Issuance of Stop Work Order Sample Clauses

Issuance of Stop Work Order. The Exchange Project Director may, at any time, by written stop work order to Contractor, require Contractor to stop all or any part of the work called for by this Agreement for a period of up to 90 Days after the stop work order is delivered to Contractor, and for any further period to which the parties may agree. The stop work order shall be specifically identified as such and shall indicate it is issued under this Section. Upon receipt of the stop work order, Contractor shall immediately comply with its terms and take all steps necessary and feasible to minimize the incurrence of costs allocable to the work covered by the stop work order during the period of work stoppage. The Work Plan shall be delayed on a Day-for-Day basis if the Exchange Project Director has issued a stop work order to Contractor and such stop work order is causing delays in completing Services in accordance with the Work Plan. The Work Plan may be delayed in addition to the Day-for-Day delays provided in the preceding sentence upon approval by the Exchange Project Director. Within a period of 90 Days after a stop work order is delivered to Contractor, or within any 11.5.1.1 Cancel the stop work order; or 11.5.1.2 Terminate the work covered by the stop work order as provided for in Section 17.1.
AutoNDA by SimpleDocs
Issuance of Stop Work Order. The Contractor will be issued an immediate stop-work order when the District is notified of cancellation of any insurance required under this Contract. Such stop order shall continue until District is notified and provided proof of new or reinstated insurance. Neither Contractor nor the subcontractor shall be entitled to any increase in Contract performance time, or to any adjustment in Contract price due to the effects of such a stop-work order.
Issuance of Stop Work Order. The Office may, at any time, by written stop work order to the Contractor, require that the Contractor stop all, or any part, of the work called for by this Contract for a period of up to ninety (90) calendar days after the stop work order is delivered to the Contractor, and for any further period to which the parties may agree. The stop work order shall be specifically identified as such and shall indicate that it is issued under this section 19. Upon receipt of the stop work order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the stop work order during the period of work stoppage. Within the period of the stop work order, the Office shall either: (a) cancel the stop work order; or (b) terminate the work covered by the stop work order as provided in section 17.
Issuance of Stop Work Order. The State may, at any time, by written stop work order to Contractor, require that Contractor stop all, or any part, of the work called for by the Contract for a period of up to ninety (90) calendar days after the stop work order is delivered to Contractor, and for any further period to which the parties may agree. The stop work order shall be specifically identified as such and shall indicate that it is issued under this Section 22. Upon receipt of the stop work order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the stop work order during the period of work stoppage. Within the period of the stop work order, the State shall either: (a) cancel the stop work order; or (b) terminate the work covered by the stop work order as provided in Section 19 of the Contract.
Issuance of Stop Work Order. ‌ The State Project Director may, at any time, by written stop work order to the Contractor, require the Contractor to stop all or any part of the work called for by this Contract for a period of up to ninety (90) Days after the stop work order is delivered to the Contractor, and for any further period to which the parties may agree. The stop work order shall be specifically identified as such and shall indicate it is issued under this Contract Section. Upon receipt of the stop work order, the Contractor shall immediately comply with the stop work order terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the stop work order during the period of work stoppage. Any applicable Project Workplan shall be delayed on a day- for-day basis if the State Project Director has issued a stop work order to the Contractor and such stop work order is causing delays in completing Services in accordance with the Project Workplan(s). The Project Workplan(s) may be delayed in addition to the day- for-day delays provided in the preceding sentence upon approval by the State Project Director. Within a period of ninety (90) Days after a stop work order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the State Project Director shall either: a. Cancel the stop work order; or b. Terminate the work covered by the stop work order as provided for in Section 19.1.1, Section 19.1.2, or Section 19.6 of this Contract.

