Changes and Extensions of Time Sample Clauses

Changes and Extensions of Time. 1. Changes in the Design Services (if required) or the Construction Work under this Contract, consisting of additions, deletions, revisions or any combination thereof, may be ordered unilaterally by City without invalidating the Contract. Such changes shall be communicated by Change Order, Field Order or supplemental agreement, as applicable. Contractor shall proceed diligently with any changes, and same shall be accomplished in strict accordance with the terms and conditions as set forth in this Contract/Delivery Order.
AutoNDA by SimpleDocs
Changes and Extensions of Time. All change orders, changes requested by Design/Builder, or extensions of Contract Time occurring during construction of the Project related to actual Construction Work shall be governed by the City’s General Conditions of Construction, Volume I. All changes to the scope of Design Services or extensions of the agreed upon Design Schedule during the design process shall be made by mutual agreement of Owner and Design/Builder, and claims for an increase in design compensation due to a change in the scope of design construction Work or for an extension of time to the Design Schedule shall be made in writing within seven (7) calendar days after occurrence of the event that gives rise to the claim. All requests for additional compensation due to a change in the scope of Design Services, and all requests for an extension of time to the Design Schedule, shall include sufficient backup documentation for Owner to reasonably understand the request and the amount of time or compensation requested and to determine the merits of the request.
Changes and Extensions of Time 

Related to Changes and Extensions of Time

  • DELAYS AND EXTENSIONS OF TIME 8.3.1 If the Contractor is delayed at any time in the progress of the Work by any act or failure to act by the State or the Architect, or by any employee of either, or by any separate contractor employed by the State, or by changes ordered in the Work, fire, unusual delay in transportation, adverse weather conditions not reasonably anticipatable, unavoidable casualties, or any causes beyond the Contractor's control, or by delay authorized by the State pending alternative dispute resolution proceedings, or by any other cause which may justify the delay, then the Contract Time shall be extended by Change Order for such reasonable time as recommended by the Architect and approved by the State.

  • Extensions of Time 34.1 If at any time during performance of the Contract, the Supplier or its subcontractors should encounter conditions impeding timely delivery of the Goods or completion of Related Services pursuant to GCC Clause 13, the Supplier shall promptly notify the Procuring Entity in writing of the delay, its likely duration, and its cause. As soon as practicable after receipt of the Supplier's notice, the Procuring Entity shall evaluate the situation and may at its discretion extend the Supplier's time for performance, in which case the extension shall be ratified by the parties by amendment of the Contract.

  • Delays and Extension of Time If the Contractor is delayed at any time in the progress of providing goods and/or services by an act or neglect of the District, or by changes ordered in the work, or by labor disputes, strikes, insurrections, fire, acts of God; unusual but well documented and excusable delays in performance, or other causes beyond the Contractor’s control, or by delay authorized by the District, then the contract Term of service may be extended by a contract amendment for such reasonable time as the District and the Contractor may agree.

  • CHANGES AND AMENDMENTS A. Any alterations, additions, or deletions to the terms of this Agreement, which are required by changes in federal or state law or by regulations, are automatically incorporated without written amendment hereto, and shall become effective on the date designated by such law or by regulation.

  • Delays and Extensions The CONSULTANT agrees that no charges or claim for damages shall be made by it for any minor delays from any cause whatsoever during the progress of any portion of the Services specified in this Contract. Such delays, if any, shall be compensated for by an extension of time for such period as may be determined by the LPA subject to the CONSULTANT's approval, it being understood, however, that permitting the CONSULTANT to proceed to complete any services, or any part of them after the date to which the time of completion may have been extended, shall in no way operate as a waiver on the part of the LPA of any of its rights herein. In the event of substantial delays or extensions, or change of any kind, not caused by the CONSULTANT, which causes a material change in scope, character or complexity of work the CONSULTANT is to perform under this Contract, the LPA at its sole discretion shall determine any adjustments in compensation and in the schedule for completion of the Services. CONSULTANT must notify the LPA in writing of a material change in the work immediately after the CONSULTANT first recognizes the material change.

  • Amendments, Changes and Modifications Except as to the termination rights of both Parties as indicated in the Facilities Lease, this Site Lease may not be amended, changed, modified, altered or terminated without the written agreement of both Parties hereto.

  • Definitions and Other Provisions of General Application SECTION 101.

  • Changes by us 2.1 We may vary any details of this agreement or a direct debit request at any time by giving you at least fourteen (14) days’ written notice.

  • Extensions and Renewals All extensions or renewals of leaves shall be applied for and granted in writing.

  • Captions and Interpretations Paragraph headings in this Agreement are used solely for convenience, and shall be wholly disregarded in the construction of this Agreement. No provision of this Agreement shall be interpreted for or against a party because that party or its legal representative drafted such provision, and this Agreement shall be construed as if jointly prepared by the Parties.