Project Force Majeure Event definition

Project Force Majeure Event has the meaning given in clause 9.1 (“Definition of Project Force Majeure Event”).
Project Force Majeure Event has the meaning given in clause 19.1 (“Definition of Project Force Majeure Event”).
Project Force Majeure Event is an event or circumstance, or combination of events or circumstances, occurring after the Signing Date that:

Examples of Project Force Majeure Event in a sentence

  • Any suspension of obligations pursuant to clause 19.4 (“Suspension of obligations”) will not affect any rights or obligations which may have accrued prior to the suspension or, if the Project Force Majeure Event affects only some obligations, any other rights or obligations of LTES Operator.

  • If there is no Project Force Majeure Event affecting the Trading Interval, then PFME Generation is deemed to be zero; and MLFTI = the Marginal Loss Factor for the Trading Interval.

  • The “PFME Generation” for a Trading Interval is an amount (in MWh) equal to Sent Out Generation that would have been generated during that Trading Interval but for a Project Force Majeure Event (and, for the purposes of this clause only, Project Operator will not be taken to have caused any curtailment or congestion affecting the availability of the Network by virtue of the Project dispatching electricity to the Network).

  • Any suspension of obligations pursuant to clause 19.4 (“Suspension of obligations”) will not affect any rights or obligations which may have accrued prior to the suspension or, if the Project Force Majeure Event affects only some obligations, any other rights or obligations of Project Operator.

  • Accrued rights and obligations Any suspension of obligations pursuant to clause 19.4 (“Suspension of obligations”) will not affect any rights or obligations that may have accrued prior to the suspension or, if the Project Force Majeure Event affects only some obligations, any other rights or obligations of Project Operator.

  • The Milestone Dates may be extended for any delay caused by a Project Force Majeure Event, provided that FC Sunset Date may not be extended beyond the date that is 18 months after the FC Sunset Date set out in clause 7(b).

  • If the performance by Project Operator or its obligation under this agreement or the operation of the Project are adversely affected by a Project Force Majeure Event on or after the Commercial Operations Date, then Project Operator must use its best endeavours (including by incurring reasonable costs) to mitigate the effect of that Project Force Majeure Event upon the Project and Project Operator’s performance of its obligations under this agreement as soon as is reasonably practicable.

  • Accrued rights and obligations Any suspension of obligations pursuant to clause 19.4 (“Suspension of obligations”) will not affect any rights or obligations which may have accrued prior to the suspension or, if the Project Force Majeure Event affects only some obligations, any other rights or obligations of Project Operator.

  • Any suspension of obligations pursuant to clause 20.4 (“Suspension of obligations”) will not affect any rights or obligations which may have accrued prior to the suspension or, if the Project Force Majeure Event affects only some obligations, any other rights or obligations of LTES Operator.

  • For the purposes of clause 21.2(a), each of the following does not constitute a Connection Force Majeure Event: a Project Force Majeure Event; and any Change in Law.


More Definitions of Project Force Majeure Event

Project Force Majeure Event is an event or circumstance which is beyond the reasonable control of LTES Operator and could not have prevented by the exercise of reasonable care and good electricity industry practice. (b) Despite paragraph (a), the following events will not constitute a Project Force Majeure Event: (i) lack of funds, financial hardship or inability to obtain financing or insurance by LTES Operator and its related bodies corporate; (ii) shortage of materials and consumables required by LTES Operator except to the extent it is itself caused by a Project Force Majeure Event; (iii) breakdown of property or equipment caused by normal wear and tear; (iv) strikes and industrial disputes that only affect LTES Operator; and (v) lack of solar/wind resources.
Project Force Majeure Event is an event or circumstance, or combination of events or circumstances, occurring after the Signing Date that: is not within the reasonable control of Project Operator; and Project Operator could not have avoided, mitigated, remedied or overcome through the exercise of reasonable care, compliance with its obligations under this agreement and Good Industry Practice, including: a Major Casualty Event; and any curtailment or congestion affecting the availability of the Network, that satisfies the above criteria. For the purposes of paragraph (a), the following do not constitute a Project Force Majeure Event: lack of funds, financial hardship, failure or inability of any person to pay any sum due and payable, or the inability of Project Operator (or any of its Related Bodies Corporate) to obtain financing or insurance or to make a profit or to achieve a satisfactory rate of return; a shortage or delay in delivery of materials, consumables, equipment or utilities required by Project Operator or any failure by Project Operator to hold sufficient stock of spares, except to the extent that such a circumstance is itself caused by a Project Force Majeure Event; a malfunction, temporary unavailability, breakdown or failure of Project Operator’s equipment, property or assets caused by normal wear and tear; any event or circumstance arising due to a failure by Project Operator, any of its Related Bodies Corporate or any of their respective employees, agents or Subcontractors to take reasonable measures to maintain, secure and protect any equipment, property or asset in accordance with Good Industry Practice, except to the extent that such a circumstance is itself caused by a Project Force Majeure Event; strikes, industrial disputes or other industrial actions or disruption that only affect Project Operator or any group of companies of which it is a part; failure by any person (other than the other party to this agreement) to perform an obligation, except when such failure is caused by any event or circumstance that, if such event or circumstance had happened to Project Operator, would have been a Project Force Majeure Event under this agreement; delay in obtaining any Authorisation required to be held by a party to perform its obligations under this agreement; any absence, failure, lack or excess of any Input Resource, at the site of the Project; wet or inclement weather (other than extreme storms, floods, hurricanes, cyclones, tornados, typhoons, tsunamis, ice and ice...

Related to Project Force Majeure Event

  • Force Majeure Event means an event beyond the reasonable control of the Party affected, including, but not limited to, acts of God, embargoes, governmental restrictions, strikes, riots, insurrection, wars or other military action, civil disorders, acts of terrorism, rebellion, fires, explosions, accidents, floods, vandalism, cable cuts and sabotage. Market conditions or fluctuations are not Force Majeure Events.

  • Force Majeure means an event beyond the control of the supplier and not involving the supplier’s fault or negligence and not foreseeable. Such events may include, but is not restricted to, acts of the purchaser in its sovereign capacity, wars or revolutions, fires, floods, epidemics, quarantine restrictions and freight embargoes.

  • Event of Force Majeure means one of the following events:

  • Excusable Delay means a delay due to acts of God, governmental restrictions, stays, judgments, orders, decrees, enemy actions, civil commotion, fire, casualty, strikes, work stoppages, shortages of labor or materials or other causes beyond the reasonable control of Borrower, but lack of funds in and of itself shall not be deemed a cause beyond the control of Borrower.

  • Disaster means a sudden emergency occurrence beyond the control of the licensee, whether natural, technological, or man-made, that renders the licensee unable to operate the facility or makes the facility uninhabitable.