Delayed Tests; Deemed Completion Sample Clauses

Delayed Tests; Deemed Completion. 6.4.1 In the event that Contractor’s conduct or completion of the Performance Tests is delayed for less than sixty (60) Days from the date on which such test would otherwise have commenced, been conducted or completed due to the failure of Company to fulfill any of its obligations under this Contract, then Company shall issue a Change Order extending the Schedule Day-for-Day for each Day of delay for those Schedule items that are affected by the Company’s failure to fulfill its obligations and compensating Contractor for its additional costs incurred as a result of such delay. 6.4.2 In the event that Contractor’s conduct or completion of the Performance Test is delayed for thirty (30) Days from the Substantial Completion Date due to a Company Default, then Company shall pay to Contractor fifty percent (50%) of the payment milestone set forth in the Milestone Payment Schedule for the Final Completion payment milestone. 6.4.3 In the event that Contractor’s conduct or completion of the Performance Test is delayed for sixty (60) Days from the Substantial Completion Date due to a Company Default, then the Facility shall then be deemed to be completed for all purposes under this Contract, Company shall pay to Contractor the remainder of the Contract Price less only the amounts withheld for Punchlist Items pursuant to Section 4.10 and Final Completion shall be deemed to have occurred. 6.4.4 Subject to Section 6.4.5, prior to the commencement of the Performance Tests or, if the Performances Tests have been delayed as provided in this Section 6.4, if and when the events that prevented the commencement of the Performance Tests cease, the Parties shall inspect the Facility and: (a) if geothermal fluid and or cooling water have been run through any part of the Facility or the Facility has otherwise been operated by Company, for a cumulative period of more than two (2) weeks, or based on shortfall in the test results, Contractor may require that the parties jointly open and inspect the Facility prior to the Performance Tests being carried out or prior to repeating of the test as the case may be; and (b) if the Facility is in good, clean and as-installed condition, Contractor will proceed within a reasonable period of time to conduct the Performance Tests not previously completed; or (c) if the Facility is not in good, clean and as-installed condition, prior to the conduct of the Performance Tests, Company will within a reasonable period of time clean and repair the Fac...
AutoNDA by SimpleDocs
Delayed Tests; Deemed Completion. 6.4.1 In the event that Contractor's conduct or completion of any test is delayed for less than _________ (___) Days from the date on which such test would otherwise have commenced, been conducted or completed due to the failure of Company to fulfill any of its obligations under this Contract, then the Schedule shall be extended Day-for-Day for each Day of delay (without need of a Change Order). 6.4.2 In the event that Contractor's conduct or completion of the Performance Test is delayed for ___________ (___) Days or more from the date on which such test would otherwise have commenced, been conducted or completed due to a Company Default, then, as of the date on which such testing was scheduled to be completed, the Facility will then be deemed to be completed for all purposes under this Contract including, without limitation, satisfaction of the Performance Guarantee, and Company shall pay to Contractor the remainder of the Contract Price less only the cost savings of Contractor (if any) associated with it not performing such Performance Test.
Delayed Tests; Deemed Completion. 6.4.1 In the event that Contractor's conduct or completion of any test is delayed from the date on which such test would otherwise have commenced, been conducted or completed due to an Uncontrollable Company Default then the Schedule shall be extended Day-for-Day for each Day of delay (without need of a Change Order). 6.4.2 In the event that Contractor's conduct or completion of the Performance Test is delayed for ninety (90) Days or more from the date on which such test would otherwise have commenced, been conducted or completed due to an Uncontrollable Company Default, then, as of the date on which such testing was scheduled to be completed, the Facility will then be deemed to be completed for all purposes under this Contract including, without limitation, satisfaction of the Performance Guarantee, and Company shall pay to Contractor the remainder of the Contract Price less only the cost savings of Contractor (if any) associated with it not performing such Performance Test. In the event that the circumstances which prevented the conduct or completion of the Performance Test have ceased to exist, Contractor will assist the Company to perform such test.

Related to Delayed Tests; Deemed Completion

  • Final Completion The full and final completion of all Work in accordance with the Contract Documents.

  • Project Completion The Contractor agrees to schedule a final job walk with the County. If required, the County will prepare a list of incomplete items, the “Punch List”. The Contractor agrees to complete the “Punch List” corrections and schedule a final project completion job walk. The County will sign the “Punch List” as completed when determined, the project is finished. The Contractor agrees to submit the following along with its final payment request:

  • Payment for Material Completion The Contractor may request payment of the remaining contract balance, including retainage, less amounts credited the Owner or incurred as liquidated damages, and less amounts withheld for the Punchlist by reason of Minor Items or Permitted Incomplete Work (See Paragraph 6.5.3.2). Payment for Material Completion shall be made by a check payable jointly to the Contractor and Surety and shall be mailed to the Surety.

  • Substantial Completion 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which has been accepted in writing to by the State, is substantially complete as defined in Subparagraph

  • Random Testing Notwithstanding any provisions of the Collective Agreement or any special agreements appended thereto, section 4.6 of the Canadian Model will not be applied by agreement. If applied to a worker dispatched by the Union, it will be applied or deemed to be applied unilaterally by the Employer. The Union retains the right to grieve the legality of any imposition of random testing in accordance with the Grievance Procedure set out in this Collective Agreement.

  • Stability Testing Patheon may be requested to conduct stability testing on the Products in accordance with the protocols set out in the Specifications for the separate fees and during the time periods set out in Schedule C to a Product Agreement. Patheon will not make any changes to these testing protocols without prior written approval from Client. If a confirmed stability test failure occurs, Patheon will notify Client within one Business Day, after which Patheon and Client will jointly determine the proceedings and methods to be undertaken to investigate the cause of the failure, including which party will bear the cost of the investigation. Patheon will not be liable for these costs unless it has failed to perform the Manufacturing Services in accordance with the Specifications, cGMPs, and Applicable Laws. Patheon will give Client ail stability test data and results at Client’s request.

  • Project Completion Date It is agreed between the Parties that the Project Completion Date is <END DATE, YEAR>. If the Project is not completed by such date then, subject to an amendment agreed to between the Parties, Alberta Innovates may elect to terminate this Investment Agreement. In such event, Alberta Innovates will notify the Applicant of its decision to terminate as soon as reasonably practical and shall advise the Applicant of the effective date of termination. Alberta Innovates will have no liability or obligation to reimburse the Applicant for any Project Costs incurred after the effective date of termination and may require the Applicant to return any portions of the Investment which were spent on Ineligible Expenses. Additionally, any portion of the Investment not used and accounted for in accordance with this Agreement as of the Project Completion Date or earlier termination is repayable by the Applicant to AI at AI’s request.

  • Substantial Completion Date Substantial Completion of the Work as defined in Article 6.1.2 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by July 31, 2022.

  • Follow-up Testing An employee shall submit to unscheduled follow-up drug and/or alcohol testing if, within the previous 24-month period, the employee voluntarily disclosed drug or alcohol problems, entered into or completed a rehabilitation program for drug or alcohol abuse, failed or refused a preappointment drug test, or was disciplined for violating the provisions of this Agreement and Employer work rules. The Employer may require an employee who is subject to follow-up testing to submit to no more than six unscheduled drug or alcohol tests within any 12 month period.

  • Final Completion Date Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management shall be achieved by October 31, 2024.

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!