Force Account Change Orders Sample Clauses

Force Account Change Orders. A Force Account Change Order may be used in the event (i) CM/GC and Owner cannot agree on the Change Order Sum for a Lump Sum Change Order, (ii) costs associated with a Change Order cannot be reasonably determined prior to beginning the Change Order Work, or (iii) the Owner and CM/GC have agreed to Unit Prices for the Work but cannot determine the number of Units involved in the Change Order (“Unit Price Change Order”).
AutoNDA by SimpleDocs
Force Account Change Orders. The District may at its discretion issue a Force Account Change Order whenever the parties cannot agree to a Lump Sum Change Order or the District concludes that a Force Account Change Order is advisable. The Force Account Change Order shall instruct the DB Contractor to perform the Work, indicating expressly the intention to treat the items as changes in the Work and setting forth the kind, character, and limits of the Work as far as they can be ascertained; the terms under which changes to the Contract Price will be calculated; and the estimated total change in the Contract Price anticipated there under. Upon final calculation of the allowable costs, the District shall issue a modified Change Order setting forth the final adjustment to the Contract Price. The costs and additional amounts allowed in Section 15 (and no others) shall be used for calculating the change in the Contract Price. No direct compensation will be allowed for other miscellaneous costs for which no specific allowance is provided in Section 15.5. The District and the DB Contractor may agree to negotiate unit prices for a Force Account Change Order. Measurement of any unit-priced quantities will be as specified in the Change Order. Unit prices shall be deemed to include all costs for labor, material, overhead, and profit; and shall not be subject to change regardless of any change in the estimated quantities. Upon final determination of the quantities, the District will issue a modified Change Order setting forth the final adjustment to the Contract Price.
Force Account Change Orders. TxDOT may at its discretion issue a Force Account Change Order whenever TxDOT determines that it is advisable. The Force Account Change Order shall instruct DB Contractor to perform the additional (or modified) Maintenance Services, indicate expressly the intention to treat the items as changes in the Maintenance Services, set forth the kind, character, and limits of the Maintenance Services as far as they can be ascertained, state the terms under which changes to the Maintenance Price will be determined and state a not-to-exceed (NTE) total change in the Maintenance Price. DB Contractor will maintain its records as required by Section 4.5.12 and submit daily records in accordance with Section 4.5.12.2.1. Upon final determination of the allowable costs and subject to Section 4.5.12.2.4, TxDOT shall issue a modified Change Order setting forth the final adjustment to the Maintenance Price, which shall not exceed the stated NTE amount.
Force Account Change Orders. TxDOT may at its discretion issue a Force Account Change Order whenever TxDOT determines that it is advisable. The Force Account Change Order shall instruct DB Contractor to perform the additional (or modified) Maintenance Services, indicate expressly the intention to treat the items as changes in the Maintenance Services, set forth the kind, character, and limits of the Maintenance Services as far as they can be ascertained, state the terms under which changes to the Maintenance Price will be determined and state a not-to-exceed (NTE) total change in the Maintenance Price. DB Contractor will maintain its records as required by Section 4.5.12 and submit daily records in accordance with Section 4.5.12.2.1. If DB Contractor determines that the costs of the Maintenance Services authorized pursuant to a Force Account Change Order will exceed the stated NTE, DB Contractor shall notify TxDOT of the additional costs required to complete such Work and TxDOT may approve an increase to the stated NTE. DB Contractor is not obligated to perform Work authorized pursuant to a Unit-priced Change Order once the approved NTE (as it may be adjusted) has been reached. Upon final determination of the allowable costs and subject to Section 4.5.12.2.4, TxDOT shall issue a modified Change Order setting forth the final adjustment to the Maintenance Price, which shall not exceed the stated NTE amount (as such amount may be adjusted as described herein).
Force Account Change Orders. TxDOT may at its discretion issue a Force Account Change Order whenever TxDOT determines that it is advisable. The Force Account Change Order shall instruct DB Contractor to perform the additional (or modified) Maintenance Services, indicate expressly the intention to treat the items as changes in the Maintenance Services, set forth the kind, character, and limits of the DocuSign Envelope ID: 69FAD993-F221-4BEC-895E-9675AB93CDF8
Force Account Change Orders. VPRA may issue a Force Account Change Order if VPRA determines that doing so is beneficial, including if VPRA and Contractor are unable to negotiate a price for Extra Work Costs in a Change Order as provided in Section 14.9 of these General Terms and Conditions. VPRA may also issue a Directive Letter with pricing determined on a Force Account basis.
Force Account Change Orders. TxDOT may at its discretion issue a Force Account Change Order whenever TxDOT determines that it is advisable. The Force Account Change Order shall instruct DB Contractor to perform the additional (or modified) Maintenance Services, indicate expressly the intention to treat the items as changes in the Maintenance Services, set forth the kind, character, and limits of the Maintenance Services as far as they can be ascertained, state the terms under which changes to the Maintenance Price will be determined and state a not-to-exceed (NTE) total change in the Maintenance Price. DB Contractor will maintain its records as required by Section
AutoNDA by SimpleDocs

Related to Force Account Change Orders

  • Contract Changes Changes may not be made in the terms and conditions of this contract without the agreement and written permission of the Director of Residence Life or the Director’s designee.

  • Change Orders Any alteration or deviation from the Services mentioned or any other contractual specifications that result in a revision of this Agreement shall be executed and attached to this Agreement as a change order (“Change Order”).

  • ADDITIONAL SPECIAL CONTRACT CONDITIONS A. Special Contract Conditions revisions: the corresponding subsections of the Special Contract Conditions referenced below are replaced in their entirety with the following:

  • Checking Accounts The Credit Union may refuse any check or other item drawn against your account or used to withdraw funds from your account if it is not on a form approved by us. We also reserve the right to refuse any check or other item drawn against your account or used to withdraw funds from your account if made in a manner not specifically authorized for your account, if made more frequently or in a greater number than specifically permitted for your account, or if made in an amount less than the minimum withdrawal or transfer specifically permitted for your account. If we accept a check or other item not on a form approved by us, you will be responsible for any loss by us in handling the item. We may pay checks or other items drawn upon your account in any order determined by us, even if paying a particular check or item results in an insufficient balance in your account to pay one or more other items that otherwise could have been paid out of your account. Because of the nature of the Credit Union check program, neither the Credit Union nor any other processing entities shall be responsible for the authenticity of the checks with regard to the signature or alterations; and checks, when presented, shall be paid without verification. We may disregard all information on or any writing or memorandum attached to any check or item except for your signature, the amount and the information that is magnetically encoded. You agree that we do not fail to use ordinary care because our procedures do not provide for sight examination. You will notify us immediately if you learn or have reason to know that any of your checks have been lost or stolen. If you are negligent in safeguarding your checks or if there is a processing problem due to your use of a check printer we do not approve, we will not have any liability or responsibility for any losses you incur as a result if we act in good faith pursuant to standard commercial practices.