Project Deadlines Sample Clauses
POPULAR SAMPLE Copied 2 times
Project Deadlines. The Recipient will:
(a) commence the Project by the Project Start Deadline;
(b) award the Project construction contracts that account for the bulk of the construction work by the Construction Contract Award Deadline; and
(c) complete the Project by the Project Completion Deadline.
Project Deadlines. It’s critical that both Client and WRAL Digital meet deadlines established under this Agreement, as such the following applies:
a. If Client does not provide required feedback within thirty (30 days) of WRAL Digital’s request, WRAL Digital reserves the right to require an Agreement addendum that will include both new timeframes for the Deliverables, and related additional expenses Client will be charged as a result of the change in timeframe (an “Addendum”).
b. If Client requires work outside of what’s detailed in the SO, an Addendum will be required.
c. Both parties must agree to the terms of the Addendum, and acknowledge that it is limited in scope, only applying to the terms it details. All other terms of the Agreement remain in effect.
d. WRAL Digital will consider any request for an Addendum, but approval is at the sole discretion of WRAL Digital.
Project Deadlines. It is understood and agreed that this Lease, all obligations under this Lease, and the timing thereof are of critical importance to Landlord. To this end, ▇▇▇▇▇▇ agrees to use commercially reasonable efforts to achieve the following results by the critical dates stated below (each a “Project Deadline”):
(a) Approval of the architectural plans and specifications by Landlord and Tenant (75 days from the Effective Date);
(b) Approval by the City of Lincolnton Planning Department (120 days from the Effective Date);
(c) Tenant secures all land development permits, construction permits, and any site plan approval and/or permits required by North Carolina Department of Transportation for curb cuts (150 days from the Effective Date);
(d) Tenant provides construction schedule to Landlord (120 days from the Effective Date).
(e) Tenant commences construction of the Building (150 days from the Effective Date);
(f) Tenant achieves substantial completion of the Building (300 days from the Effective Date); and
(g) Tenant secures a certificate of occupancy for the Building (320 days from the Effective Date). In the event Tenant has not provided Landlord with satisfactory evidence that it has timely met each Project Deadline as stated above, Landlord may demand compliance with the Project Deadline by written notice to Tenant (each a “Compliance Demand”). In the event Tenant has not met the Project Deadline within ten (10) days of the Compliance Demand, Landlord may terminate this Lease upon written notice to Tenant not later than thirty (30) days after the date of the Compliance Demand.
Project Deadlines. It’s critical that both Client and Capitol B meet deadlines established under
a. If Client does not provide required feedback within thirty (30 days) of Capitol B’s request, Capitol B reserves the right to require an Agreement addendum that will include both new timeframes for the Deliverables, and related additional expenses Client will be charged as a result of the change in timeframe (an “Addendum”).
b. If Client requires work outside of what’s detailed in the SOW, an Addendum will be required.
c. Both parties must agree to the terms of the Addendum, and acknowledge that it is limited in scope, only applying to the terms it details. All other terms of the Agreement remain in effect.
d. Capitol B will consider any request for an Addendum, but approval is at the sole discretion of Capitol B.
Project Deadlines. The Project Schedule attached as Exhibit E-1 to the First Amendment is deleted and replaced with Schedule 1 hereto. The Project Schedule includes, without limitation, an extension of the Commerce Project Substantial Completion date to July 15, 2022. The last sentence of Section 1.3 of the Development Agreement is hereby deleted and replaced with the following: On or before July 15, 2022 (the date that Developer is required to Substantially Complete the Commerce Project), Developer shall cause the following to occur (collectively, “Common Facilities Completion”): (i) construction of the Parking Garage to be completed in accordance with the 8027 Plans and in accordance with the Plans and Specifications, (ii) construction of the Terrace Garden, including without limitation the Fitness Center, to be completed in accordance with the 8027 Plans and in accordance with the Plans and Specifications, and (iii) the Parking Garage, Terrace Garden and Fitness Center (which may be referred to collectively as the “Common Facilities”) to be open to and fully operational. The date on which Substantial Completion of the Commerce Project and Common Facilities Completion have both occurred may be referred to as the “Opening Date”.
Project Deadlines. Project deadlines will be agreed at the beginning of each month and confirmed in writing (in ▇▇▇▇▇▇) between the business and the contractor. Project management will be conducted in ▇▇▇▇▇▇: the business will set up boards with key milestones for the contractor, and the contractor is responsible for updating the ▇▇▇▇▇▇ board with progress. Failure of the contractor to deliver work will result in the business not paying for the time taken for that specific task.