Allowance Items and Allowance Values Sample Clauses

Allowance Items and Allowance Values. 5.6.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Exhibit, which is included within the GMP. 5.6.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. Nothing herein is intended in any way to constitute a guarantee by Design-Builder that the Allowance Item in question can be performed for the Allowance Value. 5.6.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if Design-Builder is not provided written authorization to proceed on an Allowance Item by the date set forth in the Project schedule, due to no fault of Design-Builder, Design-Builder may be entitled to an adjustment of the Contract Time(s) and Contract Sum. 5.6.4 The Allowance Value for an Allowance Item includes the direct cost of labor, materials, equipment, transportation, taxes and insurance associated with the applicable Allowance Item. All other costs, including design fees, Design-Builder’s overall project management and general conditions costs, overhead and fee, are deemed to be included in the original Contract Sum, and are not subject to adjustment, regardless of the actual amount of the Allowance Item. 5.6.5 Whenever the actual costs for an Allowance Item is more than or less than the stated Allowance Value, the Contract Sum shall be adjusted accordingly by Change Order, subject to Section 5.4. The amount of the Change Order shall reflect the difference between actual costs incurred by Design-Builder for the particular Allowance Item and the Allowance Value.
AutoNDA by SimpleDocs
Allowance Items and Allowance Values. 6.4.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Exhibit and are included within the GMP. 6.4.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. 6.4.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. 6.4.4 The Allowance Value for an Allowance Item includes the direct cost of labor, materials, equipment, transportation, taxes and insurance associated with the applicable Allowance Item. All other costs, including design fees, Design-Builder’s overall project management and general conditions costs, overhead and fee, are deemed to be included in the original GMP, and are not subject to adjustment, regardless of the actual amount of the Allowance Item. 6.4.5 Whenever the actual direct costs for an Allowance Item is more than or less than the stated Allowance Value, the GMP shall be adjusted accordingly by Change Order, subject to Section
Allowance Items and Allowance Values. 5.6.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Exhibit, which is included within the GMP. 5.6.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. Nothing herein is intended in any way to constitute a guarantee by Design-Builder that the Allowance Item in question can be performed for the Allowance Value. 5.6.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if Design-Builder is not provided written authorization to proceed on an Allowance Item by the date set forth in the Project schedule, due to no fault of Design-Builder, Design-Builder may be entitled to an adjustment of the Contract Time(s) and Contract Sum.
Allowance Items and Allowance Values. 6.4.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Proposals and are included within the GMP. 6.4.2 XXXX and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. XXXX and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. Nothing herein is intended in any way to constitute a guarantee by XXXX that the Allowance Item in question can be performed for the Allowance Value. 6.4.3 No work shall be performed on any Allowance Item without XXXX first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if XXXX is not provided written authorization to proceed on an Allowance Item by the date set forth in the Project schedule, due to no fault of XXXX, XXXX may be entitled to an adjustment of the Contract Time(s) and Contract Price. 6.4.4 The Allowance Value for an Allowance Item includes the direct cost of labor, materials, equipment, transportation, taxes and insurance associated with the applicable Allowance Item. All other costs, including XXXX’x overall project management and general conditions costs, overhead and fee, are deemed to be included in the original Contract Price, and are not subject to adjustment, regardless of the actual amount of the Allowance Item. 6.4.5 Whenever the actual costs for an Allowance Item is more than or less than the stated Allowance Value, the Contract Price shall be adjusted accordingly by Change Order, subject to Section 6.4.4. The amount of the Change Order shall reflect the difference between actual costs incurred by XXXX for the particular Allowance Item and the Allowance Value.