Related to Issuance of Stop Work Order

  • Stop Work Order (a) NYSERDA may at any time, by written Order to the Contractor, require the Contractor to stop all or any part of the Work called for by this Agreement for a period of up to ninety (90) days after the Stop Work Order is delivered to the Contractor, and for any further period to which the parties may agree. Any such order shall be specifically identified as a Stop Work Order issued pursuant to this Section. Upon receipt of such an Order, the Contractor shall forthwith comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Work covered by the Order during the period of work stoppage consistent with public health and safety. Within a period of ninety (90) days after a Stop Work Order is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, NYSERDA shall either: (i) by written notice to the Contractor, cancel the Stop Work Order, which shall be effective as provided in such cancellation notice, or if not specified therein, upon receipt by the Contractor, or (ii) terminate the Work covered by such order as provided in the Termination Section of this Agreement. (b) If a Stop Work Order issued under this Section is cancelled or the period of the Order or any extension thereof expires, the Contractor shall resume Work. An equitable adjustment shall be made in the delivery schedule, the estimated cost, the fee, if any, or a combination thereof, and in any other provisions of the Agreement that may be affected, and the Agreement shall be modified in writing accordingly, if: (i) the Stop Work Order results in an increase in the time required for, or in the Contractor’s cost properly allocable to, the performance of any part of this Agreement, and (ii) the Contractor asserts a claim for such adjustments within 30 days after the end of the period of Work stoppage; provided that, if NYSERDA decides the facts justify such action, NYSERDA may receive and act upon any such claim asserted at any time prior to final payment under this Agreement. (c) If a Stop Work Order is not cancelled and the Work covered by such Order is terminated, the reasonable costs resulting from the Stop Work Order shall be allowed by equitable adjustment or otherwise. (d) Notwithstanding the provisions of this Section 12.01, the maximum amount payable by NYSERDA to the Contractor pursuant to this Section 12.01 shall not be increased or deemed to be increased except by specific written amendment hereto.

  • Stop Work Orders A. The JBE may, at any time, by Notice to Contractor, require Contractor to stop all or any part of the Services for a period up to ninety (90) days after the Notice is delivered to Contractor, and for any further period to which the parties may agree (“Stop Work Order”). The Stop Work Order shall be specifically identified as such and shall indicate it is issued under this provision. Upon receipt of the Stop Work Order, Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the Services covered by the Stop Work Order during the period of stoppage. Within ninety (90) days after a Stop Work Order is delivered to Contractor, or within any extension of that period to which the parties shall have agreed, the JBE shall either (i) cancel the Stop Work Order; or (ii) terminate the Services covered by the Stop Work Order as provided for in this Agreement. B. If a Stop Work Order issued under this provision is canceled or the period of the Stop Work Order or any extension thereof expires, Contractor shall resume the performance of Services. The JBE shall make an equitable adjustment in the delivery schedule, the Contract Amount, or both, and the Agreement shall be modified, in writing, accordingly, if: i. The Stop Work Order results in an increase in the time required for, or in Contractor’s cost properly allocable to the performance of any part of this Agreement; and ii. Contractor requests an equitable adjustment within thirty (30) days after the end of the period of stoppage; however, if the JBE decides the facts justify the action, the JBE may receive and act upon a proposal submitted at any time before final payment under this Agreement. C. The JBE shall not be liable to Contractor for loss of profits because of a Stop Work Order issued under this provision.

  • CHANGE ORDERS AND AMENDMENTS A. Any alterations, additions, or deletions to the terms of this Agreement, which are required by changes in federal or state law or by regulations, are automatically incorporated without written amendment hereto, and shall become effective on the date designated by such law or by regulation. B. To ensure the legal and effective performance of this Agreement, both parties agree that any amendment that affects the performance under this Agreement must be mutually agreed upon and that all such amendments must be in writing. After a period of no less than 30 days subsequent to written notice, unless sooner implementation is required by law, such amendments shall have the effect of qualifying the terms of this Agreement and shall be binding upon the parties as if written herein. C. Customers have the right to issue a change order to any purchase orders issued to the Contractor for the purposes of clarification or inclusion of additional specifications, qualifications, conditions, etc. The change order must be in writing and agreed upon by Contractor and the Customer agency prior to issuance of any Change Order. A copy of the Change Order must be provided by the Contractor to, and acknowledged by, H-GAC.