. 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
14.3.2 Adjustments made in the cost of performance may have a mutually agreed fixed or percentage fee.
Suspension by the Owner for Convenience. A.
14.3.1 The Owner may, without cause, order the Design-Builder in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1.
Suspension by the Owner for Convenience. The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work, in whole or in part for such period of time as the Owner may determine.
Suspension by the Owner for Convenience. 12.3.1. Owner’s Right to Suspend 12.3.2. Cost and Time Modifications
Suspension by the Owner for Convenience. 11.4.1 The Owner may order the Contractor in writing to suspend, delay or interrupt all or any part of the Work without cause for such period of time as the Owner may determine to be appropriate for its convenience.
11.4.2 Adjustments caused by suspension, delay or interruption shall be made for increases in the Contract Price and/or the date of Substantial Completion. No adjustment shall be made if the Contractor is or otherwise would have been responsible for the suspension, delay or interruption of the Work, or if another provision of this Agreement is applied to render an equitable adjustment.
Suspension by the Owner for Convenience. § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine.
§ 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by suspension, delay or interruption as described in Section 14.3.1. No adjustment shall be made to the extent .1 that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or .2 that an equitable adjustment is made or denied under another provision of the Contract.
Suspension by the Owner for Convenience. (a) Owner may, without cause, order Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as Owner may determine. Any such suspension of the Work shall entitle Contractor to a Change Order pursuant to Article 9.
(b) Owner shall continue to meet the payment obligations to Contractor during any suspension, delay or interruption for Work actually performed.
(c) During any suspension, Contractor shall take reasonable precautions to protect, store and secure the Equipment against deterioration, loss or damage and to minimize the charges for the suspension.
(d) Contractor shall resume any suspended Work promptly following receipt of notice from Owner to do so. “[**]” in this Exhibit 10.01 indicates material that has been omitted pursuant to a request for confidential treatment and filed separately with the Securities and Exchange Commission. Execution Version Confidential Trade Secret Information—Subject to Restricted Procedures