Allowance Items and Allowance Values. 7.7.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the Contract Price Amendment or the Phase 2 Price Proposal. 7.7.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. Nothing herein is intended in any way to constitute a guarantee by Design-Builder that the Allowance Item in question can be performed for the Allowance Value. 7.7.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if Design-Builder is not provided written authorization to proceed by the date set forth in the Project schedule, due to no fault of Design-Builder, Design-Builder may be entitled to an adjustment of the Contract Time(s) and Contract Price. 7.7.4 The Allowance Value includes the direct cost of labor, materials, equipment, transportation, taxes, and insurance associated with the applicable Allowance Item. All other costs, including design fees, Design-Builder’s overall project management and general conditions costs, overhead and Fee, are deemed to be included in the original Contract Price, and are not subject to adjustment notwithstanding the actual amount of the Allowance Item. Article 8‌
Allowance Items and Allowance Values. 18.4.1 XXXX Firm and City shall: (a) collaborate in good faith to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items; and (b) collaborate in good faith during the preparation of the design to develop Construction Documents consistent with the Allowance Values. 18.4.2 For each Allowance Item, the City Representative shall give XXXX Firm a written instruction either deleting that Allowance Item from the Agreement or requiring XXXX Firm to proceed with the relevant Allowance Item (prior to XXXX Firm proceeding with such Work). 18.4.3 If any Allowance Item is deleted from this Agreement: (a) the Target Cost of the Work and GMP will be reduced by the Allowance Value; (b) the XXXX Firm’s Fee for Construction Phase only will be reduced by a percentage of the XXXX Firm’s Fee that is equal to the dividend of the Allowance Value of the deleted Allowance Item divided by the Target Cost of the Work, as shown below: (c) Reduction in XXXX Firm’s Fee = (Allowance Value of Deleted Allowance Item ÷ Target Cost of the Work); and (d) City may engage an Other Contractor to carry out the Allowance Item or perform such Allowance Item itself. 18.4.4 All other costs and Construction Phase Fixed General Conditions Cost are deemed to be included in the original Preconstruction Phase Services Fee or GMP (as applicable) and are not subject to adjustment, regardless of the actual costs of the Allowance Item. 18.4.5 If the actual costs for an Allowance Item differs from the stated Allowance Value, the Target Cost of the Work, XXXX Firm’s Fee and GMP shall be adjusted accordingly by Change Order; however, XXXX Firm shall provide written notice of the difference between the actual cost and the Allowance Value. The amount of the Change Order shall identify the difference between actual costs incurred by XXXX Firm for the particular Allowance Item and the Allowance Value and reflect a proportional adjustment to the XXXX Firm’s Fee.
Allowance Items and Allowance Values. 5.6.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Exhibit, which is included within the GMP. 5.6.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. Nothing herein is intended in any way to constitute a guarantee by Design-Builder that the Allowance Item in question can be performed for the Allowance Value.
AutoNDA by SimpleDocs
Allowance Items and Allowance Values. 6.3.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in an Exhibit hereto. 6.3.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will continue working closely together during the preparation of the design to develop Construction Documents consistent with the Allowance Values. 6.3.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if Design-Builder is not provided written authorization to proceed on an Allowance Item by the date set forth in the Project schedule, due to no fault of Design-Builder, Design-Builder may be entitled to an adjustment of the Contract Time(s). 6.3.4 The Allowance Value for an Allowance Item includes the direct cost of labor, materials, equipment, transportation, taxes and insurance associated with the applicable Allowance Item. All other costs, including design fees, Design-Builder’s overall project management and general conditions costs, overhead and fee, are deemed to be included in the original Contract Price, and are not subject to adjustment, regardless of the actual amount of the Allowance Item.
Allowance Items and Allowance Values. 6.4.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Exhibit and are included within the GMP. 6.4.2 Design-Builder and Owner have worked together to review the Allowance Items and Allowance Values based on design information then available to determine that the Allowance Values constitute reasonable estimates for the Allowance Items. Design-Builder and Owner will 6.4.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. 6.4.4 The Allowance Value for an Allowance Item includes the direct cost of labor, materials, equipment, transportation, taxes and insurance associated with the applicable Allowance Item. All other costs, including design fees, Design-Builder’s overall project management and general conditions costs, overhead and fee, are deemed to be included in the original GMP, and are not subject to adjustment, regardless of the actual amount of the Allowance Item. 6.4.5 Whenever the actual direct costs for an Allowance Item is more than or less than the stated Allowance Value, the GMP shall be adjusted accordingly by Change Order, subject to Section
Allowance Items and Allowance Values. 6.4.1 Any and all Allowance Items, as well as their corresponding Allowance Values, are set forth in the GMP Exhibit or GMP Proposal and are included within the GMP. 6.4.2 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if Design-Builder is not provided written authorization to proceed on an Allowance Item by the date set forth in the Project schedule, due to no fault of Design-Builder, Design-Builder may be entitled to an adjustment of the Contract Time(s) and Contract Price. 6.4.3 No work shall be performed on any Allowance Item without Design-Builder first obtaining in writing advanced authorization to proceed from Owner. Owner agrees that if Design-Builder is not provided written authorization to proceed on an Allowance Item by the date set forth in the Project schedule, due to no fault of Design-Builder, Design-Builder may be entitled to an adjustment of the Contract Time(s) and Contract Price.
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!