ESTIMATED COSTS OF INTERCONNECTION FACILITIES Sample Clauses

ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below.
AutoNDA by SimpleDocs
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below. As described in the Facilities Study for the Small Generating Facility, the estimates provided herein: SERVICE AGREEMENT NO. 2638 Assume: • 5X10 construction work week; • outages are available; • all major material is delivered to site (i.e., no costs are included for transport from storage); • existing equipment to remain is functional. Exclude (as applicable): • discussions and negotiations of issued interconnection study; • application fees; • applicable surcharges; • overall project sales tax; • property taxes; • line switching; • property/easement acquisitions; • access roads and associated matting; • future operation and maintenance costs; • recurring monthly communications circuits’ charges, if any, responsible by the Interconnection Customer to the communications utility; • soil testing; • adverse field conditions such as rock, water, weather, and Interconnection Customer electrical equipment obstructions; • environmental mitigation; • extended engineering to minimize outage time or Connecting Transmission Owner’s public duty to serve; • extended craft labor hours, to minimize outage and/or construction time; • property transactions reviews associated with Interconnection Customer’s requests to occupy the Connecting Transmission Owner’s rights-of-way and/or fee owned property; or • any required permits. Cost adders estimated for overtime will be based on 1.5 and 2 times labor rates if required for work beyond normal business hours. Meals and equipment are also extra costs incurred for overtime labor.
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below. As described in the Facilities Study for the Small Generating Facility, the estimates provided herein: Assume: • 5X10 construction work week; • outages are available; • all major material is delivered to site (i.e., no costs are included for transport from storage); and • existing equipment to remain is functional. Exclude (as applicable): • discussions and negotiations of issued interconnection study; • application fees; • applicable surcharges; • overall project sales tax; • property taxes; • line switching; • property/easement acquisitions; • access roads and associated matting; • future operation and maintenance costs; • recurring monthly communications circuits’ charges, if any, responsible by the Interconnection Customer to the communications utility; • soil testing; • adverse field conditions such as rock, water, weather, and Interconnection Customer electrical equipment obstructions; • environmental mitigation; • extended engineering to minimize outage time or Connecting Transmission Owner’s public duty to serve; • extended craft labor hours, to minimize outage and/or construction time; or • any required permits. Cost adders estimated for overtime will be based on 1.5 and 2 times labor rates if required for work beyond normal business hours. Meals and equipment are also extra costs incurred for overtime labor.
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. Description Estimated Costs
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. SERVICE AGREEMENT NO. 2591 The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below. As described in the Facilities Study for the Small Generating Facility, the estimates provided herein: Assume: • 5X10 construction work week; • outages are available; • permitting is not required; and • existing equipment to remain is functional. Exclude (as applicable): • discussions and negotiations of issued interconnection study; • application fees; • applicable surcharges;
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below. As described in the Facilities Study for the Small Generating Facility, the estimates provided herein: Assume: • 5X10 construction work week; • outages are available; • permitting is not required; and • existing equipment to remain is functional. Exclude (as applicable): • discussions and negotiations of issued interconnection study, • application fees, • applicable surcharges, • overall project sales tax, • property taxes, • line switching, • property/easement acquisitions, • future operation and maintenance costs, • recurring monthly communications circuits’ charges, if any, responsible by the Interconnection Customer to the communications utility, • soil testing, • adverse field conditions such as rock, water, weather, and Interconnection Customer electrical equipment obstructions, • environmental mitigation, • extended engineering to minimize outage time or Connecting Transmission Owner’s public duty to serve, • extended craft labor hours, to minimize outage and/or construction time, or • any required permits. Cost adders estimated for overtime will be based on 1.5 and 2 times labor rates if required for work beyond normal business hours. Meals and equipment are also extra costs incurred for overtime labor.
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. No new facilities are expected to be constructed by the Connecting Transmission Owner. Customer construction document review, site review and witness testing of customer equipment are the only activities required of the Connecting Transmission Owner. This is estimated to be a cost of $0 to the Interconnection Customer and will be reconciled to the actual costs at project completion. A refund or further invoice will be generated based on the actual costs. NYISO Agreements --> Service Agreements --> SGIA between NMPC and Bayside Solar LLC In-Service Date: August 16, 2022 Critical milestones and responsibility as agreed to by the Parties: (1) Building Permit - January 6, 2022 (2) Construction NTP - May 18, 2022 (3) Main Equipment Delivery - June 13, 2022 (4) Meter installation - July 10, 2022 (5) Mechanical Completion - August 5, 2022 (6) Energization/utility testing - August 12, 2022 (7) Complete Installation of RTU - April 1, 2022 (8) Issue permission to operate - August 19, 2022 (9) Project closeout/reconciliation: November 18, 2022 Responsible Party Interconnection Customer Interconnection Customer Interconnection Customer Interconnection Customer Interconnection Customer Connecting Transmission Owner Connecting Transmission Owner Connecting Transmission Owner Connecting Transmission Owner The Connecting Transmission Owner shall also provide requirements that must be met by the Interconnection Customer prior to initiating parallel operation with the New York State Transmission System or the Distribution System. (a) The Interconnection Customer must comply with all applicable NYISO tariffs and procedures, as amended from time to time. (b) To the extent not inconsistent with the terms of this Agreement, the NYISO OATT, or applicable NYISO procedures, Interconnection Customer must comply with Connecting Transmission Owner’s operating instructions and requirements, which requirements shall include the dedicated data circuits, including system protection circuits, to be maintained by Interconnection Customer in accordance with Article 1.5 of this Agreement. Interconnection Customer must also comply with the applicable requirements as set out in the Connecting Transmission Owner’s ESBs, which have been identified and provided to the Interconnection Customer as amended from time to time to the extent not inconsistent with the terms of this Agreement or applicable NYISO tariffs and procedures. Upon the Connecting Transmission Owner’s notice to the Interconnection...
AutoNDA by SimpleDocs
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. The total estimated costs (+30%/-15%) of the work associated with the Interconnection Facilities required for the interconnection of the Small Generating Facility are presented in the table below. Engineering review and compliance verification of the ICIF, including all required drawings and equipment specifications reviews, relay settings, construction and testing assistance by engineering, field verification, and witness testing Engineering, design, construction, testing and commissioning for revenue metering and EMS-RTU at Collector Station and line tap. Contingency $465,200 SERVICE AGREEMENT NO. 2600 As described in the Facilities Study for the Small Generating Facility, the estimates provided herein: Assume: • 5X10 construction work week; • outages are available; • all major material is delivered to site and no costs are included for transport form storage; and • existing equipment to remain is functional. Exclude (as applicable): • discussions and negotiations of issued interconnection study; • application fees; • applicable surcharges; • overall project sales tax; • property taxes; • line switching; • property/easement acquisitions; • access roads and associated matting, • future operation and maintenance costs; • recurring monthly communications circuits’ charges, if any, responsible by the Interconnection Customer to the communications utility; • soil testing; • adverse field conditions such as rock, water, weather, and Interconnection Customer electrical equipment obstructions; • environmental mitigation; • extended engineering to minimize outage time or Connecting Transmission Owner’s public duty to serve; • extended craft labor hours, to minimize outage and/or construction time; or SERVICE AGREEMENT NO. 2600 • any required permits.
ESTIMATED COSTS OF INTERCONNECTION FACILITIES. Description Estimated Costs Connecting Transmission Owner’s $635,000 Interconnection Facilities