Possession of the Site Sample Clauses

Possession of the Site. 21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the relevant activities and this will be Compensation Event.
AutoNDA by SimpleDocs
Possession of the Site. 3.5.1 The Department shall give possession of the site to the Contractor. If possession of a part site is given, the Department will ensure that the part site so handed over is amenable to carry out the work at site by the Contractor. 3.5.2 The Contractor shall provide the Engineer-in-Charge and any person authorized by the Engineer- in-Charge, access to the site and to any place where work in connection with the Contract is being carried out or is intended to be carried out.
Possession of the Site. 10.4.1. In order to handover the possession of the Site pursuant to Clause 4.2.1, the authorised representatives (as given in recitals) of the ULB (and the Concessionaire shall, on mutually agreed date and time, inspect the Site and prepare a memorandum containing an inventory of the Site including the vacant and unencumbered land, building, structures, road network, trees, pipelines and any other immovable property on or attached to the Site. Such memorandum shall have appended thereto an appendix (the ―Appendix‖) specifying in reasonable detail those parts of the Site to which vacant and unencumbered possession of the Site has not been granted to the Concessionaire. Signing of the memorandum, as above, by the authorised representatives of the Parties shall, subject to the provision of Clause 10.1, be deemed to constitute a valid handover of possession of the Site to the Concessionaire for free and unrestricted use and development of the vacant and unencumbered Site during the Concession Period under and in accordance with the provisions of this Agreement and for no other purpose whatsoever. For avoidance of doubt, it is agreed that vacant and unencumbered possession of the Site in respect of those parts of the Site which have been set forth in the Appendix shall be deemed to have been granted to the Concessionaire upon vacant handover of possession being provided 10.4.2. Without prejudice to the provision of Clause 10.4.1, the Parties hereto agree that on or prior to the Appointed date, the ULB has handed over vacant possession of land to the Concessionaire such that Appendix shall not include more than 20% (twenty percent) of the total area of the Site required to be handed over in accordance with Schedule 9. 10.4.3. On and after signing the memorandum referred to in Clause 10.4.1, and until the Transfer Date, the Concessionaire shall maintain a round-the-clock xxxxx over the Site and shall ensure that no encroachment thereon takes place, and in the event of any encroachment or occupation on any part thereof, the Concessionaireshallreportsuchencroachmentoroccupa tionforthwithtothe ULB and undertake its removal at its cost and expense. 10.4.4. The ULB to provide support on best effort basis to handover, no later than 90 (ninety) days from the date of signing the Concession Agreement, the possession of the land included in the Appendix, and in the event of delayfor reason other than Force Majeure or breach of this Agreement by the Concessionaire, it shall...
Possession of the Site. 21.1 The Employer shall give possession of part of the site mentioned in the current milestone. If possession of a part is not given by the date, Contractor is eligible for extension of time for the corresponding period.
Possession of the Site. The park owner agrees: (a) to make sure the site is vacant so the occupant can move in on the date agreed; and (b) that there is no legal reason that the park owner knows about, or should know about when signing this agreement, why the site cannot be used as the site of a residence for the term of this agreement.
Possession of the Site. 20.1 The Procuring Entity shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by thedate stated in the SCC, the Procuring Entity shall be deemed to have delayedthe start of the relevant activities, and this shall be a Compensation Event.
Possession of the Site. (Clause 21)
AutoNDA by SimpleDocs
Possession of the Site. 13.1 The Procuring Entity shall give possession of the Site or part(s) of the Site, to the Contractor on the date(s) stated in the PCC. If possession of a part of the Site is not given by the date stated in the PCC, the Procuring Entity will be deemed to have delayed the start of the relevant activities, and this will be a Compensation Event as stated under GCC Sub Clause 67.1(a).
Possession of the Site. 15.1 The Authority shall handover the Site to the Operator free from encumbrances to carry out Works. The Operator may have to accommodate/ adjust with other Operator/s if required by Empowered Committee. 15.2 Upon completion of Works and as per condition of Agreement, the Operator shall handover the Site free from all encumbrances.
Possession of the Site. 20.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is not given by the date stated in the PCC, the Employer shall be deemed to have delayed the start of the relevant activities, and this shall be a Compensation Event.